T2S Project status and way forward IT NUG Milan, 14th July 2015 1. Project status 2. T2S defects status 3. MT Community Testing status London Stock Exchange Group 15 July 2015 Page 2 1. Project status London Stock Exchange Group Page 3 Report from T2S CSG - 2nd July • Approved plan for MT go-live on 31 August: 1) MIG2 restarted to operate with Live Timing on 06/07 and will continue until 14/08, after that will return to Synchronised Standard day until end of testing period (21/08) 2) Migration weekend Dress reharsal is planned for 01 and 02 August, preceded by the usual preparation activities. 3) T2S regular software releases will continue until 24/07, after this date, only prod defects will be deployed or blocking issues identified in the meantime as part of the Community or Business Day test. 4) Defined a list of defects (baseline) to be solved for MT go-live • Works of the ad-hoc task force still on-going to evaluate impacts on other waves London Stock Exchange Group Page 4 Plan for MT go-live on 31 August London Stock Exchange Group Page 5 Report from ABI/ASSOSIM meeting – 3rd July • MWEDR on 1-2 August: 1) Agreed participation of intermediaries (communication already sent) 2) No possibility to copy production data in the test environment (clarified by 4CB) but committment by alll actors involved to re-create the same conditions of migration weekend 3) Analysis on-going with 4CB to simulate a business day on Monday (volumes to be considered • Descoping of functionalities 1) Confirmed descoping of CAoF standards management for OTC tx and cash forecasting 2) Organised a meeting on 7 July to define operational management of CAoF on pending tx 3) MT to send market notice to clarify descoping areas and that no detection will be executed for OTC tx from go-live to date tbd (expected by end of week) • Portfolio transfer 1) Confirmed management of 3 decimals for Deal Price 2) MT to send list of ICP using RNI message switching (for the issue on using ‘/’ as separator) 3) Workaround proposed by participants (query to detect PORT with 5 decimals and report to ICPs) not feasible because of operational burden • Hold/Release 1) Meeting with interested parties already planned (Wednesday, 15 July) to agree on the solution • Matching ICP/DCP 1) Confirmed adoption of workaround for go-live (DCP to set Party 2 either blank or with a unilateral BIC code assigned to Client) 2) MT to verify DCPs static data set-up and contact bilaterally, if required London Stock Exchange Group Page 6 Report from PT-TUG Settlement Optimisation - 7 July Agreed actions Outcome 1 Il PBI risulta come hotfix con data risoluzione 24/7 Problema semt.027 (PBI156444): MT sta intraprendendo tutte le attività necessarie per risolvere la criticità e riferirà nel corso del NUG-IT del 14 luglio 2 Predisposizione di una tabella riepilogativa di tutti i problemi attualmente presenti sulla piattaforma e loro monitoraggio in funzione delle future release CAoF OTC: L’unica attività amministrativa svolta da Monte Titoli per l’OTC è la cancellazione delle istruzioni pending per le operazioni di Aumento di Capitale a pagamento, Inoptati e per tutti gli eventi societari in cui il titolo scade (es. redemption) in cui almeno una delle controparti è un ICP Integrare tabella pag. 5, specificare campo “rif. Msg mittente” e proporre una soluzione alternativa per il campo “nr. Oper. Spec” si prevede di generare un messaggio 7B2 like per le CAoF on Exchange generate con procedura amministrativa Confermare e documentare la cancellazione automatica della underline transaction alla maturity date Confermare e documentare la procedura di riattivazione dello stesso ISIN per diritti di opzione per l’asta dei diritti inoptati Predisporre un prospetto riepilogativo dei processi (automatici / amministrativi) che Monte Titoli utilizzerà per le varie tipologie di eventi societari ed evidenziare eventuali differenze di gestione per i DCP e ICP. Sul punto Monte Titoli riferisce dell’attività amministrativa di cancellazione delle istruzioni pending alla maturity date, e che sarà predisposto l’elenco degli eventi societari impattati Predisporre degli esempi di messaggi generati automaticamente e in via amministrativa a fronte della medesima istruzione CAoF, al fine di confrontare nel dettaglio i campi utilizzati dai partecipanti. 3 4 5 6 7 8 9 London Stock Exchange Group 14 July 2015 La lista dei defects (T2S) prioritari per il Go Live, che sarà sempre in progress, sarà proposta nel NUG del 14/07 Si allega la tabella “Elenco processi amministrativi.xlsx” con l’elenco degli eventi societari per i quali sono generate istruzioni CAoF Transformation ed è prevista la cancellazione, indicando altresì le casisistiche per cui l’attività sarà eseguita automaticamente o manualmente. Si allega il documento “T2S incontro ABI 7lug15 upd 2015.07.09.pptx” con gli aggiornamenti richiesti. In allegato si fornisce il template “7B2 like.xlsx” del file Excel che sarà utilizzato per la segnalazione delle CAoF generate con procedura amministrativa. Cfr #4 Il processo è descritto negli use cases delle CAOF e nelle slides del PT-TUG Cfr #3 Si allega il documento “Sample 20022 CAOF AMM VS ORIG 2.xlsx” Page 7 Self assessment report summary Area OVERALL PROGRESS DOMESTIC SETTLEMENT (OTC) DOMESTIC SETTLEMENT (ONEX) CrOSS BORDER SETTLEMENT - Cross-CSDs CROSS BORDER SETTLEMENT - External CUSTODY ON STOCK - Reorganisation CUSTODY ON STOCK - Cash Distribution CUSTODY ON FLOW COLLATERAL - MT management COLLATERAL - T2S management CASH INTEROPERABILITY CASH AUTHORISATION - DCP only CONTINGENCY SCENARIOS Stato Attività G Y R X n/a NO DATA G 3 10 5 3 8 9 9 2 10 7 19 9 6 Y 14 12 11 4 4 8 14 8 3 10 4 2 5 R 2 3 3 3 4 1 0 9 2 2 0 0 1 n/a 0 0 6 11 7 3 0 3 9 5 1 8 6 X 0 0 0 2 1 3 1 2 0 0 0 0 4 NO DATA 6 0 0 2 1 1 1 1 1 1 1 6 3 Totale 25 25 25 25 25 25 25 25 25 25 25 25 25 Definizione Attività in linea con la pianificazione e la data di migrazione Attività in ritardo rispetto alla pianificazione ma senza impatti sulla migrazione Attività in ritardo che (in assenza di misure correttive) può avere impatti sulla migrazione Attività non ancora iniziata Non applicabile (funzionalità non utilizzate) Campo non valorizzato London Stock Exchange Group 15 July 2015 Page 8 2. T2S defects status London Stock Exchange Group Page 9 Status of “important” T2S defects TICKET NUMBER SUMMARY SEVERITY SUBMIT DATE STATUS FOLLOW UP PBI000000152490 Settlement Restrictions linked “WITH” together did not settle together 2-Urgent 01/12/2014 In Progress Confirmed post go-live. Workaround available in PROD. INC000000165780 Error DSU1042 when removing a closed restriction from an ISIN. 24/06/2015 In Progress Planned for the 24/7 release INC000000166099 MIG2 - Same settled transaction is reported in two delta semt.017s 4-Low 30/06/2015 In Progress INC000000166353 MIG2 - 4 missing sese.025s due to internal sequencing not completed 2-Urgent 06/07/2015 In Progress 3-Medium 15/05/2015 Resolved PBI000000155776 Outbound messages screen not reachable when clicking on “Related Outbound Messages” button in the Settlement Instruction Details screen Customer Follow-Up Required PBI000000155787 MIG2 - CSD user cannot transfer DCA to a different account holder due to an unknown error 3-Medium 15/05/2015 Resolved PBI000000156229 (MT-1472) Incoherence into the ReturnLimit answer sent from T2S 3-Medium 10/06/2015 Resolved Customer Follow-Up Required PBI000000156330 Object Privileges (cross system entity) not shown in GUI 3-Medium 15/06/2015 Pending Future Enhancement PBI000000156416 T2S Multilateral: Additional parties incorrectly displayed on T2S GUI 2-Urgent 18/06/2015 Pending Pending Original Problem PBI000000156444 Pending instruction not present in semt.027 response from T2S MIG2 2-Urgent 19/06/2015 In Progress Planned for the 24/7 release PBI000000156532 MIG2 - GUI visualisation issue 4-Low 23/06/2015 Pending Future Enhancement PBI000000155843 semt.018 wrongly including SttlmSts and InstrPrcgSts 2-Urgent 18/05/2015 Pending Waiting Internal Enhancement Customer Follow-Up Required INC000000166532 MT-2492 Missing T2S sese.024 for our instructions 3-Medium 08/07/2015 Assigned INC000000166286 No remaining amount shown in statement of pending instructions Jira MT-2478 Intesa Sanpaolo. 2-Urgent 03/07/2015 Pending London Stock Exchange Group 14 July 2015 Client Action Required Page 10 3. MT Community Testing status London Stock Exchange Group 15 July 2015 Page 11 Settlement STATUS OWNER Issue /comment RESOLUTION DATE ECB - Autocollateralization: process almost tested. Solution identified for issue messages sequencing received from the T2S platform Release on 17/7 Counterparty Hold: Analysis performed and solution identified. Terms presented to DB and the other participants during last PT-TUG. Ad hoc meeting to be organized in the next days. TBD MARKET opening/resending/closing POST TRADE PRE-SETTLEMENT/SETTLEMENT (not guaranteed trades) Party 2: workaround starting from 31/8 – MT verification on bilateral basis static data where it could be possible a mis-matching when Party 2 field is populated. Ongoing. POST TRADE PRE-SETTLEMENT/SETTLEMENT (guaranteed trades) – Bilateral netting (net and gross margin model) See above ROUTING ICSD (Bilateral balance Creating TLN) and original trade for EuroMOT CCP flows Portfolio Transfer As per agreement in PT-TUG: • character allows in all transmission channels (‘-’ instead of ‘/’): MT will send ABI list of participants who used RNI Messages Switching. • Decimals: value 3 bytes, percentage 5 bytes confirmed. MT will send all participants the info on the limitation PCT/PCR Note: PCR under testing (even if out of scope for the lunch of the service) Cash Forecast Descoped. Administrative solution presented during PT-TUG (template and standard query) Cross and External CSD Settlement STATUS OWNER Issue RESOLUTION DATE CROSS CSD SETTLEMENT Reporting/Input/Allegment/Cancellation/ Matching/Forwarding to Settlement System Process/Reporting EXTERNAL CSD SETTLEMENT Reporting/Input/Allegment/Cancellation/ Matching/Forwarding to Settlement System Process/Reporting Partial Settlement on UK market Incoming and outgoing messages for the whole process work properly MT -‘giri dump’ (Spain and USA) Issues on outgoing messages have been fixed. Analysis done on issue raised on incoming messages Dual listing: released and currently under testing TBD Corporate Actions on Flow (CAOF) STATUS OWNER Issue RESOLUTION DATE OTC descoped (management presented during PTTUG) On Exchange: Tested with positive result: • Dividendi (in cash e in natura) • Pagamento interessi • Rimborso (totale) Under testing: • Reorganization (gratuite, a pagamento, mandatory) Missing semt.027 related to semt.026 sent ECB: INC 165270 closed since it is linked to PBI 156444 that is the summary of the CAOF messages incidents raised. TBD Market claim rejected by X-TRM if Party2 not present in X-TRM (DCP failed transactions) MT CR (ADDITIONAL MANAGMENT OF THIS SPECIFICITIES) Party 2: w/a starting from 31/8 – MT verification on bilateral basis static data where it could be possible a mis-matching when Party 2 field is populated. Cfr. ‘Matching Criteria in T2S’ document Market claim rejected by X-TRM-Securities account of the counterparty missing MT CR (REMOVE OF CONTROL AND INSERT OF THE BIC OF THE COUNTERPARTY IN X-TRM) WORKAROUND SUGGESTED BY MT Cfr. ‘Matching Criteria in T2S’ document Custody and Corporate Action STATUS OWNER Issue Admission of Financial Instruments No issues Issuance / Mark up No issues Mark Down No issues Cash Distribution - MT Issuer No issues Reorganization – MT Issuer No major issues Cash Distribution - MT Investor No major issues Reorganization – MT Investor Minor regression on reorganization with options will be fixed and relevant test will be performed again next week RESOLUTION DATE Government Bond - Auction No issues PBI 154860 4-09-15 - Cash Payment Tests on Govies were successfully performed, both for interest and redemption payments. There are still some issues related to “link after”.. Concerning the book-out of securities positions due to redemption, an issue generated by the creation of balances caused a delay in the settlement of relevant instructions. PBI_154860 4-09-15 INC_164983 PBI_156215 INC_163852 - Coupon Stripping No issues Thanks for the attention! London Stock Exchange Group Page Disclaimer The publication of this document does not represent solicitation, by Borsa Italiana S.p.A., of public saving and is not to be considered as a recommendation by Borsa Italiana S.p.A. as to the suitability of the investment, if any, herein described. This document is not to be considered complete and is meant for information and discussion purposes only. Borsa Italiana S.p.A. accepts no liability, arising, without limitation to the generality of the foregoing, from inaccuracies and/or mistakes, for decisions and/or actions taken by any party based on this document. AGREX, BEST VENUE INDICATOR, BORSA ITALIANA and BORSA ITALIANA’s logo, BORSA ITALIANA ITALIAN STOCK EXCHANGE, BORSA VIRTUALE, BORSAM@T, CITY FOR GOOD, DDM, ELITE, ETFplus, EUROMOT, EXPANDI, EXTRAMOT, IDEM-THE ITALIAN DERIVATIVES MARKET, IDEX, MARKET CONNECT, MIB, MIB 30, MIBTEL, MIDEX, MINIFIB, MIV, MOT, MTA, MTF, NIS, SEDEX, STAR, STAR SEGMENTO TITOLI CON ALTI REQUISITI, TECHSTAR are registered trademarks owned by Borsa Italiana S.p.A. CC&G is a registered trademark owned by Cassa di Compensazione e Garanzia S.p.A. MONTE TITOLI, X-TRM, MT-X are registered trademarks owned by Monte Titoli S.p.A. MTS, BOND VISION, EUROMTS are registered trademarks owned by MTS S.p.A. PALAZZO MEZZANOTTE CONGRESS CENTRE AND SERVICES, BEST VENUE INDICATOR, MARKET CONNECT are registered trademarks owned by BIt Market Services S.p.A. London Stock Exchange, the coat of arms device and AIM are registered trademarks of London Stock Exchange plc. FTSE is a trademark of the London Stock Exchange Group companies and is used by FTSE International Limited under licence. GATElab, Traderpath, Algorithmicpath, Exchangepath are registered trademarks owned by Gatelab S.r.l. The above trademarks and any other trademark owned by London Stock Exchange Group cannot be used without express written consent by the Company having the ownership on the same. The Group promotes and offers the post-trading services of Cassa di Compensazione e Garanzia S.p.A. and Monte Titoli S.p.A. in an equitable, transparent and non-discriminatory manner and on the basis of criteria and procedures aimed at assuring interoperability, security and equal treatment among market infrastructures, to all subjects who so request and are qualified in accordance with national and community legislation, applicable rules and decisions of the competent Authorities. London Stock Exchange Group Page 17