Stato tracciatore •Stato produzione moduli •MTCC •Stato integrazione shells e dischi •Piano integrazione e installazione TIB/TID •Piano complessivo integrazione + installazione 04/04/06 E.Focardi 1 Si sensors & Front-End Hybrids HPK delivery is completed in Nov.05. In Dec. an additional order has been placed :285 TEC, 100 sensors TOB To be delivered by mid April. Delivery of Hybrid production completed last December (17700). In Dec. we have placed an additional TEC hybrid order (500 pcs) This additional delivery has been received mid-Feb, some rework needed on ~150 hybrids. 7.300 (114%) TEC assembled Hybrids delivered to the gantries and US bonding centers. Assembly of main TEC hybrid order was completed end of January. ~ 300 TEC Pitch Adapters (additional order by RMT and Planar) have been delivered mid- Feb. PA Qualification was done and OK. Hybrid/PA assembly of additional order is ongoing. ~ 100 already sent out. The rest (250) should go out in ~ 1 week. 04/04/06 E.Focardi 2 TIB/ID summary TIB Weekly Module Production 4000 100.0 100% completed 3600 95.0 90.0 75% completed 2800 85.0 2400 2000 80.0 50% completed 1600 75.0 1200 25% completed 70.0 800 65.0 400 0 60.0 1 5 9 13 17 21 25 29 33 37 41 45 49 1 5 9 13 17 21 25 29 33 37 41 45 49 1 5 weeks 2004 Hybr at Gantry weeks 2005 Mod Assem Mod Bonded Mod ARC Tested weeks 2006 Mod LT Tested Total Good Yield G.M.Bilei 04/04/06 E.Focardi 3 Yield % # Modules 3200 Expected End Dates TOB modules prod. FNAL • • Will finish TOB modules when final OB1 sensors arrive Expect to build 240 R7modules – Est. end date: ~April 14th • UCSB Will use part of April recovering some modules 04/04/06 • 206 TEC & 507 TOB modules left to finish – 713 Total • expected end date ~April 22nd – To get some contingency, will increase production rate to finish at ~April 14th E.Focardi 4 Impegno dell’INFN nel supporto alla produzione dei moduli TEC del tracciatore di CMS • • • • • • • • • Assemblaggio robotizzato di 426 moduli dei tipi Ring3 e Ring4 nella Sezione di Bari (Gantry) dopo test di accettazione componenti (ibrido,sensore e frame in fibra di carbonio) , con un rate max di 40 moduli alla settimana Microsaldatura dei moduli nelle Sezioni di Bari, Catania, Padova e Pisa Test di funzionalita’ nei centri di microsaldatura dei moduli prodotti Spedizione moduli ai centri di integrazione TEC dove richiesto dalla comunita’ TEC Inizio produzione: seconda meta’ Gennaio 06 Il 76,5 % dei moduli sono gia’ assemblati Il 42% sono microsaldati con uno Yield del 98% Termine assemblaggio: fine Aprile 06 Fine produzione: prima meta’ di Maggio 06 Moduli del tipo Ring4 Moduli del tipo Ring3 04/04/06 E.Focardi 5 TIB in MTCC • • • • • • TIB layer 3: 1 cooling loop is mounted on the CF prototype of Layer 3 structure – 1 cooling loop = 15 strings = 45 modules = 90 fibres = 180 APVs – Final cooling, final grounding, DOHMs etc. TIB layer 2: 5 DS strings are mounted on ad hoc produced mockup of Layer 2 (doubled sided layer) – 5 strings = 15 DS_modules= 30 SS_modules = 90fibres = 180 APVs – Final cooling, final clearance Service cylinder, cables and fibers support structure – CF prototype with final dimensions and clearances TIB integration @ SPiero: all the procedures were followed as close as possible to the real TIB integration with final tooling: module integration, piping, burn-in, layer coupling, cabling, testing etc. – good exercise for the final cabling procedure. TIB transportation – very realistic exercise for the real TIB transportation: the same company, tooling, procedures, monitoring, reception test etc. TIB insertion into TOB and cabling: the same tooling, TEAM, cabling and piping procedures. 04/04/06 E.Focardi 6 MTCC TIB burn-in @ Pisa: NOISE distribution in Deconvolution mode: •some known number of dead strips Layer 3 04/04/06 E.Focardi 7 TIB(MTCC) integration @ Pisa MTCC TIB integration was done at S.Piero using the final cradle, insertion machine. Good experience, cabling procedures completely revised. 04/04/06 E.Focardi 8 Transportation 0.5 g -0.5 g TIB MTCC was transported by the company which should transport also final TIB+ and TIB-. The acceleration during the the transportation didn’t exceed 0.6g. Reception test at arrival didn’t show any damage to the tracker. Procedure ready for the final transport. 04/04/06 E.Focardi 9 TIB/TOB integration TOB TIB cooling pipes (Al) TIB Optical connectors TIB Optical connectors TOB cooling 04/04/06 E.Focardi 10 TIB/TID+ modules integration completed (Pisa, Firenze, Torino) Mounted objects http://hep.fi.infn.it/CMS/Florence_integration/status.php#detail 04/04/06 L2 L4 L3 L1 D1 E.Focardi D2 D3 11 days since January05 Integrazione TIB • Stazione di integrazione: -Supporto meccanico -DAQ per controllo e lettura di almeno 1 • • stringa di 3 moduli -Power Supply (LV, HV, controllo) 2 tavoli di integrazione a Pisa (S.Piero a Grado) 1 tavolo di integrazione a Firenze (Sesto Fiorentino)+ 1 in allestimento •Rifinitura lavori meccanici e grounding •Montaggio Analog Opto Hybrids e stesura fibre ottiche •Formatura dei cavi dei Digital Opto Hybrids •Montaggio dei moduli (e test) •Fissaggio e cablaggio dei Digital Opto Hybrids 04/04/06 E.Focardi 12 Trasporti Firenze-Pisa Torino-Pisa • Il sistema di trasporto e’ ormai consolidato • Gia’ trasportati a Pisa i layer 3,4,2 da Firenze e i dischi D1,D2,D3 + da Torino Shock absorber 04/04/06 E.Focardi 13 TIB forward: Layer 2 +1 L2 • • • Alta densita’ di fibre ottiche L2 up gia’ qualificata nel burn-in noise e cooling tests molto buoni L1 –Distanza ridotta tra stringhe sovrapposte –Alta densita’ delle fibre ottiche –Curvatura stretta dei tubicini 04/04/06 E.Focardi 14 TIB backward: componenti meccaniche • Layer 4 – In preparazione per inizio integrazione moduli (fissaggio pillars in corso) • • Layer 1 Layer 3 & 2 – Ultimato incollaggio cooling tubes – Previsto ulteriore test di raffreddamento e portata – In corso incollaggio cooling tubes 04/04/06 E.Focardi 15 Dischi Interni Ring 2 Ring 3 Ring 1 04/04/06 E.Focardi Disco ultimato a Torino e pronto per il transporto 16 Integrazione Anelli OPERAZIONI: • montaggio servizi MC,DOM,AHO,Tprobe,p.ext. • Montaggio moduli • Test OTTIMIZZAZIONI: • • • 04/04/06 Integrazione elettronica digitale Passaggio fibre Grounding E.Focardi 17 Test inserimento disco sul service cylinder E’ stato fatto un test di inserimento di un disco nudo nel service cylinder utilizzando il jig di allineamento disco04/04/06 E.Focardi 18 cilindro The climatic chamber • A large cold room (~27 m3) has been installed in Pisa to perform the burnin of the assembled layers/disks of the TIB and TID. The room has a communication door directly into the clean room where the module integration is performed. • The final configuration will allow to test up to ¼ Layer-2 and a ½ Layer-4 (half end). • The room can be operated from 30oC to +80oC and conditioned with dry air. Operations are controlled by a a dedicated PC. • Feed troughs allow the routing of the cables from the cold room with the outside and the clean room. 04/04/06 • E.Focardi 19 Setup • •DAQ –1 FEC-VME (8 channels, 4 in use) –8 FED9U Hardware – Power supply: • SY1527 • 3 crates • 22 CAEN PSM – – 18 4601H 4 4601F • 2 channels 48 Volt CAEN • + custom GUI + monitoring – Cables TK TSC • 44 LIC • 8 CAB60 cables TK TFB – Chiller FED FED FED FED • Up to 7.5 bar freon 04/04/06 E.Focardi VME VME VME VME Data v2 FECVME v2 v2 v2 TTCvx TTCv xTK front end detectors 20 Pre-test operations Disk fiber holder Ribbons Cables • Sizeable fraction of the time spent to prepare the structure – Disks and Layers 3 & 4 two days work – layer 2 fibers connected in 2 weeks (~2 • cooling people with Christmas holidays duty cycle...) All connections logged in integration DB and used for run analysis. 04/04/06 E.Focardi 21 Scenario • The burn-in protocol guarantees: – At least 30 hours powered, clocked and triggered, of which 10 hours cold – 6 hours run under CMS conditions (chamber –10C, liquid –25C, bias 400 V) to study stability, reading temperatures, pedestals, noise • Layers tested so far have been tested much longer (5 cycles, 100 hours integrated). Power supply parameters logged continuously I2.5(A) 48 APV 36 APV 04/04/06 Time (hours) Monitoring of •cooling loops temperatures •chiller pressure E.Focardi 22 Performed tests • Control ring and I2C device scan – read-write test – redundancy – at two different temperatures • warm (room 10C, C6F14 0C) • cold (room -10C, C6F14 -25C) – not responding modules are replaced • Thermal response – module temperatures measured at two working point (APV on and operational): • room -10C , C6F14 -10C • room -10C , C6F14 -25C • Channel Readout: full sequence of tuning runs: – Connection • all the modules has to be found – Timing scan – Opto-gain scan – Timing scan (FED thresholds) – VPSP scan (APV settings) – Pedestal/Noise runs • Peak and Deco mode • HV @ 400 V – tuning repeated when temperature is changed –04/04/06 Differences used to study E.Focardi• DAQ system runs smoothly thermal contact 23 Activities summary Cold room status Before: TIB+ layer3 UP: NOW: TIB+ layer3 UP: pre-reworking TIB+ layer3 DW: only I2C test TIB+ layer4 DW: TIB+ layer4 UP: TID+ disk1: TIB+ Layer 2 UP: SS modules only 20 PSU, 4 DOHM 318 fibers, 4 FED DS modules 26 PSU, 6 DOHM 368 fibers, 5 FED DS modules 42 PSU, 8 DOHM 630 fibers, 8 FED • SS modules only 20 PSU, 4 DOHM 318 fibers, 4 FED MTCC: DS modules 11 PSU, 2 DOHM 180 fibers, 2 FED Number channels doubled since midDecember: – more than 160k strips in layer 2 UP 04/04/06 E.Focardi 24 Tested structures • TIB+ L3 UP: • – no cooling loop test – reworking done after the test TIB+ L4 DOWN: • TIB+ L3 DOWN: – from Feb 3 to Feb 6 – from Oct 20 to Nov 14 • • cooling loop tested individually TIB+ L4 UP: – from Nov 15 to Dec 1 • TID+ disk 1 (3 rings) – from Dec 17 to Dec 23 • • cooling loops ring 3 to be fixed TIB+ L2 UP – from Dec 27 to Jan 26 • • I2C cold test only to spot modules to be replaced before reworking • TIB+ L3 UP (is back...): – Feb 7 to Mar 29 • Tests on new grounding scheme • Disk 2 (3 rings) • Mar 30 – April 6 (?) • Future Plans: – TIB+ L3 DOWN – TIB+ L2 DOWN MTCC structure (L3+L2) – from Jan 27 to Feb 2 • no cold test 04/04/06 E.Focardi • (both already cabled) 25 Thermal • All DCU temperatures read out during data taking at nominal flow Coolant @-25C Sensor temperature Sensor Temperatur e (- 19.53 1.64)C Hybrid Temperatur e (- 18.00 1.23)C To be compared with single module measurements of – Sensor -20.4 °C – Hybrid -17.8 °C • Hence expect that the maximum sensor temperature at end-of-life would not exceed ~16°C 04/04/06 Hybrid temperature E.Focardi 26 Disco 1 : temp sensori a silicio 04/04/06 E.Focardi Silicon @-14C for DS modules, @-17C for SS modules 27 Disco 1 : temp ibridi Ibridi Scollati :tipicamente 300 m 04/04/06 E.Focardi Good hybrids @-6C for DS modules, @-13C for SS modules 28 Results: TID+ disk1 forward backward ring 3 • Temperature pattern in the other strings is being compared with expectation • Problem serious enough to stop burn-in and wait for reparation to redo it sensors hybrids • • Problems in both forward strings of ring3: poor cooling liquid flux in those strings Confirmed by: – direct temp measurements – retrieving cooling loop test 04/04/06 data E.Focardi 29 Timing scan ADC Step 1) all modules should be time aligned Synchronization pulses (tick-marks) from each modules are sampled by the FED and reconstructed in time with different delays. • All (~258 ) tick marks are reconstructed and aligned • All modules delayed to compensate the delay in the time arrival of trigger on the module consistent with logical position in the ring Opto gain First position in the ring 04/04/06 Last position in the ring E.Focardi 30 Grounding studies Low High Noise RMS String number 04/04/06 E.Focardi 31 Summary of results Peak L4 04/04/06 Deconvolution L4 E.Focardi 32 Noise run results: TIB+ L2 UP peak warm peak cold • TIB+ L2 UP strip noise distribution – deco warm 04/04/06 deco cold E.Focardi after CM subtr. • Normalized to have a tick-mark height=640 counts • Strips statistics: out of 161280: – – • ~100-180 noisy ~75-110 dead ~1.5-2 per mil of bad strips ! 33 Tracking Integration Facility 04/04/06 E.Focardi 34 TST in the TIF 04/04/06 E.Focardi 35 TOB Rod insertion 04/04/06 E.Focardi 36 169 petals assembled 148 tested TEC TEC- @TIF 04/04/06 E.Focardi 37 TEC status 18 15 2 6 04/04/06 Cosmic muon in TEC+, reconstructed in ORCA E.Focardi (23.3.06) 38 Forward Pixel test 04/04/06 E.Focardi 39 Forward pixel, Milano • Impegni 1. 2. 3. 4. • Organizzazione e responsabilita’ dei test su fascio dei fwd pixel Sviluppo e responsabilita’ del software per il test-stand per la fase di produzione dei fwd pixel Sviluppo e responsabilita’ del programma di allineamento dei fwd pixel In prospettiva, partecipazione al commissioning dei fwd pixel Beam test – Abbiamo appena concluso (Febbraio ’06) un primo run dei rivelatori irraggiati a 3 1013 • – I risultati dimostrano che I rivelatori funzionano in modo pressocche’ perfetto e non manifestano alcun segno di degrado a 3 1013 • – Gli stessi rivelatori, non irraggiati, erano stati provati su fascio lo scorso Luglio Si tratta del primo test su fascio dei nuovi chip di lettura condotto con un sistema di tracciamento ad alta risoluzione Il set up utilizzato e’ quello di BTeV da noi opportunamente adattato 04/04/06 • Per ulteriori dettagli vedi E.Focardi presentazione Luigi alla pagina http://indico.cern.ch/conferenceDisplay.py?confId=a061628 40 Progressi • Pixel Test-Stand – Il software, DAQ e relativi programmi di analisi, e’ praticamente completo – Si sta ora lavorando sull’interfacciamento al DB – Principali caratteristiche del sistema sono • L’alto grado di interattivita’ nell’eseguire la diagnosi completa dei rivelatori • Brevissimi tempi di esecuzione grazie all’utilizzo di microprogrammi su FPGA http://docdb.fnal.gov/CMS-public/DocDB/ListBy?authorid=27 • Allineamento Pixel – Preso possesso dei vari programmi sviluppati – Si sta ora cercando di capirne le prestazioni e I limiti utilizzando I mezzi di calcolo dello CNAF (Pedrini) – http://indico.cern.ch/conferenceDisplay.py?confId=a058113 • contributo allo sviluppo del software di tracciamento: – Terminato il porting del pacchetto di Kalman filter in CMSSW, – si e’in ora in fase di begug & validation vedi ad es presentazioni Stefano/Marco/Giuseppe http://indico.cern.ch/conferenceDisplay.py?confId=a06913 04/04/06 E.Focardi 41 Off detector electronics 04/04/06 E.Focardi 42 Power System Components Delivery Status 820/1000 400/1000 A4601H PSMs modules already delivered, end by summer ‘06 Back Boards delivered, end by fall ‘06 80/130 Easy 4000 crates delivered, end by summer ‘06 1/90 3/60 A4602 PSMs for the controls: first proto delivered, production by fall ‘06 A3486 Ac/Dc (48 Volts) delivered, end fall ‘06 22/22 A1676 Branch controller delivered 2/2 SY1527 delivered Cables Al cables and short control cables : received @Cern ~100/650 LIC production assigned:a sample of 2 Km are expected in April 04/04/06 - 25% produced by mid July, E.Focardi production completed by Fall 43 L4 sub-assembly 04/04/06 E.Focardi Insertion jig@work 44 ! Test after final assembly We have checked the possibility to perform a final test of the TIB/TID+ fully assembled before transport. The entire cradle fits into the cold-room. Possibility to anticipate in Pisa the tests foreseen at TIF (hunt for unforeseen problems in the final assembly; possibility to operate in cold the entire TIB/TID; sort of pre-commissioning of TIB/TID+). The drawback is the time: 3 additional weeks are needed. The integration/burn-in team strongly supports the proposal. No impact on the overall schedule, backward part integration 04/04/06 on April 3-rd. E.Focardi 45 started Status and plans 1. The integration of the modules on the TIB/TID+ is done. 2. The sub-assembly has successfully started (L4). 3. With pre-commissioning in the cold room in Pisa we shall transport TIB/TID+ to CERN in May. 4. The module integration on the TIB/TID- part started at the beginning of April (5 integration teams in parallel). 5. We plan to transport TIB/TID- to CERN by August. 04/04/06 E.Focardi 46 v34.4 :best projection from current position Magnet test over: early Aug 06 Central wheel ready to lower: late Oct 06 Tracker installation: Feb 07 CMS "ready to close" end Jul 07 04/04/06 E.Focardi Re-optimised: ECAL, Preshower, Tracker Installation 47 plus YB lowering. Integration, electronics & commissioning 04/04/06 E.Focardi 48 Milestones for Siliconstrip Completion of TIB / TID+ Integration in Italy May-06 Completion of TOB Modules May-06 Magnet Test System at P5 commissioned May-06 Completion of TEC Modules Jun-06 Completion of TIB / TID- Integration in Italy Aug-06 Completion of TOB RODs Aug-06 Completion of the Integration of TOB+ Aug-06 Completion of TEC Petals Sep-06 Completion of the Integration of TEC+ in Aachen Sep-06 Completion of the Integration of TOB- Oct-06 Completion of the Integration of TEC- at CERN Nov-06 TRACKER READY FOR TRANSPORT TO P5 Jan-07 04/04/06 E.Focardi 49 Milestones for pixels Forward Pixels Completion of a full production blade Jul-06 Completion of the first production half ring Dec-06 Completion of full FPIX readout chain system test Dec-06 Barrel Pixels System test of complete BPIX module group with supply tube Jul-06 and final powering 1/3 of modules for layer 1 & 2 fabricated & tested Sep-06 2/3 of modules for layer 1 & 2 fabricated & tested Nov-06 Supply tubes & mechanics for commissioning system delivered to PSI Dec-06 04/04/06 E.Focardi 50