The NEMO-Phase2 tower elements
8 floors
8 m bars, vertical dist. = 40 m, Htot = 450 m
32 OM, 18 hydrophones
oceanographic instruments
Final validation of the DU for Capo Passero
The OM: 10” Hamamatsu R7081, Front End
Module, Time Calibration, LED beacons
Hydrophones: acoustic positioning and
bioacustics
32 OMs, all fully tested and calibrated.
2 OMs equipped with piezo-hydrophones
Erlangen, June 22-23, 2012
Antonio Capone
1
4 OMs/floor
2 hydrophones
Nemo-Phase 2 Status
Mechanical structure, including anchor and
deployment tools ready at LNS
All “offshore” electronic cards integrated
and tested in their vessels, ready at LNS
All “on-shore” electronic cards integrated
and tested, ready at LNS
The Data Acquisition software ready, will be
tested during July/August at Catania lab.
All cables/connectors ready at LNS
The Power Feeding system, the MEOC, the
Junction Box ready at Capo Passero
Erlangen, June 22-23, 2012
Antonio Capone
2
Attività prevista (Luglio-prima settimana settembre)
• Questa settimana
Test FCM, chiusura vessel di piano, test Vessel su camera iperbarica
integrazione backbone , break out e PMT su struttura meccanica
• Integrazione piani:
Si parte dal piano piu’ vicino alla base
-collegamento OM-FCM
-collegamento FCM-break out di piano
-test con 4 OM oscurati simile a quello di fase 1 (acquisizione fondo PMT,
misura margine ottico, …..
-si passa al piano successivo
• Test finale
Effettuato oscurando tutta la struttura come se la torre fosse in mare
Si utilizza tutta la on shore electronics
- Trigger System Controller (TSC): monitors and serves the TriDAS - (1 GbE I/O) (to be finalized)
- Hit Managers (HM): receive optical data; prepare and distribute the Time Slice (TS) to the TCPU (DONE)
- TriggerCPUs (TCPU): apply the trigger logics to the assigned TS and transfer the selected data to the EM;
note: more than 1 TCPU process can run on a TCPU server (Quasi done: TriggerAlgos to be finalized)
- Event Manager (EM): receives the triggered data from TCPUs and build the Post-Trigger events data file
(Started)
sector
NEED OF NEW SERVERS FOR THE Test Bench IN BOLOGNA
Minilinea ANTARES per Capo Passero
Provata la settimana scorsa dopo 1.5 anni di stop
configurazione in via di definizione
Capo Passero
Termination Frame
SJB#1
8
Outputs
SJB#2
8
Outputs
SJB#3
8
Outputs
SJB#4
8
Outputs
Primary
JB
Capabilities:
20 Optical Fibers G 655
10kV/375V DC-DC converter
 up to 8.8 KW available off shore
50 kW available onshore
SEA operations – June 2012
Short summary report
R. Papaleo
22 june 2012
Scope of work
Deploy SN1 underwater station and connect to
TSN termination frame
Deploy LIDO acoustic station and connect to
NEMO JB
Option: Make a visual inspection of the NEMO
Mechanical Tower deployed 2 years ago
The Catania Test Site: a multidisciplinary deep sea-lab
LIDO demo mission of ESONET-EMSO: Refurbishment of SN1 and OnDE observatories
Goals: Bioacoustics, ocean monitoring,Tsunami warning.
LNS-INFN Catania
North Branch (SN1)
4 LBW hydrophones
2 LF hydrophones
CTD, ADCP,
Seismometers
magnetometers
pressure gauges
GPS time stamping
100 Mbps Internet
Radio Link
20 km
NEMO JB
LNS Test Site Laboratory
at the port of Catania
South Branch
(Onde2)
4 LBW
hydrophones
Underwater GPS
time
stamping
Infrastructure requested by UCL and CSIC for installation of deep-sea
stations
in 2013
SN1 (TSN) installation and connection: 8 June 2012
SN1 deployed with the MODUS
Shuttle (INGV standard operation)
MODUS Shuttle power failure.
SN1 released 250 above seabed (1850 m).
SN1 fallen upside down on the seabed
ROV and Certamen C/L Vessel joint operation:
SN1 hooked and turned correctly above the seabed
SN1 connected to the TSN cable
termination. Switch on.
First data from SN1
Hydrophones data
Seismometer data
Acoustic event, detected by SN1
hydrophones, acquired in time
coincidence with a seismic event
detected by INGV (June 15th, 6:28
UTC with GURALP seismometer)
with intensity 3.8 M.
OnDE 2 (TSS) a full NEMO Phase II floor
•
•
•
•
•
•
•
• All electronics is sucessfully
working
• Underwater GPS data time
stamping OK
• Optical attenuationof the line
• (including JB) 12 dB
• Heading -8.5° North
• Hydrophone data under analysis
Mechanical vessel and interfaces
Cabling
Power Control and feeding System
DWDM optical data transmission system
Floor Control Module main board
Acoustic Boards
Compass
ONDE
•Stato attuale:
il segnale dei 4 idrofoni e’ ‘affogato’ nel rumore.
•Causa probabile:
Modifiche effettuate per estendere la banda verso
 basse frequenze( 20 Hz) x terremoti e balene.
•Soluzioni possibili
svolgimento cavo connessione
bypassare la JB
Scope of work of the mechanical tower
Check deployment and release procedures
Check unfurling procedures
Check behaviour of the tower after the
unfurling procedures
dyneema
dyneema
BASE
RECUPERABILE
CATENA
ANCORA
Prossime Operazioni
• Test operatività ROV a 3500 m previsto per seconda
metà luglio
• Deployment e connessione torre a Capo Passero
previsto a settembre
Compatibilmente con la slot temporale disponibile ,si
cercherà anche di intervenire sul sistema acustico
(ONDE)
Scarica

Diapositiva 1