Un intervento in corsa Maurizio Delucchi Quick Work Ansaldo Sistemi Industriali S.p.A. has extended and adapted the substation which supplies power to the entire QATAR STEEL plant in the industrial zone of Mesaieed in QATAR, achieving a complete reorganization of the 66kV Electrical Power Supply. The special feature of the work was the extremely limited time available for work on site due to the fact that updating of the substation required the complete shut-down of the plant. This article describes the solutions, precautions and work methods adopted which enabled the steelworks to return to production early compared to the already tight schedule for works on site. QATAR STEEL required a complete reorganization of the distribution network inside its steelworks in the industrial zone of Mesaieed on the outskirts of Doha Qatar. The electrical power supply for the plant was provided by a 66kV double connection supplied by Kaharama (the electricity distribution body in Qatar). The receiving substation, originally built by the Japanese in the 1970s, had been subject to various extensions and rebuilds. It is an air-insulated substation, installed in an industrial shed where every circuit has its counterpart in an insulated bay in the relevant cell. Above each cell, suspended from the roof by insulators, run the main busbars made of tubular aluminium designed to handle 2000 A and 25 kA of short circuit current. (Fig. 1 section) The work had multiple aims as indicated below: 1. To separate the electrical loads subject to rapid and frequent variations (the so-called “dirty” loads) from the stable ones (“clean” loads). 2. To change the connection of the TAs of the EF2R furnace which, over the course of various modifications, had become configured incorrectly. 3. To replace the old electromechanical bar protection, which covered only part of the main busbar system, with modern and functional differential digital busbar protection. To carry out the work described in point 1 above it was necessary to move the power supply for 2 circuits (Gasal and RM2) from the QS no. 1 substation, connecting it to the receiving substation (busbars with “clean” loads) where there was only one free cell. The solution adopted had therefore to take into account the limited space available for the extension of the receiving substation and still give preference to solutions which ensured a minimum shut-down time. INNOVATION 10 The order for the turnkey installation was awarded, following an international tender process, to Ansaldo Sistemi Industriali S.p.A. which in 12 months has planned and completed the work. The solution adopted included the following solutions: For the extension of the 66kV bays, hybrid system technology was used, installing 2 bays with equipment insulated with Gas SF6 inside the only cell available (Fig 2), while the main busbar was extended with air insulation as in the existing solution. For the modification of the existing ammeter circuit, various solutions were evaluated because the limited space and the specific layout of the existing plant would not allow the TAs to be moved; thus it was preferred to modify the existing busbar, adopting a solution using bars insulated with resin (Duresca ®) which allowed the circuits to be correctly connected in spite of the limited space available. (Fig 3) The most critical work, however, was that relating to the extension and replacement of the existing busbar protection. The old busbar protection consisted of electromechanical protection dating from the 1970s, which covered the existing 10 feeders and was composed of four independent relays for the protection of phases R, Y, B and the homopolar circuit. This last relay is indispensable for detecting faults in the grounding which is limited to 100 A by an impedance placed on the neutral of the 66kV system. A differential protection was added to the above relay, installed when the system was being extended to construct the second furnace (EF2R), covering both the transformer for the furnace and a portion of the busbar attached to it. This reflected the need to cover the whole busbar with a single protection by adopting a new form of protection. This replacement involved the following risks: • the need to interface with 40 year-old equipment and circuitry • the need to work under total shut-down conditions, because the work was on the busbar for the sole energy receiving substation for the entire plant. The solution adopted had to take account of the above requirements, so it was decided to make new panels for the busbar protection containing, in line with the existing philosophy, 4 Busbar Protection SEL 487B. The new panels were built and tested in ASI’s Montebello factory taking into account that these were then to be installed and tested in the control room next to the existing busbar protection. (Fig. 4,5) To minimize the time needed for the work, it was decided to keep the existing connections in the field in action up to the support terminal board inside the existing panels already located in the control room; while the circuits from the support terminal board up to the new protection were produced and fully tested before the shut-down. Ansaldo Sistemi Industriali S.p.A. ha realizzato l’estensione e l’adeguamento della sottostazione che alimenta l’intero stabilimento di Qatar Steel nella zona industriale di Mesaieed in Qatar realizzando una completa riorganizzazione del Electrical Power Supply a 66kV. Caratteristica particolare dell’intervento è stata la tempistica di realizzazione in sito estremamente ridotta in quanto l’adeguamento della sottostazione ha richiesto il fuori servizio generale dello stabilimento. L’articolo descrive le soluzioni, gli accorgimenti e le modalità di intervento adottati che hanno permesso all’impianto siderurgico di tornare in produzione in anticipo rispetto al già ridotto programma delle attività in sito. Qatar Steel ha previsto una riorganizzazione completa della rete di distribuzione interna allo stabilimento siderurgico ubicato nella zona industriale di Mesaieed alla periferia di Doha Qatar. L’alimentazione elettrica allo stabilimento avviene a mezzo di una doppia connessione a 66 kV fornita da Kaharama (Ente distributore elettrico del Qatar) La sottostazione ricevente, costruita originariamente dai Giapponesi negli anni ’70, è stata oggetto di diverse estensione e rifacimenti. Trattasi di una sottostazione isolata in aria, installata in capannone industriale dove ogni circuito trova riscontro in una baia segregata in apposita cella. Al di sopra di ogni cella si estendono, sospese al tetto tramite isolatori, le barrature principali in alluminio tubolare da 2000 A, 25 kA di corto circuito. Lo scopo dell’intervento è stato molteplice come di seguito indicato: 1. Realizzare la separazione dei carichi elettrici soggetti a rapide e frequenti variazioni (i cosidetti carichi “sporchi”) da quelli stabili (carichi “puliti”). 2. Modificare il collegamento dei TA del forno EF2R che nel corso delle varie modifiche avevano assunto una configurazione non corretta. 3. Rimpiazzare la vecchia protezione di sbarra elettromeccanica che copriva solo parte del sistema sbarra principale tramite una moderna e funzionale protezione digitale differenziale di sbarra. Per effettuare l’intervento di cui al punto 1 precedente occorreva spostare l’alimentazione di n° 2 circuiti (Gasal e RM2) dalla QS substation n° 1 collegandoli alla sottostazione ricevente (sbarre con carichi “puliti”) dove era disponibile una sola cella libera. La soluzione adottata doveva pertanto tenere conto degli spazi ridotti per l’estensione della sottostazione ricevente e comunque privilegiare le soluzioni che garantissero un tempo di fuori servizio minimo. La commessa per la realizzazione chiavi in mano dell’intervento è stata affidata, tramite gara internazionale, ad Ansaldo Sistemi Industriali S.p.A. che in 12 mesi ha progettato e realizzato l’intervento. La soluzione adottata ha previsto le seguenti soluzioni: Per l’estensione delle baie a 66 kV è stata adottata la tecnologia dell’impianto Ibrido installando n° 2 baie con apparecchiature isolate in Gas SF6 all’interno dell’unica cella disponibile (Fig 2), mentre la barratura principale è stata estesa con isolamento in aria in analogia con la soluzione esistente. Per la modifica del circuito Amperometrico esistente sono state valutate varie soluzioni in quanto gli spazi ristretti ed il 11 Maurizio Delucchi Particular attention was paid during the design and construction to carrying out all the preliminary activities which could help to reduce downtime and the risks arising from the interface with the existing plant. The work schedule, including the resulting plant shutdown time, was subjected to in-depth analysis in a series of constructive discussions with the customer until a detailed work timetable had been defined, setting, with about 6 months advance warning, the date when the plant would shut down. The schedule agreed with the customer provided for a total shut-down of 5 days plus a period of 3 days to energize the GASAL and RM2 circuits. Coinciding with the work in question, the customer’s Maintenance Unit arranged for other ordinary and extraordinary maintenance work to take place involving other subcontractors, thus creating a schedule which it would be very difficult to deviate from. Work on-site Before the period agreed for the work all the components and materials needed were collected on site and those which would not interfere with production activity (the GIS hybrid, parts of the 66Dv cabling, protection panels, control panels, auxiliary equipment and BT interconnection cables) were assembled. In addition all the pre-commissioning activities which it was possible to carry out with the plant still energized were completed, such as checking of all the BT cables already attached to the side of the new equipment, pre-commissioning tests on the hybrid system and the feeder protection panels etc. The schedule provided for double shift work involving the presence on site of various work teams doubled up both in terms of specialists and workmen to provide the necessary assistance for the specialists. The work groups operated on the following fronts: • one group worked on the physical modification of the busbar • one group worked on the 66kV connection to the GIS hybrid • one group worked on cabling and testing for the busbar protection and the new feeders • one group worked on the 66kV cables. Particular attention was paid to coordination and safety, taking into account that some activities would, by their nature, interfere with others. In particular all the voltage tests at industrial frequency were performed, during which it was obviously not possible to work near the parts subject to testing. The following were high voltage tested, at the industrial frequency testing voltage required by the regulations: • GIS hybrid (before the shutdown) • 66kV cable towards the RM2 • 66kV cable towards the GASAL • Duresca ® busbar. In order to test the stability of the busbar protection, the primary injections were carried out on all the circuits, taking care not to interfere with the industrial frequency tests and avoiding work on the portions of the busbar where the extension work was under way. In this way a complete check of the ammeter circuits, both new and existing, was carried out, including checking that the existing TAs were in good condition (check on connections and polarity). The opportunity was also taken to rationalize an existing marshalling kiosk where cabling was repaired and rationalized. The total on site work (assembly, cabling, testing and commissioning) involved a shut-down time of five days, at the end of which all the certificates for the tests carried out were delivered to the Kaharama Electricity Authority; this allowed the whole plant to be re-energized from the sixth day, that is, 2 days early with respect to the overall schedule agreed with the Customer. This exceptional result was possible thanks to the commitment of all the personnel of Ansaldo Sistemi Industriali S.p.A., all the specialists who worked on site and also to the availability and willingness of the Qatar Steel Maintenance Service which did all it could, using all its staff, to help the contractor with his work and to enable, in the common interest, this great performance to be achieved. a partire dal sesto giorno ovvero con un anticipo di 2 giorni rispetto al programma complessivo concordato con il Cliente. L’eccezionale risultato di cui sopra è stato possibile grazie all’impegno di tutto il personale Ansaldo Sistemi Industriali S.p.A., di tutti gli specialisti intervenuti in sito e grazie anche alla disponibilità del Servizio Manutenzione di Qatar Steel che si è prodigato con tutto il suo personale per assistere il contrattista nel suo lavoro e facilitare, nell’interesse comune, la realizzazione di questa importante performance. particolare layout dell’impianto esistente non consentivano di spostare i TA; pertanto si è preferito modificare la barratura esistente adottando una soluzione con barre isolate in resina (Duresca ®) che ha consentito di realizzare la corretta connessione di circuiti pur negli angusti spazi a disposizione. L’intervento più critico è stato comunque quello relativo alla estensione e sostituzione dell’esistente protezione di sbarra. La vecchia protezione di sbarra era costituita da una protezione elettromeccanica degli anni ’70 che copriva gli esistenti n° 10 feeders ed era costituita da quattro relè indipendenti per la protezione delle fasi R,Y,B e del circuito omopolare. Quest’ultimo relè risulta indispensabile per poter rilevare il guasto a terra che è limitato a 100 A da una impedenza posta sul neutro del sistema a 66 kV. Ai sopraccitati relè si aggiungeva una protezione differenziale installata in fase di estensione per realizzazione del forno 2 (EF2R) che copriva sia il trasformatore del forno sia la porzione di sbarra afferente a quest’ultimo. Ne derivava l’esigenza di coprire con un’unica protezione la completa barratura adottando una protezione nuova. Tale sostituzione comportava i seguenti rischi: • necessità di interfacciarsi con equipaggiamenti e circuiteria vecchi di 40 anni • necessità di operare in regime di totale fuori servizio in quanto si interveniva sulla sbarra della sola stazione ricevente energia per l’intero stabilimento. La soluzione adottata ha dovuto tenere conto delle esigenze di cui sopra, si è pertanto deciso di realizzare nuovi pannelli per la protezione di sbarra contenenti, in analogia con la filosofia esistente, n° 4 Busbar Protection SEL 487B. I nuovi pannelli sono stati costruiti e provati presso la fabbrica ASI di Montebello considerando che gli stessi andavano poi installati e provati ubicandoli in sala controllo a fianco del quadro esistente di protezione di sbarra. (Fig. 4,5) Per minimizzare i tempi di intervento si è deciso di mantenere attivi i collegamenti esistenti dal campo fino alle morsettiere di appoggio all’interno dei quadri esistenti già ubicati in sala controllo; mentre i circuiti dalla morsettiera di appoggio fino alle nuove protezioni sono stati realizzati e completamente testati prima della realizzazione del fuori servizio. Particolare attenzione è stata posta durante tutta la progettazione e realizzazione dell’opera a predisporre tutte le attività preliminari che potevano contribuire alla riduzione dei tempi di fuori servizio e dei rischi derivanti dall’interfaccia con l’esistente. Il programma di intervento con conseguente fermo dello stabilimento è stato oggetto di approfondite analisi a confronti costruttivi con il Cliente fino alla definizione di una tempistica dettagliata di intervento che ha fissato con circa 6 mesi di anticipo la data in cui lo stabilimento si sarebbe fermato. Il programma concordato con il Cliente prevedeva un fuori servizio totale di 5 giorni più un periodo di 3 giorni per l’energizzazione dei circuiti GASAL e RM2. In concomitanza con l’intervento in oggetto, il Gruppo di Manutenzione del Cliente ha fissato altre attività di manutenzione ordinaria e straordinaria che coinvolgevano altri subappaltatori, creando così una programmazione per la quale sarebbe stato molto difficile gestire qualsiasi variazione. Attività in sito Prima del periodo fissato tutti i componenti e materiali oggetto della realizzazione sono stati radunati in sito e sono stati montati quelli che non interferivano con le attività produttive (GIS ibrido, parte dei cavi 66 kV, pannelli protezione, pannelli controllo, ausiliari, cavi BT di intercollegamento ). Sono state inoltre completate tutte le attività di precommissioning che è stato possibile sviluppare con l’impianto esistente energizzato, quali ad esempio il controllo di tutti i cavi BT già cablati lato nuove apparecchiature, le prove di precommisioning dell’ibrido, dei quadri protezione di feeder, ecc. Il programma ha previsto di lavorare su doppio turno comportando la presenza in sito di diversi team di lavoro ridondati sia nelle figure specialistiche che nella mano d’opera per la necessaria assistenza agli specialisti. I gruppi di lavoro hanno operato sui seguenti fronti: • un gruppo ha operato sulla modifica fisica della barrature • un gruppo ha operato per la realizzazione delle connessioni a 66 kV al GIS ibrido • un gruppo ha operato ai cablaggi e prove per le protezioni di sbarra e di nuovi feeder • un gruppo ha operato sui cavi 66 kV Particolare attenzione è stata posta al coordinamento e alla sicurezza considerato che alcune attività hanno avuto, per loro natura, interferenze con altre. In particolare sono state effettuate tutte le prove di tensione applicata a frequenza industriale durante le quali ovviamente non è stato possibile operare nelle vicinanze degli organi soggetti a prova. Sono stati provati in alta tensione, alla tensione di prova a frequenza industriale prevista dalla normativa: • GIS ibrido (prima del fuori servizio). • Cavo a 66 kV verso RM2 • Cavo a 66 kV verso GASAL • Condotto sbarre Duresca ® Per la prova di stabilità della protezione di sbarra sono state effettuate le iniezioni primarie su tutti i circuiti avendo cura di non interferire con le prove a frequenza industriale ed evitando di operare sulle porzioni di sbarra dove era in corso l’estensione delle stesse. In tal modo è stata fatta una completa verifica dei circuiti amperometrici sia esistenti che nuovi inclusa la verifica di buono stato dei TA esistenti (verificati i rapporti, le polarità). Con l’occasione è stato anche razionalizzata una marshalling kiosk esistente dove sono stati rifatti e razionalizzati alcuni cablaggi. In totale l’intervento in sito (montaggio, cablaggio, prove e commissioning) ha comportato un fuori servizio di cinque giorni al temine del quale sono stati consegnati all’Ente Elettrico Kaharama tutti i certificati delle prove effettuate; questo fatto ha permesso di rienergizzare l’intero impianto INNOVATION 12 13