l’industria italiana del Cemento The 3rd International fib Congress Washington DC, May 29 – June 2, 2010 Italian National Report ISSN 0019-7637 ISSUE € 30,00 Research and Construction ASSOCIAZIONE ITALIANA TECNICO ECONOMICA DEL CEMENTO SPECIAL ISSUE ANNO / YEAR LXXX APRILE / APRIL 2010 854 RIVISTA DELL’ASSOCIAZIONE ITALIANA TECNICO ECONOMICA DEL CEMENTO (AITEC) 854 Anno/Year LXXX Aprile/April 2010 Direttore responsabile Managing Editor Laura Negri l’industria italiana del Cemento Contents 3 Foreword (M. Menegotto) RESEARCH SEISMIC BEHAVIOR Collaboratori Assistants Marco Veronesi Grafica e Impaginazione Design & Editing Studio Mariano - Roma Editore Publisher 6 Earthquake Engineering of Reinforced Concrete Structures: The Italian State-of-the-art L. Ascione, E. Cosenza, G. Mancini, G. Manfredi, G. Monti, P. E. Pinto 74 Experimental Research on Seismic Behavior of Precast Structures F. Biondini, G. Toniolo CONCRETE 80 Direzione e redazione: Piazza Guglielmo Marconi, 25 - 00144 Roma - Tel. 06/54210237 Telefax 06/5915408 - E-mail: [email protected] Autorizzazione del Tribunale di Roma n. 301 del 24 Ottobre 1950. Concessionaria per la pubblicità: Idra S.A. Strada Cardio, 4 - 47891 Dogana (RSM) Tel. 0549-909090, fax 0549-909096 e-mail: [email protected] – www.idrabeton.com L’AQUILA EARTHQUAKE 88 Damages of L’Aquila earthquake G. Manfredi 124 Reconstruction between temporary and definitive: the CASE project G.M. Calvi, V. Spaziante Amministrazione: PUBBLICEMENTO s.r.l. - Sede legale:Viale Ettore Franceschini, 37 00155 Roma. Sede amministrativa e operativa: Piazza Guglielmo Marconi, 25 - 00144 Roma Tel. 06/54210237 - Telefax 06/5915408 Fascicolo/Issue 30 € Tutti i diritti di riproduzione sono riservati. Nessuna parte di questa Rivista può essere riprodotta in nessuna forma. La Rivista non assume la responsabilità delle tesi sostenute dagli Autori e delle attribuzioni relative alla partecipazione nella progettazione ed esecuzione delle opere segnalate dagli stessi Autori. All rights of reproduction are reserved. No part of this Magazine may be reproduced in any form whatsoever.The Magazine assumes no responsibility for the theses put forward by the authors or for the authors' indications of their responsibilities regarding participation in the design and construction of the works. Associata all’Unione Stampa Periodica Italiana. ISSN 0019-7637 Stampa/Printed by: Grafica Ripoli snc - Via Paterno - Villa Adriana (Tivoli) In copertina On front cover Pantheon dome, Rome. Inside view State-of-the-art on Research on Structural Concrete in Italy M. Collepardi CONSTRUCTION CIVIL ENGINEERING WORKS 154 188 192 196 200 204 208 212 216 220 224 228 232 236 240 242 244 248 250 254 Italian High-Speed Network. A special focus on concrete structures • HS railway cable-stayed bridge over Po river • “Piacenza” viaduct • “Modena” system viaducts • “Savena” viaduct • “Caivano” variation structures • Tunnels in the Florence-Bologna stretch of High-Speed Line • New stations for Italian High-Speed Network “Colletta” cable-stayed bridge Rio S’Adde viaduct Bridge over Vajont creek “Cesare Cantù” cable-stayed bridge Bridge between La Maddalena and Caprera Islands “Don Bosco” bridge. Architecture, white as light Viaduct for State Road (SS) 23 “Roccaprebalza” viaduct “Sandro Pertini” bridge upgrade Cable-stayed footbridge over the Frodolfo river Bridge over Mazzocco creek Bridge over the Sacco river Bridge over the Santa Caterina channel Bridge over the Cimadolmo branch “Isola della Scala” bridge The “Strada dei Parchi” A24 – Completion of the motorway Roma-L’Aquila-Teramo “S. Antonio” viaduct Viaduct for the Algeria East-West Motorway l’industria italiana del Cemento Contents BUILDINGS 258 262 266 270 274 278 282 286 290 294 298 302 306 310 314 318 MAXXI – Center for the contemporary arts “Olympic Palavela” New Bocconi University Milanofiori 2000 – Corporate Center “Acqua minerale San Benedetto” plant New Sky Italia Headquarters Light Pavilion Agenzia Spaziale Italiana new headquarters “Altra Sede” for the Regione Lombardia New “Sant’Anna” Hospital “Verdi” Theatre Banca Lombarda Center Boglietti Palace “Cuore immacolato di Maria” parish complex “San Giovanni Battista” parish complex “Somada” Business Center Edited by A.I.C.A.P. (Associazione Italiana Calcestruzzo Armato Precompresso) and “l’industria italiana del Cemento – ii C” The 3rd International fib Congress Italian National Report Research and Construction Foreword he 3rd fib International Congress takes place during (hopefully towards the end of) a global downturn in the economy. The impact was felt in all fields, including construction industry, and in all countries. Crises are opportunities for rethinking activities and habits. The need to face high costs of materials and production stimulates the search for improvements. This parallels the awareness of further needs, not of immediate return, such as saving resources, building more durable constructions, recover for reuse or recycling at least of materials, or better yet of whole structures or parts of them. Design and construction usually take account of safety and economy but more and more they consider too service life requirements, products’ life cycle assessment, resource saving and other environmental issues, in one word, sustainable development. CEB and FIP, now fib, were accompanying and leading the progress of structural concrete design and construction during the past half century and have been a great partner in cultural interchange for our country. AICAP, the national association for structural concrete, mirrors fib and takes advantage also of its actions to contribute in its turn to the dissemination of knowledge and the improvement of practice. Among other initiatives directed toward encouraging engagement in better design and execution, AICAP launched for the first time a national award for the best concrete structures for buildings and civil engineering works, that will be given every second year, and edits this National Report, where a selection of works using structural concrete and completed in Italy in the last four years is illustrated, among which both 2009 award winners. Rome’s Pantheon is the exception, with its record 43.4 m dome shown on the cover, cast altogether 20 centuries ago, using a lightweight concrete quite similar to the modern one. Research is playing a decisive role in advancing techniques to fulfil new requirements and has progressed in Italy during these years, promoted also by the industry, more sensitive to it while under pressure of the crisis. Therefore, this Report also describes some results related to the national state of the art. Italy is a highly seismic country, thus most researchers in recent past have worked in the field of seismic engineering, aiming at better design of new structures as well as at assessing and retrofitting older ones. Unfortunately, one year ago this science was called to prove its ability after the L’Aquila earthquake. The authors of the articles in this Report were personally involved also in the field operations. Their contributions helped the surveys in the immediate post-event days, the directives for the repairs and the implementation of the CASE project. The latter has represented quite a successful system response, up-to-date and praised worldwide, that provided a large population of homeless with sets of permanent houses, built in few months on seismically isolated platforms, located in sites purposely selected and equipped in the city neighbourhoods. AICAP is then glad to present the 2010 National Report, which comes in to being too thanks to the renowned magazine ii C, which is publishing this special issue, in spite of the difficult times. T Marco Menegotto Head of the Italian delegation to fib iiC•4/2010 3 RESEARCH Earthquake Engineering of Reinforced Concrete Structures: the Italian State-of-the-art his extended paper summarizes part of the results, those related to reinforced concrete (RC) structures, of the largest research program on earthquake engineering ever held in Italy. The ReLUIS project funded by the Department of the National Civil Protection granted 15.000.000 € and involved more than 600 researchers all over the country between 2005 – 2008. The ten research tasks (lines) ranged from the seismic risk of existing structures to new design paradigms, including geotechnical earthquake engineering issues and innovative approaches to seismic risk reduction as earthquake early warning systems as well as emergency management. In the following the ReLUIS research lines regarding: (I) assessment of existing RC buildings (Line 2); (II) bridges (Line 3); and (III) retrofit of RC structures via innovative materials (Line 8), coordinated by the authors, are described in their development and findings. The three section of the paper are structured as stand-alone, including their own introduction, conclusions, vision and references, for readability purposes. More details, references and products of the project may be found in the research section of the ReLUIS website (http://www.reluis.it/). Because of timeliness of the ReLUIS project and the involved scientists, the work described in the following is likely to express the state of the art of earthquake engineering concerning reinforced concrete structures in Italy. T I - ASSESSMENT AND REDUCTION OF THE VULNERABILITY OF EXISTING REINFORCED CONCRETE BUILDINGS 1. INTRODUCTION Research Line 2 focuses on the assessment of the seismic performance of existing reinforced concrete buildings, covering a wide spectrum of problems, each one treated within a single Task. These aspects span from those related to the preliminary knowledge phase, to the use of nonlinear assessment methods, while placing emphasis on peculiar modeling problems, such as those related to the presence of stairs, infills, beam-column joints, and biaxial behavior of the elements. The Research Line is also devoted to the study of mixed-type (masonry/RC) buildings and of prefabricated industrial buildings. The following Task list collects and organizes the entire scientific activity: 1–MND: Non-Destructive Methods for the Knowledge of Existing Structures 6 2–FC: Calibration of Confidence Factors 3–IRREG: Assessment of the Nonlinear Behavior of Buildings, with Emphasis on Irregular Ones 4–MIX: Assessment and Strengthening of Mixed-type (Masonry/RC) Buildings 5–TAMP: Influence of Infills on Structural Response 6–SCALE: Behavior and Strengthening of Stairs 7–NODI: Behavior and Strengthening of Beam-Column Joints 8–BIAX: Behavior and Strengthening of Columns under Combined Axial Load and Biaxial Bending and Shear 9–PREFAB: Behavior and Strengthening of Prefabricated Industrial Structures For the sake of clarity of exposition, given the large variety of different subjects, the structure of the paper, in each of its sections, follows the Task organization above. 1.1 MND: Non-Destructive Methods for the Knowledge of Existing Structures Task MND specifically focuses on the knowledge of the constituent material properties of Reinforced Concrete (RC) existing structures. Particularly, Task MND is devoted to the estimation of the in-situ concrete strength by using destructive and non destructive methods. Data on material properties from several in-situ and laboratory investigations were collected and analysed with the major objective of defining reliable as well as not very expensive procedures and criteria for the estimation of the in-situ concrete strength. Further, methods for the treatment of the uncertainty that characterizes experimental data obtained through in-situ and laboratory investigations were analysed and some theoretical simulations of the influence of material properties on the seismic capacity of existing buildings were carried out. 1.2 FC: Calibration of Confidence Factors A fundamental phase in the assessment of existing reinforced concrete buildings and in their strengthening design is the knowledge process that one has to follow to acquire the necessary information. This is based on the collection of different kinds of information regarding: a) the structural system configuration, b) the materials strength, c) the reinforcing steel details, and d) the conditions of the structural elements. The Italian Code (OPCM 3431, 03-05-05, Annex 2) as well as the most advanced International Codes (FEMA 356, EC8 Part 3) specifies data collection procedures about the configuration of the structural system, as well as material strength and condition of the structural elements comprising the building, and ensuing Confidence Factors (CF) to apply to the mean values materials properties, based on the quantity and RESEARCH - Seismic behavior Luigi Ascione1, Edoardo Cosenza2, Giuseppe Mancini3, Gaetano Manfredi2, Giorgio Monti4 and Paolo E. Pinto4 Università degli Studi di Salerno, Fisciano (SA), Italy degli Studi “Federico II”, Naples, Italy Politecnico di Torino, Turin, Italy 4 Sapienza Università di Roma, Rome, Italy 1 2 Università 3 quality of the information gathered (the so called Knowledge Level). In the current approach, the CFs are given through tables. Aim of the Task has been: a) evaluation of CF effects on the assessment of buildings seismic performances; b) development of a procedure for the evaluation of concrete and steel strength, to be reliably used in assessing members capacity; c) new definition of CF, evaluated by a closed-form equation as a function of number, kind and reliability of each testing method employed, and of the reliability of prior information. 1.3 IRREG: Assessment of the Nonlinear Behavior of Buildings, with Emphasis on Irregular Ones Task IRREG deals with problems related to the definition of plan and elevation irregularity and the effects of irregularity on the structural behavior and its prediction though different methods of analysis provided by the current design codes. More specifically, the main focuses of this tasks are: a. Study of the definition and effects of plan irregularity on the response of RC buildings up to the Ultimate and Collapse limit states; b. Comparison and calibration of different linear and nonlinear methods for reinforced concrete structural members, with emphasis on pushover and nonlinear dynamic analyses; c. Comparison between research-oriented and professional-oriented structural analysis software, in order to identify analytical tools that satisfy both modeling precision and computational speed. 1.4 MIX: Assessment and Strengthening of Mixed-type (Masonry/RC) Buildings The work has been developed on the evaluation of the seismic response of mixed-type buildings behaving as parallel systems, with regard to both local (interaction between masonry and RC elements) and global features, by performing a series of non linear numerical analyses. The research activity has been focused on: a. the classification of the main geometrical characteristics of such kind of buildings and the study of their response – behaving as parallel systems – subjected to horizontal forces; b. the problems concerning the modelling of mixed-type buildings and on the distribution of the seismic action between masonry and reinforced concrete elements by performing a series of numerical analyses obtaining the capacity curves of individuals resistance elements and the building as a whole. 1.5 TAMP: Influence of Infills on Structural Response Several theoretical and numerical analyses, and, above all, the damage distributions on buildings that have suffered an earthquake show that RESEARCH - Seismic behavior masonry infills can modify substantially the expected seismic response of framed structures although special devices connecting the infill panels with the surrounding meshes of frame are not applied. In spite of that, most seismic codes (the more recent too) give some provisions in order that the resisting elements of frame bear the unfavourable effects of a non-uniform infill distribution in plan or/and in elevation, but they do not suggest any procedure to quantify these effects or the favourable lateral stiffness and resistance contributions that infills give when they are uniformly located. This gap occurs since the influence of the masonry infills on the seismic response of framed buildings is a still open research topic, where univocal and general results do have not been achieved. The present study refers to this subject with the following main objectives: - mechanical characterization of the masonry infill kinds that are commonly utilized in the Italian country by means of experimental tests on their components (resisting elements and mortar) and masonry samples; - experimental investigation on infilled meshes of RC frames, with the aim of calibrating a pin-jointed equivalent diagonal strut model. A companion study has also been devoted to verifying the influence of the infills on the seismic response of RC framed structures; for this purpose, shaking table tests on a 1:2 scaled 3D building and numerical nonlinear analyses of multi-storey frames have been carried out. 1.6 SCALE: Behavior and Strengthening of Stairs The main objectives of this Task are the following: Identification of the main stairs typologies used in the past construction practices; Numerical investigation of the influence of the stair substructure on the structural seismic response. In particular, both global and local seismic performance have to be investigated with reference to frame and stairs members connections; Construction of building sub-assemblages, including a stair substructure, for experimental tests execution, specifically targeted at understanding their seismic performance. 1.7 NODI: Behavior and Strengthening of Beam-Column Joints This Task aims at investigating the experimental behaviour of RC structural members, particularly beam-column joints without or with strengthening, thus providing a contribution to a more reliable evaluation of the seismic vulnerability of RC existing buildings. In particular of great interest is the understanding and the validation of capacity models relevant to the joint panel zone in beam-column sub-assemblages reported in the literature and in seismic codes. Further, there is a need of knowledge in the field of strengthening and retrofit systems that can be used taking into account the actual geometry of joints: e.g. presence of slab and other framing elements that could prevent an effective arrangement of the retrofitting system. To this purposes, wide 7 bibliographic research on the experimental investigations on beam-column joints and on different repairing/strengthening techniques as well as experimental researches on different joint specimens have been carried out. 1.8 BIAX: Behavior and Strengthening of Columns under Combined Axial Load and Biaxial Bending and Shear Modern approach to safety assessment of existing reinforced concrete structures and design of strengthening interventions, in particular those aimed at increasing ductility of columns, are based on enhanced and complex methods for structural analysis (seismic demand), but also on the availability of data concerning performances of members at failure (seismic capacity). On the other hand, common constructions are not necessarily affected by regular shapes and/or regular distribution of seismic resistant substructures, so that seismic actions result in complex deformation paths on columns and in general on compressed resisting members. This is the reason why Task BIAX research activity has been devoted to provide an insight on the response of r.c. members subjected to biaxial bending and axial load. In particular, some aspects have been analysed in detail. In compliance with the overall objectives of the research programme as a whole, Task BIAX duties were the definition of a set of reliable and well documented data and procedures concerning: (a) rotation capacity of r.c. members subjected to generalised bending and axial forces; (b) development of simplified methods of analysis for general r.c. cross sections for design safety checks; (c) development of refined methods for assessment of generalized moment-curvature relationships of cross sections; (d) extension of results to r.c. members reinforced with FRP materials. 1.9 PREFAB: Behavior and Strengthening of Prefabricated Industrial Structures The assessment and reduction of seismic vulnerability of a widespread category of precast structures typically used for industrial buildings is a topic of high importance. The production of these structures starts since from the years ‘50s of last century with elements and construction solutions which had a relevant evolution through the subsequent times. It is a social important interest to know the state of this wide building heritage with respect to its seismic vulnerability so to address, following rational criteria, possible interventions of upgrading of inadequate structures. 2. BACKGROUND AND MOTIVATION The essential motivation for each Task stems from recognizing some 8 gaps in the code, related to certain procedural and methodological aspects in the seismic assessment of existing buildings. Specifically, for Task MND, it is noted that, in the case of non-destructive testing, a lack of clearness exists about the relative importance of such tests with respect to destructive ones for the evaluation of material properties. The data acquisition modality has immediate consequences on the calibration of Confidence Factors, treated in Task FC, which may assume different values from those given in the code, in case one accepted to include results from non-destructive tests in addition to – or even in substitution of – destructive ones. Moving to the level of analysis methods for seismic safety evaluation, the need of a deeper insight into the usual assessment techniques is recognized, with particular emphasis to their predictive capacity when dealing with irregular buildings, dealt with in Task IRREG. It would be expedient to identify, for example, a synthetic parameter capable of quantifying the level of irregularity and, possibly, an associated applicability threshold that helped selecting the most appropriate assessment method, be either of simplified nature, such as pushover analyses, or more refined, such as nonlinear dynamic analyses. For mixed-type (masonry/RC) buildings, the lack of code provisions, which could guide the designer towards the assessment of the compound behavior in a unitary manner – also accounting for interface actions between different constructive typologies – , is absolutely striking and appropriate methods and provisions should be identified in Task MIX. A different remark is needed for the influence of infills on the structural response, where the motivation for the research carried out by Task TAMP stems from the absence of code provisions to account for the meaningful interactions that develop between infills and structure, with significant effects, both, at the global level (behavior factors), and at the local level (collapse mechanisms induced by the presence of localized forces). The following three Tasks SCALE, NODI and BIAX, related to stairs, beam-column joints, and biaxial behavior of columns, respectively, deal with three aspects where the need of providing the designers with operational tools is imperative, especially for as regards the assessment of the capacity of such elements. In the first case, the motivation is to obtain a deeper insight about the influence of stiffening elements – the stairs – on the structural response. Generally, when modeling the resisting system, these elements are either neglected or modeled with unacceptable simplifications. In the second case, that relative to beam-column joints, it is necessary to develop more accurate capacity models, accounting for the joint panel behavior, but also for the presence of secondary phenomena significantly modifying the resisting mechanism, RESEARCH - Seismic behavior such as concentrated forces ensuing from hook-bent bars, or bond-slip in rebars. In the third case, that of biaxial behavior of columns, the motivation for research stems from the awareness that the capacity equations currently available in the code are calibrated on the monoaxial behavior, besides, without interaction with shear. Finally, for the prefabricated structures studied in Task PREFAB, the intention is to provide the normative framework with more complete indications than those currently available, with the objective of bridging the current information gap through the proposition of specific guidelines for the seismic assessment and strengthening of such buildings. The above considerations are expanded in the following sections. 2.1 MND: Non-Destructive Methods for the Knowledge of Existing Structures Modern seismic codes require that a knowledge level (KL) is defined (e.g. 3 KLs in EC8 part 3: limited, normal and full knowledge) in order to choose the admissible type of analysis and the appropriate confidence factor values in the evaluation. Among the factors determining the KL, there are the mechanical properties of the structural materials. In RC structures, the compressive strength of concrete has a crucial role on the seismic performance and is usually difficult and expensive to estimate. Reliable procedures to take into account the factors influencing the estimation of in-situ concrete strength, particularly in case of poor quality concrete, are not currently available. According to various codes (e.g. in Europe EC8-3, in Italy NTC 2008) estimation of the insitu strength has to be mainly based on cores drilled from the structure. However, non-destructive tests (NDTs) can effectively supplement coring thus permitting more economical and representative evaluation of the concrete properties throughout the whole structure under examination. The critical step is to establish reliable relationships between NDT results and concrete strength. The approach suggested in most codes (e.g. in EC8-3) is to correlate the results of in-situ NDTs carried out at selected locations with the strength of corresponding cores. Thus, NDTs can strongly reduce the total amount of coring needed to evaluate the concrete strength in an entire structure. 2.2 FC: Calibration of Confidence Factors Data collected for the assessment of a building are obtained from available drawings, specifications, and other documents for the existing construction, and must be supplemented and verified by on-site investigations, including destructive and nondestructive examination and testing of building materials and components. As a function of the completeness of as-built information on buildings (Knowledge Level) the Italian Code specifies different analysis methods and Confidence Factors (CF) to be applied to the mean values of mateRESEARCH - Seismic behavior rials strengths. Difference in the knowledge procedure about the single structural parameters and the actual possibility of propagation to the structure as a whole of information gathered on single members unlikely can be accounted for by a single CF to be applied to mean materials strength values. Material strength is characterized by, both, an intrinsic spatial variability and an epistemic uncertainty, caused by either workmanship (for instance not compliance with the original project, execution of structural elements in different times with different materials strength), or reliability of testing methods, or degradation of material properties with time, or a combination of the former. On the other hand, amount and detailing of reinforcement, defective detailing, etc., neglecting the intrinsic uncertainties, are characterized by epistemic uncertainties only, mainly due to lack of the original project and/or not compliance with it; collected data on one structural element are certain but do not allow to eliminate uncertainties about other elements. Objectives of recent studies (Franchin et al. 2008, Jalayer et al. 2007) have been the evaluation of the effect of CF on the assessment of the structural reliability and new proposals for calibration of a CF. 2.3 IRREG: Assessment of the Nonlinear Behavior of Buildings, with Emphasis on Irregular Ones Many of the existing RC structures were built without accounting for seismic actions, thus much attention has been paid in recent years to the development of reliable methods of analysis and assessment. Linear methods seem inappropriate in most cases; many current seismic codes and guidelines include provisions for nonlinear analysis (Eurocode 8, 2003a, EuroCode 8, 2003b, FEMA 356, 2000, ATC-40, 1996), which seems to be the natural choice for existing structures subjected to moderate and strong design earthquakes. This is obviously a big issue in Italy, a seismically active country where many buildings were erected in the ‘60s, ‘70s and ‘80s usually accounting for only gravitational actions. Furthermore, the new seismic zonation classifies areas previously considered non-seismic as seismic, thus new assessment are needed even on recently built structures. Following the publication of the most recent Italian Seismic Codes, the ReLUIS program of the Italian Department of Civil Protection intends to validate and improve the new code, to propose alternate procedures when deemed necessary, and to provide practical examples to practicing engineers. These activities are particularly important for new methodologies, such as nonlinear methods of analysis. Focus of these studies is not only the application of the nonlinear methods of analysis, but also the use of the results of the nonlinear analyses to assess the seismic vulnerability of structure. 9 2.4 MIX: Assessment and Strengthening of Mixed-type (Masonry/RC) Buildings From the early 20th-century the combined RC-masonry buildings widely spread in European, Mediterranean and Southern America countries. Despite the diffusion of this combined building typology, the international guidelines have not followed building evolutions; nowadays, international guidelines are not exhaustive to deal with specific problems of this building typology, such as: horizontal loads repartition, connections between different technology elements and over strength factor. The Argentinean guideline (NAA-80) points out the fundamental role performed by slab, on the base of the own relative stiffness, for sharing seismic action between vertical different technology resistant elements. During the years, the Italian guidelines have provided discordant indications. The Italian guideline (D.M. 1996) suggested to assign the total seismic action to masonry walls in the case of new buildings, while for existing buildings, the combined RC-masonry buildings should be considered as structural elements typology that prevalently supports horizontal loads, generally masonry walls. Regarding masonry buildings, the Italian guideline (O.P.C.M. 3431) allows to employ different technology elements to support gravity loads, only if the seismic action is fully supported by elements with the same technology. In the need to consider the collaboration of masonry walls and different technology systems to sustain the seismic action, a nonlinear analysis should be carried out according to O.P.C.M. 3431. The latest Italian code (D.M. 2008) confirms the instructions provided by O.P.C.M. 3431 by which the real structural system should be considered with particular attention to, both, stiffness and strength of the slabs, and the connections effectiveness between the structural elements. 2.5 TAMP: Influence of Infills on Structural Response The very numerous papers that concern the behaviour of infilled frames are quite uniformly distributed within the last forty years (Figure 1a). This subject has kept topical mainly because of the following reasons: - different materials that can be utilized for the infill panels; - difficulty in modelling the frame-infill interactions; - high number of parameters governing the lateral response of an infilled mesh of frame. It follows that the models that have been proposed by different researchers are strongly related to the kind of masonry infills that were examined and to the experimental tests validating the models themselves. As regards this, Figure 1b shows how the section of the equivalent diagonal strut by different authors is differently related to the same synthetic parameter lh’, which depends on the geometrical and 10 b a Fig. 1- a) Main published papers ; b) Ratios w/d proposed by different authors. mechanical properties of the two sub-systems (frame and infill). In the figure, w denotes the height of the section and d is the diagonal length of the infilled mesh (Refs. 3-7). Further discordant results can be found considering models including the post-elastic hysteretic behaviour. Therefore, the main motivation of the present study lies in the nonavailability of an univocal approach, able to define an appropriate infill model depending on the properties of the masonry utilized. 2.6 SCALE: Behavior and Strengthening of Stairs In general the presence of a stair creates a discontinuity in a regular reinforced concrete skeleton frame made of beams and columns; in fact, from the geometrical point of view, a stair is composed by inclined elements (beams and slabs) and by short (squat) columns. These elements contribute to increase the stiffness of the stair due to the elastic behaviour of inclined elements and of squat columns. For these reasons the elements that constitutes the stair are often characterized by a high seismic demand: the squat columns are subjected to high shear force that can lead to a premature brittle failure; the inclined beams, differently from the horizontal beam, are defined by high variation in axial forces that can modify the resistance and deformability of all these elements. Although this is well known, no studies have been conducted by researchers to evidence the role of stairs on the seismic capacity of existing RC buildings; the identification of the weakest elements of the structure and the failure type considering the presence of the stairs are of particular interest. In this way, the knowledge of structural solutions and design practice of stairs is an important step in order to define their real geometric definitions and to understand their seismic performances. 2.7 NODI: Behavior and Strengthening of Beam-Column Joints Observation of the damage caused by strong earthquakes on RC buildings designed to resist only to gravity loads showed that the main mechanisms that characterize structural collapses are, beyond the yielding of primary elements such as column and beams, slippage of longitudinal bars in columns and beams and joint failures (e.g. Braga et al. 2001). Based on these observations and on the results of extensive experimenRESEARCH - Seismic behavior tal campaigns, some provisions were inserted in the Italian technical regulations imposing performance criteria for the design of new RC structures placed in seismic zones. The capacity design approach provided by current Italian and European codes (NTC 2008, CEN 2004) aims at preventing brittle failure mechanisms in beam, column and joint members as well as at ensuring a weak beam-strong column global collapse, being more favourable in terms of overall ductility. For existing RC structures, designed without anti-seismic criteria, there is the problem of a reliable assessment of their seismic resistance also in order to identify the more appropriate strengthening intervention systems. Improving knowledge on capacity models, particularly as for typical Italian building structures, is the principal thrust for the research activity of task 7 (NODI) in the framework of DPC-ReLUIS 2005-2008 Project. The workflow in terms of literature review, experimental testing and numerical analysis performed by the RUs involved in the task is, then, finalized to the analysis and validation of the provisions of Italian and European codes in order to improve them and make them more adherent to the reality of the Italian existing RC building stock. 2.8 BIAX: Behavior and Strengthening of Columns under Combined Axial Load and Biaxial Bending and Shear Modeling of reinforced concrete members is really a traditional topic of structural engineering, but some aspects need further development when seismic assessment of existing constructions is concerned. In fact, well-established results for modern concrete structures do not cover a large population of members built with obsolete materials and structural details like smooth bars. This is actually a relevant issue, since bond between steel bars and the surrounding concrete is poor and anchoring mechanical devices can play a relevant role in the development of plastic deformation and therefore of the drift capacity. A number of models characterized by different models of complexity can be found in the National and International technical literature (fib, 2003; Panagiotakos and Fardis, 2001; Park and Paulay, 1975) and provide an estimation of the rotation capacity at yielding and at failure of columns member. However, they generally are able to well represent response of r.c. members where deformed bars are used. Based on such a background, the research on columns subjected to biaxial bending and axial force has been conceived to cover the lack of knowledge at the time of proposal. In fact, advances in seismic Codes and increasing need of data for design purposes can be addressed among the primary motivations of Task BIAX. On the other hand, since tools for the estimation of strength and deformation of bare cross sections were not so consolidated, a specific focus on columns strengthened with FRP materials is certainly of applicative interest. This circumstances confirm the RESEARCH - Seismic behavior rational basis of the research and above all the actual usefulness of its results. 2.9 PREFAB: Behavior and Strengthening of Prefabricated Industrial Structures Precast structures passed through the check of weak and strong earthquakes and have been submitted to a wide specific experimental and theoretical investigation performed in the main international research centres. From these experiences some key aspects turned out to be determinant for the good seismic behaviour of precast structures. These key aspects are listed below: - dry friction supports, not suitable to avoid the loss of bearing; - diaphragm action, important to avoid joint distortions; - lateral supports, necessary to avoid the overturning of beams; - 2nd order effects, to be considered to avoid early collapses; A positive condition of the existing buildings of concern is the possible presence of a bridge-crane which required a structural design with relevant horizontal forces and a proportioning of the columns which could be adequate also for seismic action even in the presumption of low ductility. The regulation in force for the design of structures in seismic zones at the time of construction is obviously a conditioning aspect which affects the seismic capacity of existing buildings. Actions and rules for design have been taken from that regulation which may result inadequate on the base of the today knowledge. The problem concerns the seismic zoning on one hand and the design criteria on the other. 3. RESEARCH STRUCTURE In the following sections, the objectives pursued in each Task are described. 3.1 MND: Non-Destructive Methods for the Knowledge of Existing Structures Research has been mainly focused on the evaluation of the role of the main factors affecting the estimation of the in-situ concrete strength through destructive and non-destructive tests, on the determination of the design concrete strength, on the evaluation of the possible damage on core specimens due to drilling and, finally, on the load bearing capacity of structural members subjected to drilling before and after restoration interventions. Other activities were mainly devoted to analyze the correlations between the various methods and the possible spatial variability of concrete properties throughout the surveyed members. Regarding data collection, a large amount of experimental data from destructive and non destructive in-situ investigations on real strucures were collected and analysed, also through treatment of uncertain vari11 ables with different mathematical nature. In addition to the above topics, the seismic behavior assessment of buildings with structure composed of unidirectional RC frames was carried out by means of nondestructive in situ tests, with the objective of estimating their horizontal load-carrying and dissipative capacity. Finally, another important objective was the evaluation of the dispersion of experimental results from non-destructive measurements based on a critical review of data reported in the literature. 3.2 FC: Calibration of Confidence Factors This Task had two objectives. The first one was to propose a methodology for the calibration of the CF for materials strength, taking into account the uncertainties characterizing existing building and the effects on the reliability of the assessed structural performance. A methodology was also sought for the evaluation of material strength by destructive and non destructive in situ testing methods taking into account the relevant reliability. The procedures were meant to be based on the application of the Bayesian method. The proposed methodology and the equation developed for FC have been validated on several simulated cases and on tests made on several buildings. The second objective was to develop a probabilistic methodology for seismic assessment of existing buildings taking into account explicitly the uncertainties in the material properties and the structural detailing parameters and implementing the available test and inspection results. This methodology may be used for determination of confidence factors. 3.3 IRREG: Assessment of the Nonlinear Behavior of Buildings, with Emphasis on Irregular Ones The main objectives are: Validation of available modelling alternatives for RC buildings, mainly lumped-plasticity and distributed plasticity models, both in commercial and research software. Validation of current methods of analysis for the seismic assessment of existing RC buildings, with emphasis on nonlinear methods and their applicability to plan-irregular buildings. The above validations were carried out through the analysis of several buildings selected by the different research units. Three buildings (shown in Figure 2) were selected as common tested structures: one is a doubly symmetric rectangular building, one is an L-shaped building, and the third is a rectangular building with an internal court. These buildings are representative of the structural buildings commonly found in Italy. Several commercial and research programs were used for the nonlinear analyses, including SAP2000, OpenSees, Midas, etc. The final objective of this task is the compilation of a document that contains: an introduction to nonlinear modeling of RC buildings and to 12 Fig. 2- Tested buildings. the nonlinear methods of analysis of the European seismic codes: a description of the main sources of nonlinearities in existing RC buildings: the application of different modeling techniques to the seismic vulnerability assessment of the three building mentioned above. The document is intended to be a primer for practicing engineers who want to use nonlinear methods of analysis. 3.4 MIX: Assessment and Strengthening of Mixed-type (Masonry/RC) Buildings With reference to the first goal, technical literature and international guidelines have been studied in order to define the classification of the main geometrical characteristics of such kind of buildings and the study of the response of mixed-type buildings – behaving as parallel systems – subjected to horizontal forces. With reference to the second goal, a series of numerical analyses based on different and progressively refined modelling assumptions have been performed in order to investigate the seismic action distribution between different technology elements, changing the size and then the stiffness of the RC elements, but retaining the geometry of the building and comparing the seismic behaviour of the mixed-type building with the original masonry one. Pushover analysis have been performed by using a lumped model to evidence critical zones and possible failures. 3.5 TAMP: Influence of Infills on Structural Response A first experimental investigation was devoted to determining the mechanical properties of three typical kinds of resisting elements, commonly used for infill masonry, and of the mortar utilized for their assemRESEARCH - Seismic behavior bly. Then, several infill samples were subjected to compressive tests by assuming orthogonal or parallel loading directions with respect to the mortar layers. Further results were obtained under diagonal compressive loading, to determine shear modulus and resistance. At the end of this phase, the experimental values of elastic moduli and resistances were compared with the values that Italian M.D. ’87 provides by linking the mechanical properties of masonry elements to those of their components. A second phase of the experimental research was devoted to acquiring the response of square infilled meshes of RC frames subjected to a cyclically varying lateral forces. Two 1:2 scaled samples were tested for each of the three kinds of infill that had been mechanically characterized previously. The results of these tests have made it possible to calibrate the hysteretic model of pin-jointed diagonal strut proposed in Cavaleri et al., 2005. A further experimental investigation was carried out by means of shaking table tests on a 1:2 scaled 3D infilled RC frame, reproducing an actual non-infilled building, previously subjected to pseudo-dynamic tests at the ELSA-JRC-Ispra. These tests had the following objectives: - to quantify the lateral stiffness and resistance contributions that infills can provide; - to verify the influence of the infills on the crack distribution and the collapse mechanism. The same objectives were pursued by nonlinear numerical analyses on multi-storey RC frames subjected to natural seismic accelerograms. These analyses also showed the negative effects of non-uniform infill distribution along the height. Another experimental campaign on infilled r.c. frames (1:1/2 scale), on materials (concrete, steel, blocks and mortar), and on subassemblages (small panels) has been performed. These tests had the objective of calibrating equivalent strut models, through comparison of experimental results on bare and infilled frames, in order to evaluate the infill contribution as well as its uniaxial force-displacement relationship. The constitutive models for masonry infills have been also calibrated in order to predict the cyclic response of infilled frames. 3.6 SCALE: Behavior and Strengthening of Stairs With reference to the first goal, several available manuals and books at the time of construction have been studied in order to define the typology classification and the corresponding evolution of this classification during the years with the increasing knowledge on the use of the materials and of computational machines. An analysis of the codes used from 1909 to the 1980ies has been conducted in details with a critical judgement based on the actual knowledge. Examples of stairs designed for only gravitational loads have been studied with reference to different typologies. With reference to the second point a series of numerical analyses based RESEARCH - Seismic behavior on different and progressively refined modelling assumptions and criteria has been performed in order to investigate the principal failure modes. A critical study has been conducted on the different shear strength formulations present in literature (Biskinis et al.2004; Sezen et al. 2004; Zhu et al., 2007), in order to simulate potential shear failure in squat columns, which can be easily found in most buildings. The pushover analysis by using a lumped model has been performed to evidence critical zones and possible failures. With reference to the third point, a test set-up has been defined in order to investigate the experimental behaviour of a building sub-assemblages, including a stair substructure. 3.7 NODI: Behavior and Strengthening of Beam-Column Joints A wide experimental campaign on beam-column joints representative of typical members present in Italian existing buildings was planned, designed and carried out. In particular, the research activities were devoted to outline the influence of some parameters on the mechanical behaviour and the failure mechanism of the joints, such as axial force, amount of reinforcing steel and earthquake design level. Furthermore, the research focused on the code expressions for the evaluation of the ultimate rotation of RC elements in order to highlight possible discrepancies between the theoretical and experimental results. Another research objective was the analytical modelling of beam-column joints by using DIANA software to analyze the main parameters affecting their seismic performance and, specifically, the analytical modelling of experimental tests conducted on external joints. Other experimental tests on beam-column joints relevant to existing buildings were performed as well, following an experimental program complementary to the above-mentioned one, that is, in this case specimens reinforced with smooth bars were tested and, in some cases, after the first test, joints were retrofitted to evaluate the effectiveness of some retrofit systems. Finally, supplemental activities followed two main branches: on one hand, a series of either reinforced or unreinforced base joints were tested thus evaluating the performance of several strengthening systems, and, on the other hand, a wide database of tests on beam-column joints was built and analyzed. 3.8 BIAX: Behavior and Strengthening of Columns under Combined Axial Load and Biaxial Bending and Shear The activities have been planned to cover four main objectives: (1) review of technical literature with specific reference to available experimental data; (2) development of refined and simplified models for bare and FRP reinforced members; (3) experimental activity on columns subjected to cyclic actions; (4) drafting of a technical report summarizing the main applicative aspects of the work. 13 3.9 PREFAB: Behavior and Strengthening of Prefabricated Industrial Structures The study envisages a preliminary classification of the industrial prefabricated building typologies existing in Italy, from which the most frequent characteristics of element-to-element connection types will emerge. This first cataloguing phase is then followed by a purely experimental phase in which some connections, identified as more vulnerable (e.g., friction connections), are subjected to a series of cyclic tests to simulate seismic conditions. Results and information obtained from the experimental tests will serve as a basis to develop practical models for assessing the capacity of such connection zones and to orient towards the definition of criteria and techniques for strengthening interventions. The main results obtained by each Task are summarized in the following sections. 3.10 MND: Non-Destructive Methods for the Knowledge of Existing Structures The results obtained during the Project are mainly made up by the execution and analysis of experimental investigations either on in situ real structures or on laboratory specimens, by the implementation of some procedures to estimate the in situ concrete strength and by the uncertainty treatment of the structural characteristics of existing strucures. A wide experimental program was carried out, comprising more than 20 RC beam and column members, several hundreds of non destructive tests (NDTs) and more than 50 destructive tests (cores). Analysis of results has shown a large scatter of the core concrete strength both in a single member and among members extracted by the same story of a building. Lower scatters have been detected for the NDT results with the exception of the surface ultrasonic velocity (see Figure 3). As a result of these findings, the role of some factors influencing the in situ concrete properties has been carefully evaluated, and some criteria to suitably select locations for sampling have been provided. A procedure for the evaluation of the concrete strength based on the Sonreb method, using both core and NDT measurements, has been set up and widely validated, clearly showing its higher prediction capacity when compared to the relationships currently available in the technical literature. It requires that the relationship between the in situ concrete strength and the NDT measurements is experimentally derived for the specific concrete under test. As for the possible damage on core specimens due to drilling, the results have shown that the strength reduction suffered by cores can be significantly influenced by the original strength value of the in situ concrete. Consequently, adopting a constant coefficient to take into account drilling damage, as suggested in the technical literature, can determine incorrect results. On the contrary, it appears suitable adopting coefficient values, obtained during the research, which are inversely propor14 a b Fig. 3- Role of past applied loads on in-situ measurements: (a) qualitative bending moment due to vertical loads (a), and (b) test results along the lower part of the extracted beam (rebound number S, direct velocity V, surface velocity Vs, core strength fcore). tional to the core strength as provided by the compression test. Finally, some important results regarding the effect of core drilling on the structural members, performing tests before and after a possible restoration. Further, some factors influencing the relationship between the “local” strength provided by core specimens and the in situ strength of the structural member as a whole, have been highlighted. Regarding the variability of concrete mechanical properties throughout single structural members and among different sampling locations, investigations based on a wide series of experimental data gathered from surveys carried out on structures assessed for seismic vulnerability were carried out. Main results obtained are briefly outlined below: • no general trends have been recognized regarding the spatial variability of the key mechanical properties of concrete throughout column members as a possible result of the combination of the effects of the load pattern and the casting process; • although carried out on members already cracked and damaged, the results of sonic tests are affected by scatters smaller than those deriving by the compression tests on concrete samples; further, the ratio between ultrasonic velocity derived by indirect and direct measures are normally distributed around the average value of 0.75; • rebound tests have confirmed the substantial impossibility of recognizing general trends in the spatial variability of the mechanical properties of concrete and led to values affected by scatters quite similar to the destructive ones. RESEARCH - Seismic behavior Regarding the treatment of uncertainties in determining the characteristics of materials and more generally of existing building parameters, a fuzzy-logic based approach for uncertainty treatment has been set up and a computer code for its implementation has been developed. In addition, the prediction capability of some formulations provided by the current technical literature was verified based on experimental investigations through non-destructive and destructive tests on existing structures. Based on a a critical review of available literature, a database was prepared that collects literature data on non-destructive tests on concrete specimens for concrete grade assessment. Dispersion of experimental results has been estimated and the influence of uncertainties coming from the concrete grade estimation on seismic capacity of RC existing buildings has been investigated. Some results obtained during the project have been reported in papers published on journals and in proceedings of Conferences (e.g. Masi and Vona, 2008; Marano et al., 2008; Olivito et al., 2008). 3.11 FC: Calibration of Confidence Factors A first aim of the task has been the evaluation of the confidence level on structural safety of existing buildings given by seismic structural assessment carried out according to the indications of the Italian OPCM 3431, 03-05-05, Annex 2. Uncertainties in reliability structural analysis are due to material properties, structural details and condition of the structural elements. The prior distribution of the considered uncertainties takes into account their mechanical effects. The proposed probabilistic models are subsequently updated by in-situ information. A parameter describing the structural performance is defined as the demand/capacity ratio and its probability distribution is assessed by a Monte Carlo simulation. Each realization corresponds to an application of the capacity spectrum method and needs the execution of a structural linear static analysis. The Bayesian up-dating of the structural reliability is carried out by a Markov Chain Monte Carlo algorithm. The structural performance prior probability distribution function is evaluated in two different cases: 1) taking into account the uncertainties about material properties and structural details; 2) updating the structural assessment based on in-situ tests and inspections. The updating process consists of two different levels: in the first, destructive tests and relating errors are taken into account; in the second, non-destructive tests and relating errors are taken into account. Structural seismic performance has been evaluated in three cases: a) by using the mean material strength values (CF=1); b) by using the mean material strength values scaled by the CF for a Normal knowledge (CF=1.2); c) by using the mean material strength values scaled by the RESEARCH - Seismic behavior CF for a Limited knowledge (CF=1.35). For each value of the CF the demand/capacity ratio has been evaluated and positioned in the structural performance distribution, for the three knowledge levels, with reference to the structure at hand. The CF value considered as the exact one has been defined as the value corresponding to the demand/capacity ratio value with 5% exceedance probability. In this way, the CF for material strength is evaluated on the basis of the probabilistic evaluation of structural performance taking into account all the intrinsic and epistemic uncertainties, including uncertainties on the testing methods. A simplified method is proposed too, based on a limited number of Monte Carlo simulations, which is able to approximate the probability distribution of the structural parameter. This can be a basis for the development of simple procedure to use in for evaluation of structural safety. A second objective was to develop a procedure for evaluation of material strength and calibration of CF based on the application of Bayesian method, to take into account the number and the reliability of the insitu tests carried out. The Bayesian method allows to employ destructive and non-destructive testing results to update a prior probability distribution function. Destructive and non-destructive testing results are separately employed, taking into account individual testing reliability (reliability due to testing errors and errors in regression curve that provides the material resistance as a function of the testing parameter). More than one test method can be employed performing consecutive up-dating of the probability distribution function. The statistics reliability of the mean value is improved by applying the confidence interval for the mean; a 95% lower confidence level is considered, which represents the value for the structural assessment. In order to facilitate its evaluation, a simplified procedure is defined. The material strength value for structural assessment can be obtained scaling with an appropriate Confidence Factor a weighted mean of the sampling mean values obtained by, both, different testing methods and prior information: m mD = FC 艑 m̆'''inf,m̆f (1) where: m' +n x +n x m = f DM DM NDM NDM 1+nDM+nNDM [ ] (2) where xDM and xNDM are the sampling mean of the destructive and non destructive tests, respectively; nDM and nNDM are the corresponding sampling dimension. Generally, if Mi is the i-th testing method adopted, the material strength 15 for the assessment is: m' + n x m = f i Mi Mi 1+inMi [ ] (3) where xMi is the sampling mean of the i-th testing method and nMi its dimension. The CF can be expressed in an explicit form as a function of the Bayesian coefficient of variation Vm for the median value of the material strength: (4) FC = a+cVwm The parameter Vm, which estimates the reliability of the available information, is defined as: n i 2 Mi 2 ss,Mi+st,Mi sm Vm = m = (5) n x m i 2 Mi M2 i ss,Mi+st,Mi where s2s,Mi and s2t,Mi are the sampling variance and the variance of the regression curve of the i-th testing method, respectively. The Eq. (4) has been calibrated for concrete strength by applying the least squares method. A Monte Carlo method has been used to simulate sampling with destructive and non destructive testing and the resulting equation for the CF is: FC = 0.9 + Vm (6) The Eq. (6) is effective if samples have been extracted from homogeneous zones of the structure. If in the structure potential non homogeneous zones are identified, the t-Student test can be executed on the mean values extracted from the two zones. If the t-student test identify non homogeneous zones these must be separately evaluated considering two different median values for concrete strength with two CF. A method has also been investigated for the evaluation of reliability of the correlation function for the assessment of material strength by in situ tests. 3.12 IRREG: Assessment of the Nonlinear Behavior of Buildings, with Emphasis on Irregular Ones The main results of the project are as follows: • Regarding the validation of the modified pushover procedure proposed by Fajfar (2002), it was found that it is conservative for plan-regular framed structures with respect to NTHA, while it is unreliable for shear wall structures. For irregular frames, multi-modal procedures have to be used in order to improve the accuracy of static non linear analyses. Furthermore, predictions drawn from non linear static analy16 ses were often found un-conservative in terms of interstorey drifts or chord rotations; • A new pushover method that explicitly takes into account the torsional behaviour of asymmetric-plan buildings was defined. The effectiveness of the proposed procedure was evaluated by comparing the seismic demand of selected case studies with that obtained through both nonlinear dynamic analyses and other pushover methods; • The nonlinear analyses on the regular and irregular buildings have shown the importance of damping in nonlinear dynamic analysis. More specifically, as the hysteretic model improves, the damping should be decreased. Furthermore, viscous damping is hard to assign and little or no indications are given in the published literature to guide the user. A value of 2-3% damping for the elastic modes appear reasonable, but no final indications were found; • In NTHA, for both natural and generated accelerograms, the application of the seismic input in the principal directions of the structure may underestimate the demand, the structural demand varies considerably as the seismic input direction changes, more so for natural accelerograms. However, as for the number of input ground motions to use in nonlinear dynamic analyses, enhancements to the EC8 requirements were proposed; • For irregular buildings, pushovers applied in different directions indicated demands and capacities that depend on the direction considered. Partial results on the L-shaped building are shown in Figure 4. • Shear collapse in existing buildings not designed according to the capacity design rules, is often dominant. If only the flexural capacity is modelled, most frames are verified both at the Ultimate and at the Near Collapse Limit State. However, additional checks show that the shear capacity has already been reached on several elements prior to reaching the design accelerations. This indicates the need to use models that consider shear failure too (this is very rare in the available software). Furthermore, early shear failures point to possible retrofitting actions, Fig. 4- Pushover analyses on L-building: Influence of seismic input angle on the demand: displacements (left) and rotation ratios (right). RESEARCH - Seismic behavior such as shear strengthening of beams and columns; • Synthetic expressions were developed that express the plan-regularity of a building with respect to stiffness and strength distributions. Also, simple corrective coefficients were developed to compute the structural demand increase as the structural eccentricity increases. In alternative, a simplified procedure was developed that can help optimize the structural design by producing a plan-regular building; • Severe convergence problems were encountered in commercial codes that use lumped plasticity models. These problems were related to the software limitations rather than the modelling selection. As expected, fibre section models provide a better, more physically-based prediction of the section response. It is however important to extend the model to include shear failure, in order to avoid post-processing of the results; • Different Limit State definitions for performance assessment were considered, such as interstorey drift, plastic rotation and chord rotation. It was shown that different measures lead to different, sometimes very different, capacity predictions. The limits usually assumed for interstorey drift result in larger chord and plastic rotation than limits proposed by the European and American Codes. Furthermore, the procedure provided by Eurocode 8 to compute the chord rotation capacity yields predictions that are very different from those obtained analytically, that is integrating the member curvature throughout the plastic hinge length; • A simplified method for deriving fragility curves and evaluating the probability of failure was proposed. The method is based on an incremental application of the so called N2-Method with natural response spectra, whose irregularity covers the record-to-record variability of the structural response without the need for performing non-linear dynamic analysis. 3.13 MIX: Assessment and Strengthening of Mixed-type (Masonry/RC) Buildings The main activities of the first goal have involved both the literature review of mixed-type buildings and the modelling aspects related to the RC substructure of such structures. A report was produced (Decanini et al., 2006) including the main results obtained in the Task. The work involved the study of 160 papers, as indicated in Table 1. Confined masonry is listed separately to underline the difference in the amount of studies between those constructions and structures in which elements of different technologies (masonry/reinforced concrete) are not bonded. The latter case includes constructions in which masonry and reinforced concrete frames are present at the same level and construction in which reinforced concrete frames are placed in the upper floors only. RESEARCH - Seismic behavior Table 1. Literature review on mixed-type buildings Codes National International 7 15 Damages after earthquake1 National International 16 63 Mixed-type building2 Experimental Analytical studies 7 1 Confined masonry3 Experimental Analytical studies4 27 24 Total 22 Total 79 Total 8 Total 51 Reports and other papers enclosing field observations after earthquakes. Building in which elements of reinforced concrete and masonry are not bonded. Building in which bearing masonry walls are confined by reinforced concrete elements. 4 Analytical studies, including also proposal for design and for the modelling of confined masonry structures. 1 2 3 The main conclusions inferred by the study can be summarized as follows. In many codes the confined masonry structures are taken into consideration, even though usually just empirical dimensional rules are given, while methods for assessment and design are lacking and, when present, they differ substantially from a code to another. Concerning the mixed structures (unconfined masonry), only a small number of codes gives some indications, which are usually about the behaviour factor and/or the distribution of horizontal forces among different structural elements. A similar trend was found also when gathering papers on field observations, experimental tests and analytical studies: a lot of data were found concerning confined masonry structures while just a few were gained about other kinds of mixed structures. In general it is possible to state that confined masonry can withstand to seismic actions, given that materials are of good quality and good constructions rules are followed. On the contrary, some deficiency, such as small amount of transverse steel in columns, high thickness of mortar joint, lack of RC element near the openings, can generate the bed behaviour of this kind of structures. Concerning the mixed structures (other than confined masonry), the main problems which arise in the assessment and design are related to the distribution in plan of the horizontal actions, to the determination of the behaviour factor and to the study of the connections between masonry and reinforced concrete elements. In literature, indications about these points are few and further studies are needed. With reference to the second goal, the main problems concerning the non-linear analyses on RC-masonry mixed buildings have been highlighted. Particular attention has been devoted to the seismic action distribution between different technology elements. The results of the analysis carried out on 3D RC-masonry mixed building (see Figure 5) with external walls and internal frames, underline the fundamental masonry role to withstand horizontal action, while a significant translation increase could be offered by introducing RC frames. This research has shown the growing capacity offered by mixed building to bear the seismic action by increasing the RC elements stiffness. The increasing 17 Fig. 5- Analyzed models (Nardone et al., 2008). RC elements stiffness is significant for the seismic action distribution both in linear and non-linear field. From the analyses it has emerged that, by increasing the stiffness of internal RC frames, the maximum sustainable seismic action of mixed building increases, while the rate of seismic action supported by masonry walls decreases (Nardone et al., 2008). The important slab role in sharing the seismic action between the vertical resistant elements and the importance of slab to perform this function in order to avoid undesirable behaviour of the building has been underlined. In addition to that, concerning the first model, the analyses highlighted that the presence of the RC frame is generally detrimental for the masonry wall. In fact, the resisting total base shear of the mixed system is smaller than that of the masonry wall alone when the contribution of the frame wall is smaller than about 15-20% of the total base shear. Moreover, when the top connection is non effective, hinges develop at the top and the bottom of RC columns. Therefore, it seems appropriate to design the RC elements considering seismic action deriving from the pertinent vertical loads. While, if the connection between masonry and frames are effective, it would be expedient to assign the whole of the horizontal loads to the masonry (Decanini et al., 2008). In general, the analyses performed on the 3D model highlighted the difficulties in modelling the masonry and the connections between different elements (beam-masonry, floor-masonry) and indicated the strong influence on the global structural behaviour of the connections effectiveness. The parametric analyses showed the importance of the masonry tensile strength among other mechanical parameters on the global response and highlighted that the RC elements remain elastic and give a negligible contribution to the overall performance. Finally, the comparison between the mixed structures results and those obtained for the masonry structures confirmed how the practice of replacing masonry walls with RC frames, in the interior of old masonry buildings, can have negative consequences on the vulnerability of the building themselves. 3.14 TAMP: Influence of Infills on Structural Response The resisting elements that were chosen to construct commonly used masonry infills were: calcarenite ashlars, hollow clay brick and hollow lightweight concrete blocks. The results of the compressive tests on the 18 related masonry samples lead to the following main conclusions: i) calcarenite masonry exhibits middle compressive and shear strengths, and ductile behaviour up to the collapse for each of the three considered loading directions; it behaves like an orthotropic material in which the ratio between the two elastic moduli depends on the mortar properties; ii) clay brick masonry is about twice resisting in compression, but ductile behaviour was observed only under diagonal loading, when the shear behaviour of the mortar joints is involved; iii) lightweight concrete masonry has very low resistance capacities along all the loading directions; the results obtained from this kind of masonry were rather scattered, because vertical mortar joints are not provided for, due to the vertical profile of the resisting elements. The experimental values of elastic moduli and resistances showed that the values deduced by the M.D. ’87 provisions are not always reliable. In particular, the shear strength values are strongly underestimated by this code for all masonry tested. The cyclic tests on the infilled meshes of RC frames have made it possible to verify that the cross-section of an equivalent strut can be determined by using the procedure and parameters shown in Amato et al., 2008, where a not negligible role is exerted by the transverse strain ratio in the diagonal direction and the compression level transmitted to the columns after the masonry infills have been constructed. The lateral resistance of the infill can be deduced from the masonry shear strength; this can be translated into a compressive strength to be conferred to the equivalent strut, by means of a suitable criterion taking into account mainly the disconnection arising between frame and infill. Finally, these tests showed that the calibration of the adopted model leads to sufficiently approximate results (Figure 6). The shaking table tests on the 3D scaled building (Figure 7) have been carried out by assuming a natural input accelerogram (Herceg-Novi, b a c Fig. 6- Cyclic tests on infilled RC frames: a) test set-up; b) experimental results; d) validation of model. RESEARCH - Seismic behavior a b Fig. 7- Results of shaking table test (PGA = 0.3 g): a) 3D building; b) crack distributions. Montenegro 1979), scaled to three levels of PGA. These tests showed that: - the fundamental period of vibration of the structure is influenced by the presence of the infills (PGA = 0.04 g); - the crack distribution depends on the location of the infills with opening (PGA = 0.3 g); - the infilled structure bears a PGA value (0.54 g) that proves to be about three times the value that had been deduced by pseudo-dynamic tests on the corresponding non-infilled structure. With regard to the numerical investigation, two series of four-storey and twelve-storey RC frames have been considered. Frames of the first series were designed to bear only gravitational loads; the ones of the second series were designed according to the EC8 provisions. The results lead to the following remarks: - the presence of infills implies greater quantity of input energy for the structure; nevertheless, the infills can dissipate a lot of this energy so that the total balance is favourable to the resisting elements of frame with respect to the case of bare structure; - in the frames of the first series the infills can exert a decisive role towards a seismic event; - in the frame of the second series a non-uniform distribution of infill in elevation would be considered in defining the structural regularity. Finally, the studies regarding the calibration of a three-strut model arrived at the conclusion that this approach is useful for the comprehension of the local behaviour of columns in case of degradation due to infill-induced shear effects. For what concerns response in terms of displacement, single strut models seem to give satisfactory results. Strut parameters can be directly obtained from the mechanical characteristics of infill components, i.e., mortar and blocks. Moreover, a design criterion for a protecting dissipative bracing systems has been developed. The proposed approach allows to define the required minimum dimenRESEARCH - Seismic behavior sions giving the desired interstory drift. The results of this Task, synthetically presented here, are discussed in detail in the final Report of Task TAMP. The following remarks can be made, concerning their use and possible improvement of provisions: the proposed model of equivalent diagonal strut could be utilized for analyses of existing structures designed to bear only gravitational loads; - the expressions proposed by M.D. ’87 would be revised, also including values to be assigned to the transverse strain ratios; - infills would be considered for evaluation of the period of vibration of the structure and definition of structural regularity. 3.15 SCALE: Behavior and Strengthening of Stairs According to the literature, the existing stairs can be classified into two main categories depending on the static behaviour of the stair steps: (i) stairs with steps performing as cantilever beam, stair type A (see Figure 8a), (ii) stairs with simply supported steps stair, type B (see Figure 8b). Generally the stair type B are used worldwide, in Europe and USA, while the stair type A, with inclined beams, are much more adopted in Europe (Tecnica y Pratica del Hormigon Armado, 1989, Reynolds and Steedman, 2002, Guerrin and Lavaur, 1971). According to the USA’s manuals a great scatter in stair structural solutions can be found (Berry, 1999). According to the manual design criteria (Marrullier, 1910; Rosci, 1939; Santarella, 1953, 1957; Pagano, 1963; Migliacci, 1977) stair type A could be designed considering only gravity loads, any seismic actions could not be taken into consideration. The permanent and live loads on the steps generate on the beam element (bs1-bs2-bs3) a torsional moment T and a distributed load producing on the beam shear force V and bending moment M. Each flight step is designed modelling it as a cantilever beam subjected to a distributed load. As it is explained in several dated manuals (Santarella, 1953, 1957; Pagano, 1963), the design bending moment into the beam (bs1-bs2bs3) is evaluated on the basis of different static schemes corresponding to different constraints at the extreme ends of the beam. In particular, two extreme constraint conditions are suggested: full constraint and simply supported. The torsional moment is considered of relevant importance, it leads to add transversal reinforcement (stirrups) along the length of the beam (bs1-bs2-bs3). The adopted values of the torsional moment depend on the hypothesis upon the flexural stiffness of the inter-storey slab: flexible and rigid diaphragm. About stair type B, manuals indicate two limit structural schemes: (i) an horizontal beam full constraint at the end, (ii) an horizontal beam simply supported at the extreme ends. Normally bending moment and shear are the internal forces taken into consideration. In the manuals of the construction time the only severe prescription is regarding the 19 a b Fig. 8- Stair typologies: (a) stairs type A with steps as cantilever beams, (b) stairs type B with simply supported steps. Fig. 9. Results of the push-over analysis in terms of base shear versus roof displacement (Cosenza et al., 2008). design of the steel bars: a reinforcing bar should not bend to form angles that favour pull-out of the concrete cover (Pagano, 1963). The Italian stair design practice during the period 1954-1980 has been analyzed in order to identify the most common typologies and the effective adopted design criteria. As already remarked, according to the dated technical manuals and codes stairs could be designed for only gravity load. The predominant stair type in the studied building sample is type A; the flight steps are cantilever elements constraint to inclined beams having one point of discontinuity in the 53% of the cases, two points of discontinuity in the 37% of the cases and is directly connected to the column without any discontinuity in the 5% of the cases. The stair type B is present in the sample with incidence of 3%. The design practice of the most common type of stairs, composed by flight steps constrained into a beam, is herein studied. The static design scheme has a great scatter; beams were designed considering a maximum moment M+=qL2/a in the midspan with a=12 (30% cases) or a=8 (30% cases), while the minimum moment at the extremes of the beam is obtained with a=12 in most cases (76% cases). Regarding the influence of stairs on the seismic capacity, this preliminary study on the structural typologies of the building sample has evidenced the following problems related to the presence of stairs: distribution of seismic forces (not considered in the design), different modelling design of stair structure, material strengths, element detailing. The structural typology of stairs generally introduces discontinuities into the typical regular reinforced concrete skeleton, composed by beams and columns; in fact, the sub-structure “stair” is an assemblage of inclined elements as slabs or beams. All these elements contribute to increase the stiffness of the stair due to the elastic behaviour of inclined elements and of squat columns. For these reasons the elements that constitute the stair are often characterized by a high seismic demand: the squat columns are subjected to high shear demand that can lead to a premature brittle failure; the inclined beams, differently from the horizontal beam, are defined by high variation in axial forces that can modify the resistance and deformability of all these elements. All these aspects are discussed with a series of analysis on a RC build- ing representative of the studied sample; non linear static analyses (static push over analysis) finalized to the evaluation of the role of the stairs, of their elements and modelling is performed. The building without any stair is defined as reference. Two models have been considered to study stair type A with inclined beams and stair type B having reinforced concrete slab. For each structure, different modelling have been adopted to evidence the influence on the global response of: biaxial bending modelling in the beams of the substructure “stair”; bending moment-axial force (M-N) interaction into the inclined elements (beam and slabs); bending moment-shear (M-V) interaction into the inclined elements and columns. In general, the presence of stair brings to an increase of lateral strength and to a reduction in displacement capacity with respect to the building without stair (Cosenza et al., 2007a). On the contrary, the results have confirmed the need to utilize biaxial bending modelling and to account for the interaction of the different internal forces (Cosenza et al., 2008) as: bending moment-axial force interaction that characterizes the inclined elements, and the bending moment-shear interaction that governs the behaviour of squat columns. Shear failure becomes predominant in the squat columns and in the reinforced concrete slabs and precedes the conventional ductile failure (see Figure 9). 20 3.16 NODI: Behavior and Strengthening of Beam-Column Joints Main results obtained in this Task are made up by the execution and analysis of the experimental program on beam-column joints without strengthening, as well as by the execution and analysis of some tests on strengthened and unstrengthened beam-column joints and on base joints. Numerical-experimental comparisons have been performed, as well, regarding some highly representative test campaigns available in the literature and relevant to some of the tests carried out. A careful literature review was carried out relevant to: (i) experimental programs carried out by other researchers, (ii) joint capacity models, and (iii) code provisions on beam-column joints. A wide experimental program was carried out on full scale external beam-column joints relevant to typical existing RC buildings having RESEARCH - Seismic behavior a b Fig. 10- Test results on a Z2 joint (design for medium seismic zone, low axial load): a) damage pattern at drift=7%, and b) force-drift relationship. different Earthquake Resistant Design (ERD) level. Quasi-static tests have been performed with 3 loading cycles for each drift value gradually increased from 0.25% up to the total failure of the joint. Results showed yielding force equal to about 20 kN for the NE joints (gravity loads only designed), and about 40 kN for both Z2 joints (designed for seismic zone 2, medium seismicity) and Z4 joints (designed for seismic zone 4, very low seismicity), as a consequence of the minimum requirements on reinforcement amount prescribed by the Italian code. Observed failure mechanism in all the joints showed a wide and heavy cracking in the beam, due to the small amount of the longitudinal reinforcing bars as the beams were not loaded by the floor slabs in the considered building model. Joint failure was generally caused by the tensile failure of the reinforcing bars in the beam. A different as well interesting behaviour was displayed by some tests on Z2 joints (Masi and Santarsiero, 2008), where a wide cracking also in the joint panel and a softening mechanical behaviour (Figure 10) were observed, due to the reduced amount of the applied axial force (=0.15). Drift value (coincident with chord rotation value) at failure in the NE joints is about 3.0%, while in more ductile Z2 and Z4 joints, values equal to about 4.5% have been detected. As for the contribution of joint panel own deformations to the total drift of the sub-assemblage, experimental results showed that it is rather low, being always lower than 10% even in the heavily damaged specimens. Further, interesting results have been found by comparing the strength of the joint panel provided by the tests and that one obtained applying the European (CEN, 2004) and the Italian Code (NTC, 2008) expressions to evaluate the capacity of beam-column joints. Results show a good estimation ability of code expressions that have been able to predict which of the specimen was subjected to diagonal cracking of the joint panel. Regarding the ductile capacity, the difference between NE and seismic specimens was lower. In all the tests with high axial load a failure mechanism with extensive cracking of the beam and evident deterioration of the concrete at the beam-column interface has been noted. RESEARCH - Seismic behavior A parallel experimental program was devoted to the test (under imposed increasing cyclic displacements applied to the beam end) of 4 external reduced scale beam-column joints provided with smooth bars, later retrofitted after a first series of tests. For 2 of them only the anchorage of the beam bars had been restored by welding threaded bars to the ends of the longitudinal beam bars and bolting them to steel plates placed on the column external surface. For the other 2 joints, besides restoring the anchorage, also vertical and horizontal carbon fiber fabrics had been applied on the column, below and above the joint panel. Moreover, other 2 real scale beam-column joints were built and tested under cyclic loads, either with or without retrofitting, to evaluate the increase of joint performance. As for the first 4 joints, the restoration of the anchorage of the beam bars proved to be very efficient, since it provided increases in strength up to 300% with respect to not retrofitted joints. The additional carbon fiber reinforcements did not provide noticeable increases in strength, because the cracking of the joint, which would have required the carbon fiber contribution, did not occur. Regarding the other 2 joints, it was observed that the not-retrofitted one attained low strength values due to the lack of steel reinforcement for negative moment in the beam. As regards the joint retrofitted before testing, the carbon fiber fabrics applied on the beam significantly increased both strength and displacement ductility. Additional research activities were mainly focused on experimental tests on full scale RC columns (base joints not-strengthened and strengthened) tested under constant axial load and monotonic or cyclic flexure. The strengthening systems consisted in confinement by partially wrapping unidirectional carbon or glass layers around the element at the base. On some specimens, in addition to confinement, steel angles (in some cases, anchored at the foundation) were placed in correspondence of the member corners. The specimens were designed according to the Italian codes in effect during the ’60s and ‘70s with the aim of reproducing typical dimensions, rebar amount and details common at that time. Main results achieved during the Project are as follows: (i) regardless of the axial load value, the FRP confinement produces significant increases in terms of ductility, especially if a GFRP (glass) jacket is used; (ii) the arrangement of the longitudinal steel angles unconnected to the foundation leads to higher ductility levels than those measured for members strengthened by only FRP systems; this ductility gain is lower for columns tested under n=0.40, even if in these cases the unconnected angles also provide an improvement of the flexural strength; (iii) when the longitudinal angles are anchored to the foundation the flexural strength of the RC columns significantly increases, but a reduction of the available ductility is observed. A numerical-type activity focused on the analysis of the performance of RC beam-column joints through numerical simulations by using the 21 F.E. software DIANA, validated by means of experimental test campaigns available in literature (e.g. by the Shiohara working group) as well as some of the tests performed. In particular, many non linear analyses have been performed on typical existing external beam-column joints as they can be found in real buildings built in the past. The definition of typical deficiencies found in real beam-column joints and the analysis of the main parameters governing the structural behaviour of such joints allowed to highlight some effective strengthening solutions, especially for external joints. Further, such work allowed to validate some theoretical models able to predict the behaviour of both external and internal joints, as well as to validate the expressions proposed by some codes to predict the failure of the joint panel. Some results obtained during the project have been reported in papers published on journals and in proceedings of Conferences (e.g. Masi et al., 2008). 3.17 BIAX: Behavior and Strengthening of Columns under Combined Axial Load and Biaxial Bending and Shear The presentation of the results follows the research outline that has been above discussed. In particular, methodological and numerical contributions are presented separately from the main experimental findings. This choice is actually related to the nature of the results and their impact on applicative aspects of structural seismic design, namely codes and design and assessment practice. In particular, the detailed review of technical literature that has carried out during the early stages of the research pointed out the relevance of the type of reinforcement used for construction of existing buildings. In fact, it has been demonstrated that experimental response of r.c. members can be affected by type of reinforcement, smooth or deformed, and by bond interaction between steel and concrete especially in post-yielding phase. As a consequence, a concrete effort has been devoted to perform a comparative analysis of inelastic performances of members depending on type of reinforcement; this means that both numerical and experimental activities have been calibrated in order to cover at local -strength and ductility of cross sections, bond under static and cyclic loads of rebarsand at global – stiffness and rotation capacity of members-. Results of both theoretical and experimental activities have been published in the context of National and International conferences and meetings. Specific attention has been paid also to continuous education of young engineers and technical updating for practitioners. Diffusion of software packages (free download of executables and tutorials) and research results has been supplied on Reluis website. The first set of results refer to the development of methods for numerical analysis of cross sections subjected to generalised bending and axial 22 force. Different approaches have been proposed by the different teams involved in the Task, comparative analyses have been carried out and multiple applicative perspectives have been covered. A specific software has been developed and made available at the project website (www.reluis.it) for download. It is based on a Fortran language procedure and takes advantage of a user-friendly Visual Basic interface and multiple language platforms. The computational engine of the software has been also used for the development of an extended parametric analysis aimed at the evaluation of the influence of the biaxial actions not only on the ultimate strength but especially on the cross section ultimate curvature. In particular, such influence was studied on square RC cross-section characterized by different values of axial load and geometrical percentage of reinforcement. The study has been developed in order to define simplified analytical formulation to easily predict the ultimate curvature reduction in the case of biaxial bending and axial load with respect to the case of uniaxial bending. Figure 11 gives a view of the program interface (top right), an example of typical results in terms of generalised relationship between the reduction of ultimate curvature compared with the reference uniaxial value (=u,biax/u,uni), normalised axial load and the inclination of the Fig. 11- Effect of biaxial bending on cross section local deformation (Di Ludovico et al. 2008a, 2008b). RESEARCH - Seismic behavior Fig. 12- Comparison between exact (fibre method) and approximate approaches for bare (left) and FRP reinforced r.c. members (right) (Monti and Alessandri, 2008). stress plane angle (top and bottom left) and finally a comparison between simplified and refined results (bottom right). An alternative method has been proposed and implemented. It arrives at defining closed-form equations for performing assessment of existing RC columns with two-way steel reinforcement, under combined biaxial bending and axial load. Starting from the load contour method, an efficient procedure for estimating the strength/deformation section capacity has been developed. In addition, simple closed-form equations for computing section uniaxial resisting moments and ultimate/yielding curvature has been defined. The method has been also extended to cross sections reinforced with FRP, resulting in a very effective guide for fast implementation of results in more general software packages and direct application by structural engineers using easy to manage electronic sheets. Figure 12 shows an example of results that can be obtained according to this design tool, both for bare and FRP-strengthened members and its ability to give reliable results with a reduced computational effort. Another relevant achievement is related to the response of the whole member under axial force and biaxial bending. In particular, the attention has been focused on the development of the actual stiffness of the member depending on the stress level and influence of biaxial bending. A fibre model of the member has been implemented in order to provide recommendations for characterization of equivalent stiffness to be used in elastic analysis. The study carried on has been limited, at the moment, to the definition of the problems which must be taken into account while passing from a cross section to the whole member, Bosco et al. 2008. In this context, it is worth noting the contribution of UNICH that carried out nonlinear analyses of reference regular and irregular reinforced concrete buildings and on problems related to the selection of input ground motion, Canducci et al., 2008. In compliance with the main issues derived from the theoretical analysis of r.c. members and cross sections, experimental activity has been carried out at different scales. RESEARCH - Seismic behavior Fig. 13- Fibre model of the cross section (left), force-displacement curve for a column (center), normalised equivalent stiffness (right) (Verderame et al., 2008a, 2008b). At local scale, a number of bond tests on smooth rebars were devoted to the definition of a constitutive stress-slip law to be used in numerical simulations. Figure 13 reports sample data concerning specimens (left), typical cyclic experimental data (center) and finally the idealized constitutive law calibrated against the test (right). At large scale, eight experimental tests on r.c. square or rectangular full scale columns under constant axial load and uniaxial bending were performed. Monotonic or cyclic action were applied on specimens. Details about the experimental program are reported in Table 2 and Figure 14. Each test was performed under displacement control. Table 2. Summary of experimental tests on r.c. columns UNIAXIAL TESTS - Cross Section BxH (cmxcm) 30x30 30x30 50x30 30x50 Longitudinal Reinforcement 812 812 1212 1212 Steel Rebars type Plain Deformed Plain Deformed Normalized Axial Load, 0.2 0.2 0.1 0.1 Type of action Monotonic Cyclic Cyclic Cyclic Number of tests 2 2 2 2 Primary experimental outcomes clearly indicate that the contribution of the base rotation on the global deformation mechanism is noticeably different in case of columns reinforced by plain or deformed rebars, however, the overall member global deformation and energy dissipation capacity is not strongly affected by the bond performances of the internal rebars. The global deformation capacity in the case of plain rebars, is mainly due to a localized source of deformability at the column foun23 Fig. 14- Experimental tests on columns. dation interface (fixed end rotation), while a more diffused crack pattern along the column end was observed in columns reinforced by using deformed steel rebars. The significant influence of P- effect on the global behavior of specimens has also clearly emerged by the experimental tests; if such effect is neglected, the ultimate rotation recorded on columns reinforced by deformed steel rebars is clearly less than that observed in columns reinforced by using plain rebars. However, due to P- effect the ultimate rotations related to the two different columns typologies is very close. Such result can be explained by considering two main aspects: the higher strength of members reinforced with deformed rebars and the higher slope of the softening branch of the shear-drift curves, if P- effect is considered. A calibration of a numerical model able to take account of specific aspects related to bond of smooth rebars and anchoring end details has been also developed (Verderame et al., 2008c). 3.18 PREFAB: Behavior and Strengthening of Prefabricated Industrial Structures The first activity consisted of a wide survey of the existing buildings produced from the ‘50s up to today and of the rendering in a reasoned way of the investigation results. This activity enjoyed the support of the National Association of prefabrication industries Assobeton which involved ten member companies to provide the design documentation of a number of constructions built in different times. So about 150 project documentations have been collected covering some decades of production. Since information about far times were lacking, this survey has been integrated with the historical memory of some experts, exploiting their knowledge together with the old bibliography of specific journals. From the examination of the project documentations a synthetic description for any building has been recorded in a standard format, summarising its features in a specific form of easy reference. This work led to the printing of the booklet “Precast structures: list of projects of existing buildings” which provides a good evidence of some decades of precast production. A complete catalogue of the different types of precast structures has 24 Fig. 15- FrontPage cover of two produced catalogues on precast concrete buildings. been drafted and published in a specific booklet (Figure 15). Every type has a short description with sketches and indications about the years of production, the regions of destination and the relative diffusion with respect to the global precast production. Some notes are added with indication of possible behaviour deficiencies for seismic destinations. Being a key point of precast construction, special attention has been addressed to the seismic behaviour of connections. Some tests have been performed to quantify their seismic capacity following a standard approach. Five principal categories of connections have been considered: - floor-to-floor connections between adjacent floor or roof elements; - floor-to beam connections between floor or roof elements and the supporting beam; - beam-to-column connections between the beam and the column; - column-to-foundation connections which provide the base support to the columns; - cladding-to-structure connections for the support of the wall panels. Two level of tests have been performed: - particular tests: referred to the qualification of single connectors inserted between two overdimensioned blocks and subjected to the principal action expected in the structural system (Figure 16, left); Fig. 16- Details of testing of structural connection. RESEARCH - Seismic behavior - local tests: referred to the qualification of the connection included between two significant portions of the elements, representing the structural arrangement and subjected to the relevant components of the action (Figure 16, right); Previously a standard protocol for testing has been drafted. It defines the six parameters: - strength: maximum value of the force which can be transferred between the parts; - ductility: ultimate plastic deformation compared to the yielding limit; - dissipation: specific energy dissipated through the load cycles; - deformation: ultimate deformation at failure limit; - decay: strength loss through the load cycles compared to force level; - damage: residual deformation at unloading compared to the maximum displacement; to be measured both by: - push over tests following a monotonic increase of displacement: - cyclic tests following an alternate history of displacements (Figure 17). A number of tests on roof-to-beam connections (8 push-over and 11 cyclic) have been performed. A complete report is available with the results of the experimentation. Three types of steel connectors have Force Fig. 17- Specific energy and cyclic behaviour of the connection. been examined (Felicetti et al., 2008). In parallel, a testing frame has been set up for push over and cyclic tests on beam-to-column connections. The common type with a couple of bars protruding from the column and passing through the holes of the beams is examined both in longitudinal and transverse direction. The experimental test results in terms of force displacement allowed to characterise the connection roof element to beam, as global ductility, ultimate strength and dissipative capacity. In Figure 18, force-displacement curves are illustrated (monotonic test on rigid blocks) comparing the traditional existing connection with a modified solution of the connection. While a brittle behaviour is expected for the traditional existing connection (concrete crash of the beam edges), a ductile behaviour is then obtained if the steel plate in the connection is opportunely reduced. Almost similar conclusions can be obtained for quasi-static cyclic tests as reported in the research reports and papers. Some other tests have been performed on dry bearing in order to measure the friction factor of neoprene pads over the concrete surface and their deformation parameters. Tilting tests and on inclined plane have been made with different levels of normal loads (Magliulo et al., 2008). The comparison between tests results and friction coefficient values provided by PCI Handbook (1999), CNR 10018 (1999), and UNI-EN 1337:3 (2005), is shown in Figs. 19 and 20. In Figure 19 the neoprene compressive stress (s) is reported on the horizontal axis, while the shear one () on vertical axis; in Figure 20 on this axis the friction coefficient is presented. It is evident that PCI Handbook and CNR 10018 curves well approximate the experimental data linear regression curve; this does not happen in the case of UNI-EN 1337:3 curve. However CNR 10018 provides a bit larger friction strength with respect to the experimental results, while PCI Handbook provides larger friction strength only for compressive stress lower than 3 N/mm2. Furthermore, the tests results confirm the light increment of friction strength, which corre- Displacement Fig. 18- Push-over test: comparison of the two different solution (traditional vs. slightly modified). RESEARCH - Seismic behavior 25 sponds to a light decrement of the friction coefficient, as the compressive stress increases. On the base of experimental results, the following relationships for neoprene-concrete friction coefficient are proposed: m= 0.49 if s 0.15N/mm2 if 0.15 < s 5N/mm2 m = 0.1+ s where s is the compressive stress and =0.055 N/mm2; s=5 N/mm2 is the neoprene maximum compressive strength according to CNR 10018. These formulations along with the linear regression curve of tests mean results are plotted in Figure 21: the two curves are almost coincident. Fig. 19- Comparison between compressive-shear stress curves provided by PCI Handbook, CNR 10018 and UNI-EN 1337:3 and tests regression 4. DISCUSSION 4.1 MND: Non-Destructive Methods for the Knowledge of Existing Structures The research activities scheduled within the Task have been to a great extent carried out without significant delays or anticipations, and the main objectives have been achieved. 4.2 FC: Calibration of Confidence Factors The results obtained agree with those expected, concerning the development of a Bayesian procedure for material strength evaluation and the calibration of confidence factors. 4.3 IRREG: Assessment of the Nonlinear Behavior of Buildings, with Emphasis on Irregular Ones The results obtained by the Task are in line with the objectives originally established. Several papers by the different research units have been published or are in press in international journals or conferences. The only problems encountered by some of the units originated from convergence issues in nonlinear codes. This is a well-known problem, but some software failed to converge on a regular basis, thus delaying advances in the research. However, overall, the task followed the schedule of work originally outlined. 4.4 MIX: Assessment and Strengthening of Mixed-type (Masonry/RC) Buildings The Task has pursued the proposed objectives. In particular, aspects of modelling the behaviour of mix-type buildings through non linear analysis have been investigated. These analyses have highlighted the different steps in which the resistant elements withstand the seismic action. The analyses performed allowed the identification of the main parameters affecting the structural behaviour of mixed building and gave indications on feasible modelling and verification criteria. Fig. 20- Comparison between compressive stress – friction coefficient curves provided by PCI Handbook, CNR 10018 and UNI-EN 1337:3 and tests regression curve. Fig. 21- Proposed compressive stress - concrete–neoprene friction coefficient relationship. 26 4.5 TAMP: Influence of Infills on Structural Response The objectives that have been pursued by this research are consistent with the expected ones. Nevertheless, it must be observed that the experimental calibration of the parameters defining the cyclic behaviour of the proposed equivalent diagonal strut model is affected by the following main limitations: - it has been made considering only square meshes of infilled RC frames; - the possible presence of an infill with opening has not been considered. These limitations, due to not sufficient time and resources, did not allow the model to be validated by its use to reproduce the experimentally detected response of the 3D infilled building subjected to the shaking RESEARCH - Seismic behavior table tests. 4.6 SCALE: Behavior and Strengthening of Stairs The Task has pursued the proposed objectives. A detailed investigation of the main stairs typologies and of the most used design procedures have been performed; in particular, a report including the main results was developed (Cosenza et al., 2007b). Numerical investigations have been performed in order to understand the seismic behaviour, and the possible failure mechanisms of buildings having the most common stair typologies. The results have confirmed the need to utilize biaxial bending modelling and to account for the interaction of the different internal forces as: bending moment-axial force interaction that characterizes the inclined elements, and the bending moment-shear interaction that governs the behaviour of squat columns. Shear failure becomes predominant in the squat columns and in the reinforced concrete slabs and precedes the conventional ductile failure. An experimental set-up has been designed on the basis of some simulations performed by using different modelling: dimensions of a single span frame with inclined beam, loads and resisting-wall have been defined. 4.7 NODI: Behavior and Strengthening of Beam-Column Joints The research activities scheduled within the Task have been to a great extent carried out without significant delays or anticipations, and the main objectives have been achieved. 4.8 BIAX: Behavior and Strengthening of Columns under Combined Axial Load and Biaxial Bending and Shear Summary of results reported in the previous sections leads to recognize that the development of the work basically complies with the initial schedule. In particular, as numerical analyses and software deliverables are considered, a good agreement with the program can be addressed. In fact, different approaches and numerical procedures have been set and made available to technical community. They cover at different levels the need of tools for checks required by modern codes in terms of strength and local deformation. This applies both to design and assessment of existing un-strengthened concrete structures and to seismic upgrading using FRP materials. Interaction between groups involved in the study of irregular structures and of use of FRP for seismic upgrading of structures is another positive aspect of the work. When experimental program are concerned, it is worth noting that a relevant contribution to the knowledge of bond mechanisms for smooth bars has been given and an approach to the comparative analysis of performances in terms of rotation capacity of full scale r.c. members with smooth and deformed bars has been accomplished. The work is not RESEARCH - Seismic behavior actually exhaustive, since trial biaxial tests have been designed depending on the findings of the theoretical work, but not completed. This results in the need to extend and validate the results obtained in the context of the present task and give a direct contribution to the development of specific design recommendations for members under combined axial load and biaxial bending. 4.9 PREFAB: Behavior and Strengthening of Prefabricated Industrial Structures The research activities scheduled within the Task have been to a great extent carried out without significant delays or anticipations, and the main objectives have been achieved. 5. VISIONS AND DEVELOPMENTS 5.1 MND: Non-Destructive Methods for the Knowledge of Existing Structures A large amount of RC buildings, both private and public, now placed in seismic zones, were originally designed taking into account only gravity loads and without explicitly provide ductile detailing. An extraordinary rehabilitation program needs to be implemented on such buildings, where an accurate evaluation of the available seismic capacity is important to set up cost-effective interventions. Investigations have a crucial role to adequately know the structure to be evaluated. For this reason, there is an increasing need to set up and put at disposal of technicians and other involved stakeholders sufficiently reliable as well as not very expensive methods to estimate in-situ material properties. Number of tests required to suitably apply these methods have to be as low as possible, thus making the total required budget sustainable to building owners and thus further encouraging their use. To this purpose, the results obtained in this Task confirm that a smart combination of NDTs and direct tests (such as core extraction) gives effective solutions from both the economical and technical point of view. Future research work should be devoted to the following: • Provide methods more and more capable of achieving effective results in terms of prediction capability of concrete properties taking into account both intrinsic randomness and epistemic uncertainty. • NDTs currently available on concrete do not provoke damage on structural members but on some other building components (e.g. partitions, infills, plaster, etc.) thus determining remarkable repair costs: new methods are necessary to make them really not very expensive. • As for reinforcement, taking into account the heavy damage caused by the extraction of steel bars, non destructive methods to estimate its mechanical properties need to be set up. 27 5.2 FC: Calibration of Confidence Factors The work performed by the Task has focused on problems related to the definition of a reliable assessment of structural seismic performance. A probabilistic model for structural performance has been developed and a method for calibration of Confidence Factors has been proposed. Furthermore, a procedure for evaluation of material strength has been developed based on the application of the Bayesian method, taking into account, both, amount and reliability of the in-situ tests performed. In addition to that, with reference to the prior probability distribution of structural detailing parameters, a preliminary list of possible structural defects was prepared, in which, for each defect, a set of possible values and their relative weights are envisaged. To proceed further along this path, the following developments are needed: • A complete procedure should be developed defining all phases of the knowledge process of an existing building. The procedure shall give a CF calibrated on the basis of the distribution of the assessment results conditional on the acquired knowledge. • Further studies are needed regarding the evaluation of material strength values from in-situ non-destructive tests, whose reliability depends on the reliability of the regression curves used to transform the test parameter into a material strength value. • A questionnaire, meant to be addressed to professional engineers as a survey, has been prepared. The results of such survey shall be useful in creating a thorough database of structural defects and their probability distributions. 5.3 IRREG: Assessment of the Nonlinear Behavior of Buildings, with Emphasis on Irregular Ones Several directions for future work have emerged from the project, most of them related to seismic code enhancements: • Further studies for assessing the applicability of nonlinear pushover procedures to plan irregular buildings; • Further studies on different engineering demand parameters, such as interstory drift, chord rotation, plastic hinge rotation, as means for assessing the structural response; • The need for the definition of the damping to be used in NTHA, depending on the model level of refinement. Using 5% damping results in an un-conservative assessment; • A clear definition of spectrum compatible accelerograms (according to EC8) to be used in NTHA; • The need to establish a framework for Performance Based Earthquake Engineering, based on a fully probabilistic approach; • Assessment of the current modelling capabilities for shear failure prediction, with the possible development of simplified approaches that 28 can provide an engineering estimate without adding complexity to the convergence procedure; • Possible guidelines on how to consider other sources of nonlinearities/failures, such as bond-slip, beam-column failure, etc. 5.4 MIX: Assessment and Strengthening of Mixed-type (Masonry/RC) Buildings Considering the obtained results, the development of research aimed at evaluating the seismic behavior of mixed-type buildings can be envisaged as follows: • Establish through non-linear analyses the influence of RC-masonry connections on the global behavior of the building. Particular attention should be paid at intersections between beams and perimeter masonry walls. • Evaluation of q-factors. This objective should be pursued through the implementation of (static and dynamic) non-linear analyses. • Evaluation of the seismic response (numerical and not only) of other structural configurations of mixed-type buildings not included in this study. 5.5 TAMP: Influence of Infills on Structural Response This research gave useful results concerning the effects of masonry infills on the lateral response of RC frames, supported by experimental validations. Possible developments could be aimed to pursue the following further main objectives: • to revise the available empirical expressions linking the masonry properties to those of its components, by carrying out further tests on masonry samples made of other kinds of resisting elements; • to generalize the proposed model of equivalent diagonal strut, by evaluating experimentally the role of factors that have not been considered here: infilled mesh geometry, different compression levels on the frame columns after the masonry infills have been constructed, presence and size of an opening in the infilled mesh of frame. 5.6 SCALE: Behavior and Strengthening of Stairs Considering the obtained results the future research developing would be oriented to the evaluation of the influence of the stair on the seismic response analysing the following aspects: • Experimental assessment of the strength capacity and deformability of squat columns. In this way, the behaviour of squat columns would be better understood considering the large number of models found in literature that are not completely exhaustive for a reliable assessment of the seismic behaviour of reinforced concrete structures. • Experimental evaluation of the seismic response of 2-D and 3-D RESEARCH - Seismic behavior frames with inclined elements and squat columns. The comparison of different test results would allow to evidence the influence of the introduced specific elements such as inclined beams and squat columns. • Numerical and experimental evaluation of the influence of the stair in buildings with different location of infill walls. The numerical analysis would be performed by using static and dynamic tools. This studies would allow the evaluation of the interaction between stairs and infills that are commonly modelled in different manner. 5.7 NODI: Behavior and Strengthening of Beam-Column Joints The behaviour of beam-column joints can strongly affect the seismic global behaviour of RC building structures. Some mechanisms (e.g. concrete cracking, slippage of longitudinal reinforcing bars, etc.) can be responsible of additional deformability, on one hand, while, on the other hand, can alter the capacity design assumptions on the framing structural members (beams and columns) and on the joint member itself. For this reason, research activities need to be increasingly devoted to develop accurate capacity models of beam-column joints to reliably evaluate the performances of RC building structures. Research carried out in this Task already provided important results relevant to the role of the key behavioural parameters of RC beam-column joints, thus giving useful suggestions on the reliability of current code expressions and on possible improvements. However, many other issues need to be further studied regarding both as-built and strengthened joints (already damaged or not damaged), skilfully combining purposely designed experimental investigations, review of experimental campaigns reported in the literature, and accurate numerical simulations. Among others, some future research developments can be recognized as follows: • design and execution of extensive experimental programs on joint specimens having different characteristics (e.g. internal or external, bior tri-dimensional, shape, beam type, etc.) well targeted on the types representative of the Italian and European built environment; • experimental and numerical validation of different strengthening techniques based on the comparison of the relative performance and application limits, particularly dealing with tri-dimensional joints and joints with embedded beams; • codification of test protocols to make possible and promote experimental result exchange. 5.8 BIAX: Behavior and Strengthening of Columns under Combined Axial Load and Biaxial Bending and Shear This Task research activity dealt with a specific, but relevant aspect of seismic design and assessment of r.c. constructions. An effective and RESEARCH - Seismic behavior fruitful approach to the development of tools for the theoretical estimation of strength and curvature ductility of members has been carried out. Flexural mechanisms are clearly identified both at local and global scale and an encouraging capacity of simulation is demonstrated by both static and cyclic proposed models of members with smooth bars. This means that numerical sensitivity analyses can give a positive contribution to an optimized design of an experimental program able to confirm numerical forecasts, show possible points of weakness of the theories and/or give an insight on specific aspects of the behavior under severe cyclic loads. The large variety of existing constructions and the diffusion of smooth bars in many very urbanized areas exposed to seismic risk point out the need to continue the investigation on such type of members and even develop customized strengthening techniques using advanced materials. Despite such positive feedbacks of the research, it is worth noting that further work is strongly recommended to assess: • the behavior of short columns, and • the flexure-shear interaction in presence of smooth reinforcement. In fact, the observed deformation mechanisms can produce effects on the strength and ductility of members subjected to complex forces, like those generated on columns of irregular constructions. 5.9 PREFAB: Behavior and Strengthening of Prefabricated Industrial Structures The experimental campaign and the numerical investigations carried out have highlighted that the most vulnerable buildings are those with disarticulated diaphragm behaviour. However, as emphasised in Palermo et al. (2008), an accurate study on the modelling of connections needs to be done in order to correctly predict the overall response of precast concrete buildings. 6. MAIN REFERENCES 6.1 MND: Non-Destructive Methods for the Knowledge of Existing Structures - Masi A., Vona M. (2008). “La stima della resistenza del calcestruzzo in situ: impostazione delle indagini ed elaborazione dei risultati”, Progettazione sismica, Anno I, No. 1, IUSS Press, ISSN 1973-7432. - Marano G.C., Morrone E., Mezzana M. (2008), “Approccio ibrido fuzzy per l’integrazione e l’interpretazione delle prove non distruttive”, Atti del convegno Valutazione e riduzione della vulnerabilità sismica di edifici esistenti in cemento armato, E. Cosenza, G. Manfredi, G. Monti editors, Polimetrica International Scientific Publisher, Roma, Italy. - Olivito R.S., Spadea G., Carrozzini A., Spadafora A.R. (2008). “Strutture esistenti in cemento armato: controlli e verifiche mediante tecniche 29 non distruttive”. Atti del convegno Valutazione e riduzione della vulnerabilità sismica di edifici esistenti in cemento armato, E. Cosenza, G. Manfredi, G. Monti editors, Polimetrica International Scientific Publisher, Roma, Italy. 6.2 FC: Calibration of Confidence Factors - Franchin P., Pinto P. E., Pathmanathan R., (2008). “Assessing the adequacy of a single confidence factor in accounting for epistemic uncertainty”, Convegno RELUIS “Valutazione e riduzione della vulnerabilità sismica di edifici esistenti in cemento armato”, Roma 29-30 maggio 2008. - Jalayer F., Iervolino I., Manfredi G., (2007). “Influenza dei parametri di modellazione e dell’incertezza associata nella valutazione sismica di edifici esistenti in cemento armato”, Proceedings XII Convegno ANIDIS, Giugno 2007. - Jalayer F., Iervolino I., Manfredi G., (2008). “Structural modelling uncertainties and their influence on seismic assessment of existing RC structures”, submitted to Structural Safety, 2008. - Monti, G., Alessandri S., Goretti, A., (2007). Livelli di conoscenza e fattori di confidenza. Proceedings XII Convegno ANIDIS, Giugno 2007. - Monti G., Alessandri S., (2008). “Confidence factors for concrete and steel strength”, Convegno RELUIS “Valutazione e riduzione della vulnerabilità sismica di edifici esistenti in cemento armato”, Roma 29-30 maggio 2008. 6.3 IRREG: Assessment of the Nonlinear Behavior of Buildings, with Emphasis on Irregular Ones - EuroCode 8 (2003a). Design of Structures for Earthquake Resistance, - Part 1: General Rules, Seismic Action and Rules for Buildings, Draft no. 6. - EuroCode 8 (2003b). Design of Structures for Earthquake Resistance, - Part 3: Strengthening and repair of buildings, Draft no. 3 (Final Project Team – Stage 34), 2003. - Fajfar P. (2002). “Capacity Spectrum Method Based on Inelastic Demand Spectra”, Proceedings of the 12th European Conference on Earthquake Engineering, Paper 843, London (UK). - FEMA 356 (2000). Prestandard and Commentary for the Seismic Rehabilitation of Buildings, Prepared by A.S.C.E., Washington, D.C. (U.S.A.). - ATC 40 (1996). Seismic Evaluation and Retrofit of Concrete Buildings. 6.4 MIX: Assessment and Strengthening of Mixed-type (Masonry/RC) Buildings - D.M. Infrastrutture, 14 Gennaio 2008. G.U. 4-2-2008, N.29, Norme 30 tecniche per le costruzioni. - D.M. Lavori Pubblici, 16 Gennaio 1996. G.U. 5-2-1996, N.29, Norme tecniche per le costruzioni in zona sismica. - Decanini L.D., Liberatore L., De Sortis A., Benedetti S. (2006). Rapporto sui comportamenti, osservati in laboratorio e dopo terremoti severi, sulle prescrizioni di diverse normative, nazionali e internazionali, a proposito di edifici a struttura mista muratura-c.a.. Rapporto di ricerca RELUIS. Novembre 2006. - Decanini L.D., Tocci C., Liberatore L., Benedetti S. (2008). Analisi numeriche non lineari agli elementi finiti su modelli piani e spaziali di edifici a struttura mista muratura-c.a.. Rapporto di ricerca RELUIS. Gennaio 2008. - NAA-80, 1980. Normas Antisismicas Argentinas. - Nardone F., Verderame G.M., Prota A., Manfredi G. (2008). Analisi comparativa su edifici misti C.A.-Muratura. Valutazione e riduzione della vulnerabilità sismica di edifici esistenti in c.a. Roma 29-30 Maggio 2008. MIX-04. - O.P.C.M. n.3431, 2005. Suppl. Ord. n.85 alla G.U. n.107 del 10/05/2005 e s.m.i. 6.5 TAMP: Influence of Infills on Structural Response - Amato G., Cavaleri L., Fossetti M., Papia M. (2008). “Infilled frames: influence of vertical loads on the equivalent diagonal strut model”, Proc.14th WCEE, Beijing, China, CD-ROM, Paper 05-01-0479. - Cavaleri L., Fossetti M., Papia M. (2005). “Infilled frames: developments in the evaluation of the cyclic behaviour under lateral loads”, Structural Engineering and Mechanics, Teckno Press, (21) 469-494. - Decanini L.D., Bertoldi S.H., Gavarini C. (1993). “Telai tamponati soggetti ad azioni sismiche, un modello semplificato, confronto sperimentale e numerico”, Atti 6° Convegno ANIDIS, Perugia. - Durrani A.J., Luo Y. H. (1994). “Seismic retrofit of flat-slab buildings with masonry infills”, Proceedings from the NCEER Workshop on Seismic Response of Masonry Infills-Report NCEER-94-0004, 1-3. - Mainstone R.J. (1971). “On the stiffness and strengths of infilled frames”, Proceedings Institution of Civil Engineers, London, Supplement IV, Paper 7360S, 57-90. - Stafford-Smith B. (1966). “Behavior of square infilled frames”, Journal of the Structural Division, ASCE, 92 (1), 381-403. - Stafford-Smith B., Carter C. (1969). “A method of analysis for infilled frames”, Proceedings Institution of Civil Engineers, London, (44) 31-48. 6.6 SCALE: Behavior and Strengthening of Stairs - Berry R. (1999), The construction of buildings. 5th edition Vol. 2. Blackwell Science. - Biskinis D.E., Roupakias G.K, Fardis M.N., (2004).“Degradation of RESEARCH - Seismic behavior shear Strength of Reinforced Concrete Members with Inelastic Cyclic Displacements. ACI Structural Journal title no. 101-S76. - Cosenza E., Mariniello C., Verderame G.M., Zambrano A. (2007), Il ruolo delle scale sulla capacità sismica degli edifici in C.A. Atti Del XII Convegno Anidis “L’ingegneria Sismica In Italia”, 10-14 Giugno 2007, Pisa, Italia. (in Italian). - Cosenza E., Verderame G.M., Zambrano A. (2007), Rapporto sull’analisi tipologica delle scale e criteri di progettazione statica e sismica. Rapporto di ricerca RELUIS. (in Italian). - Cosenza E., Verderame G.M., Zambrano A.(2008), Capacità sismica degli edifici esistenti in C.A.: L’influenza delle scale, Proc. Reluis2rm08 “Valutazione e riduzione della vulnerabilità sismica di edifici esistenti In C.A.” Roma 29-30 Maggio, E. Cosenza, G. Manfredi, G. Monti Eds., Polimetrica International Scientific Publisher, Isbn 978-88-7699-1255. (in Italian). - Marrullier E. (1910), Guida Pratica per la costruzione degli edifici con speciale riguardo al cemento armato, Editori Torinesi. (in Italian). - Migliacci A. (1977), Progetti di strutture, raccolta delle lezioni tenute presso il Politecnico di Milano negli anni accademici 1966-67, 196768, Parte seconda, Edizioni Masson, Milano. (in Italian). - Pagano M. (1963), Strutture, Liguori Editore. (in Italian). - Perri E. (1966), Ingegneria Sismica, Unione tipografico- Editrice Torinese. (in italian). - Reynolds C. E., Steeedman J.C., (2002). Reinforced concrete designer’s handbook, Spon Press Taylor & Francis Group London. - Rosci L. (1939), Manuale pratico di volgarizzazione del Calcolo del Cemento Armato, G. Lavagnolo, II edizione, Torino. (in Italian). - Santarella L. (1953), Il cemento armato, le applicazioni alle costruzioni civili ed industriali, Vol. II, 13, Edizione Hoepli. (in Italian). - Santarella L. (1957), Il cemento armato, monografie di costruzioni italiane civili ed industriali, Vol. III, 13, Edizione Hoepli. (in Italian). - Sezen H., Moehle J.P., (2004). “Shear Strength Model for Lightly Reinforced Concrete Columns, Journal of Structural Engineering, ASCE November 2004, pp.1692-1703. - Tecnica y Pratica del Hormigon Armado. (1989) Ceac ed. Barcelona.(in Spanish). - Zhu L., Elwood K.J., Haukaas T., (2007). “Classification and seismic safety evaluation of existing reinforced concrete columns”, Journal of Structural Engineering, ASCE. 1316-1330. 6.7 NODI: Behavior and Strengthening of Beam-Column Joints - Braga F., De Carlo G., Corrado G.F., Gigliotti R., Laterza M., Nigro D., (2001). “Meccanismi di risposta di nodi trave-pilastro in c.a. di strutture non antisismiche”, Atti del X Congresso Nazionale “L’ingegneria Sismica in Italia”, Potenza-Matera, Italia. RESEARCH - Seismic behavior CEN Comité Européen de Normalisation (2003). Eurocode 8 – Design of structures for earthquake resistance - Part 3: Assessment and retrofitting of buildings (draft n. 6)”, prEN 1998-3, Brussels. - Masi A., Santarsiero G. (2008). “Sperimentazione su nodi trave-colonna in c.a. progettati con diversi livelli di protezione sismica: primi risultati”, Atti del convegno Valutazione e riduzione della vulnerabilità sismica di edifici esistenti in cemento armato, E. Cosenza, G. Manfredi, G. Monti editors, Polimetrica International Scientific Publisher, Roma, Italia. - Masi A., Santarsiero G., Moroni C., Nigro D., Dolce M., Russo G., Pauletta M., Realfonzo R., Faella C., Lignola G.P., Manfredi G., Prota A., Verderame G.M., (2008). “Behaviour and strengthening of RC beam-column joints: experimental program and first results of the research activity in the framework of DPC-Reluis Project (Research Line 2)”, Proc. of the 14th World Conference on Earthquake Engineering, Beijing, China. - NTC 2008, Decreto Ministeriale 14 gennaio 2008, Norme tecniche per le costruzioni, Suppl. or. n.30 alla G.U. n.29 del 4/2/2008. 6.8 BIAX: Behavior and Strengthening of Columns under Combined Axial Load and Biaxial Bending and Shear - Alessandri S., Monti G. (2008). “Design equations for the assessment and FRP-strengthening of reinforced rectangular concrete columns under combined biaxial bending and axial loads”. Journal Mechanics of Composite Materials, 44 (3), pp. 197-324. - Di Ludovico M., Verderame G.M., Iovinella I., Cosenza E. (2008a). “Domini di curvatura in pressoflessione deviata di sezioni in c.a. – PARTE I: Analisi a fibre”. Proc. Reluis2Rm08 “Valutazione e riduzione della vulnerabilità sismica di edifici esistenti in c.a.” Roma 29-30 maggio, E. Cosenza, G. Manfredi, G. Monti Eds., Polimetrica International Scientific Publisher, ISBN 978- 88-7699-125-5, pp. 629-638. - Di Ludovico M., Verderame G.M., Iovinella I., Cosenza E. (2008b). “Domini di curvatura in pressoflessione deviata di sezioni in c.a. – PARTE II: Valutazione semplificata”. Proc. Reluis2Rm08 “Valutazione e riduzione della vulnerabilità sismica di edifici esistenti in c.a.” Roma 29-30 maggio, E. Cosenza, G. Manfredi, G. Monti Eds., Polimetrica International Scientific Publisher, ISBN 978- 88-7699-125-5, p. 639648. - fib (2003) “Seismic assessment and retrofit of reinforced concrete buildings”. Bulletin 24, ISBN 978-2-88394-064-2. - Bosco M., Ghersi A., Leanza S. (2008). “Force displacement relationship for r/c members in seismic design”. Proceedings of the 14th World Conference on Earthquake Engineering. October 12-17, Bejing, China. - Canducci G., Camata G., Spacone E. (2008). “Problematiche connesse alla descrizione del moto sismico”. Proc. Reluis2Rm08 “Valuta31 zione e riduzione della vulnerabilità sismica di edifici esistenti in c.a.” Roma 29-30 maggio, E. Cosenza, G. Manfredi, G. Monti Eds., Polimetrica International Scientific Publisher, ISBN 978-88-7699-125-5, pp. 327-334. - Panagiotakos T., Fardis M.N. (2001). “Deformation of R.C. members at yielding and ultimate”. ACI Structural Journal, 98 (2), pp. 135-148. Park R., Paulay T. (1975). “Reinforced concrete structures”. J. Wiley and Son, Inc., N.York, 769 pp. - Verderame G.M., De Carlo G., Manfredi G., Fabbrocino G.(2008a). “L’aderenza ciclica in campo elastico delle barre lisce. Parte I: la sperimentazione”, Proc. Reluis2Rm08 “Valutazione e riduzione della vulnerabilità sismica di edifici esistenti in c.a.” Roma 29-30 maggio, E. Cosenza, G. Manfredi, G. Monti Eds., Polimetrica International Scientific Publisher, ISBN 978-88-7699-125-5 - Verderame G.M., Ricci P., Manfredi G., Fabbrocino G. (2008b). “L’aderenza ciclica in campo elastico delle barre lisce. Parte II: la modellazione”. Proc. Reluis2Rm08 “Valutazione e riduzione della vulnerabilità sismica di edifici esistenti in c.a.” Roma 29-30 maggio, E. Cosenza, G. Manfredi, G. Monti Eds., Polimetrica International Scientific Publisher, ISBN 978-88-7699-125-5 - Verderame G.M., Ricci P., Manfredi G., Cosenza E. (2008c). “La capacità deformativa di elementi in c.a. con barre lisce: modellazione monotona e ciclica”. Proc. Reluis2Rm08 “Valutazione e riduzione della vulnerabilità sismica di edifici esistenti in c.a.” Roma 29-30 maggio, E. Cosenza, G. Manfredi, G. Monti Eds., Polimetrica International Scientific Publisher, ISBN 978-88-7699-125-5, p. 617-628. 6.9 PREFAB: Behavior and Strengthening of Prefabricated Industrial Structures - Felicetti R., Lamperti M., Toniolo G., Zenti C., (2008). “Analisi sperimentale del comportamento sismico di connessioni tegolo-trave di strutture prefabbricate”. XVII Congresso C.T.E., Roma, 5-8 Novembre, Italy, pp. 867-874. - Magliulo G., Capozzi V., Fabbrocino G., Manfredi G., (2008). “Determinazione sperimentale del coefficiente di attrito neoprene-calcestruzzo per la valutazione della vulnerabilità sismica delle strutture prefabbricate esistenti”. Proc. Reluis2Rm08 “Valutazione e riduzione della vulnerabilità sismica di edifici esistenti in c.a.”, Roma, 29-30 maggio, E. Cosenza, G. Manfredi, G. Monti Eds., Polimetrica International Scientific Publisher, ISBN 978-88-7699-129-5, p. 717-724. - Palermo A., Camnasio E. and Poretti M., (2008). “Role of Dissipative Connections on the Seismic Response of One-Storey Industrial Buildings”, Proc. of the 14th World Conference on Earthquake Engineering, Beijing, China. 32 II - SEISMIC ASSESSMENT AND RETROFIT OF EXISTING BRIDGES 1. INTRODUCTION he perception of the risk associated to the seismic vulnerability of the transportation infrastructure, and in particular to that of bridge structures, on the part of both the relevant authorities and the profession is a quite recent acquisition in Italy. This is possibly due to the fact that in the last two major events that have struck the Country in the second half of the 20th century (Friuli 1976 and Irpinia 1980) the transportation infrastructure has not suffered significant distress. In particular, in Friuli the construction of highways was just at the beginning. In the Apennine crossing of the A16 highway the bridges did undergo some damage, mainly due to the inadequacy of the bearing devices, but this was promptly remedied by the owner through the systematic adoption of the then innovative technique of seismic isolation. T On the other hand, it can be observed that this delay in the appreciation of the risk is not exclusive to Italy. For example, it is enough to mention that it took twelve years after the spectacular failures of quite modern bridges (Figure 1, left) during the San Fernando (1971) earthquake, for the Federal Highway Administration (FHWA) to publish a first document titled “Retrofitting guidelines for Highway Bridges” (FHWA-ATC, 1983). Still, in 1989, despite of the large retrofit program set up (later proved to be fully inadequate), the Loma Prieta earthquake exposed substantial deficiencies in bridges in California (Figure 1, right). Fig. 1- Damage to bridges during the San Fernando, 1971 (left) and Loma Prieta 1989 (right) events. The situation as briefly outlined above is sufficient to understand that the state of the art on seismic assessment and retrofit of bridges still needs to be advanced in several areas. The research undertaken within this Line of the DPC-Reluis Project aimed at providing a contribution in this direction. The areas considered to be of prioritary interest were assessment methods, retrofit criteria and techniques, abutments and foundations, with the final goal of producing a comprehensive document with guidelines and example applications. This result, which has been achieved, represents the first European document on the topic and RESEARCH - Seismic behavior could be envisaged to form the basis for a future addition to the Eurocodes system. text on the seismic assessment and retrofit of existing bridges. 3. RESEARCH STRUCTURE 2. BACKGROUND AND MOTIVATION Starting from the year 1992 on funding from the FHWA, a vast research program has been undertaken in the US to clarify several aspects related to the seismic assessment and retrofit of bridges. The first product of the above research appeared in 1995 in the form of the “Seismic Retrofit Manual for Highway Bridges” (FHWA, 1995): its further development has led to the “Seismic Retrofitting Manual for Highway Structures: Part 1 Bridges” and the “Seismic Retrofitting Manual for Highway Structures: Part 2 Retaining structures, Slopes, Tunnels, Culverts and Roadways” (FHWA- MCEER, 2005). In Europe the Eurocodes system includes a normative document for the seismic design of new bridges, which is at least partially based on the recent concepts of performance-based design: Eurocode 8 Part 2 (CEN, 2005a). This document, however, is not matched by a companion one covering existing bridges, differently with the situation of buildings, for which such a document is available in the form of Eurocode 8 Part 3 (CEN, 2005b). In the year 2003 a firm change of direction towards the harmonisation with Eurocode 8 has occurred in the Italian normative framework for seismic design. In that occasion the priority was given to the drafting of documents for the design of new structures, both buildings and bridges. A document for existing structures was also introduced, but again limited to buildings. These documents served later as the basis for the production of the seismic chapter of the current Eurocodes-aligned national design code produced by the “Ministero delle Infrastrutture” (DM2008). The need for a document dealing explicitly with the problem of assessing and retrofitting bridges in seismic areas dates back actually to 2003, when the update of the seismic design code was accompanied by the obligation of assessing, within the time limit of five years, all the strategic structures and infrastructures in the Country. Adhering to this obligation and with reference to bridges, with funding from the Civil Protection Department, the National Agency for Roads and Highways (ANAS) has launched a program for the assessment of all its bridge structures. Further, the theme is of pressing interest due to the widespread activity currently ongoing on the Italian highway network to increase its traffic capacity. Within the above context the DPC-Reluis research project, with its Line 3 is intended to respond to the outlined needs, and in particular to that of producing a document to be used as a proposal of a future normative RESEARCH - Seismic behavior The program was articulated into five main tasks: 1) Identification of bridge typologies: Bridge typologies characterising the Italian road- and railway systems were identified through contacts with the main national and regional administrations, as well as with major contractors. In particular, existing contacts were exploited and new ones were established with ANAS, Autostrade, Italferr, RFI, Ferrovie della Calabria in order to acquire detailed documentation on a number of representative structures. 2) Assessment methods: Existing methods developed for the assessment of buildings were extended to the deal with bridge structures, and methods specifically devised for bridges were further developed. The goal was to fine-tune several methods of increasing level of accuracy and required effort to be used according to the importance and size/regularity of the bridge. These include displacement-based linear and non linear static methods, as well as simplified behaviour-factor-based methods. Special attention was also devoted to modelling for non-linear analysis. 3) Retrofit criteria: This task focussed on the specific aspects of the application of traditional and innovative retrofit techniques to structural elements typical of bridges. The program of activity included the execution of an experimental campaign aimed at establishing the effectiveness of alternative retrofit techniques. This task also included the development of seismic isolation solutions to be applied in the retrofit of bridges that were not initially designed to be isolated, as well as bridge-specific seismic isolation design criteria. 4) Assessment of abutments, earth-retaining structures and foundations: Abutments and foundations are often weak elements in existing bridges. The goal of this task was to advance the state of the art in the seismic analysis and assessment of these components, an area still characterised by the widespread use of mostly empirical or conventional approaches. 5) Model applications to bridges of different typologies: It was planned that under this task at least one bridge for each of the main typologies identified under task 1 was to be subjected to a detailed assessment and retrofit design, and then documented in an application manual to complement the pre-normative document. The guidelines and the companion manual represent the main outcome of the project. The five broad tasks outlined above were split into a number of sub33 Table 1. Subdivision of the research activity into tasks and sub-tasks. tasks according to the table below. The table also shows the progress of activity over the whole project duration of three years. The progress achieved during the second year is briefly summarised in the following Table 1. (50+9×100+50 m and tall piers), Bardonecchia bridge (7×42 m) and the Millaures bridge (6×80 m, composite steel-concrete). The second highway, built between 1965 and 1975 shows a greater typological variability, which can be reduced, however, to a few homogeneous sets. Representative bridges are: the Borgotaro viaduct (slab bridge with several interconnections), the Narboreto bridge (4×30 m), the Rio Verde viaduct (2?65+6×95+76 m and very tall piers, h=150 m) and the Roccaprebalza South viaduct (13×45 m and tall piers), Rio Barcalesa (7×43m). As it regards the infrastructure in the Abruzzi region typologies and conditions were monitored along A14 and SS16. Data sheets, consisting of 7 sections that provide location, type, category, geometrical and environmental characteristics, condition, and photographic description, were compiled to catalogue all 52 bridges of the latter road. Bridges were classified according to structural type, material and geometry. The bridge conditions, the piers, and the cracking and vegetative maps were considered. 4. MAIN RESULTS The main results of the research activity are summarised in the following according to the research structure described in the previous section. 4.1 Task 1: Identification of bridge typologies The main bridge typologies on several seismic-prone portions of the Italian railway and road/highway networks have been identified during the first year of activity. In summary, the data collected from various sources (mainly national/regional administrations) pertain to the TorinoBardonecchia-Frejus (TBF) and the Parma-La Spezia (PLS) highways (Politecnico di Torino), the Firenze-Bologna (A1FiBo) portion of the A1 Milano-Napoli and the Apennine portion of the A16 highways (Università di Roma “La Sapienza” and Università di Roma Tre), the Adriatic portions of the A14 Bologna-Canosa highway and of the SS16 Adriatica state-road (Università di Chieti-Pescara), the Roma-Viterbo (RMVT) and Roma-Sulmona (RMSu) railways (Università di Roma Tre), the regional railway and roadway networks of Calabria (Università di Cosenza). Structural typologies characterizing the TBF and the PLS highways are quite different. The first highway, built in between 1983 and 1992, includes rather uniform typologies: a) about 300.000 m2 of precast segmental box girder bridges with pier heights up to 90m and span lengths between 40 and 100m, b) about 200.000 m2 of girder bridges in concrete and in composite steel-concrete with pier heights between 5 and 30m and span lengths between 20 and 80m. Representative bridges are: the Borgone viaduct (20+26×40+20 m), the Ramat viaduct 34 Bridge structures on the A1FiBo and A16 were scrutinised, and a selected number of bridges either representative of the most frequent typologies or significant for their outstanding design was identified. A further screening of the set including these structures and those identified on the TBF and PLS has led to the definition of the final case-studies for the detailed applications and the development and calibration of assessment methods. In the roadway and railway system of Calabria the most common typologies are single-stem or frame piers with full, single-, or multi-cellular hollow-core cross-section; simply supported decks, made up of reinforced or prestressed concrete girders and a cast-in-place RC deck slab. Two study cases were selected for the study of non-conventional protection/retrofit techniques. The first one is the Follone viaduct on the A3 Salerno-Reggio Calabria highway, where the spans have been connected with by means of longitudinal devices, while the second case is the Val di Leto viaduct, on a provincial road, which was recently retrofitted using oleodynamic devices. Finally, the data collected during the survey of the two railway lines RMVT and RMSu, have allowed selection of four masonry arch bridges, two per line, to be used as case-studies for the calibration of analysis methods for masonry bridges. 4.2 Task 2: Assessment methods In summary, Task 1 has shown that the relatively many important RESEARCH - Seismic behavior bridges crossing wide valleys in the mountain tracts of the Central and Southern Apennine (A1FiBo, PLS, A3) represent a negligible percentage of the total bridge stock, made up essentially of bridges with simply-supported decks (prestressed or reinforced concrete girders plus slab) with single stem of frame piers. For this reason a special effort has been devoted to devising a simplified non-linear method suitable for the analysis of bridges with simply-supported decks (Università di Roma La Sapienza). As it regards statically indeterminate bridges (continuous decks) a distinction was made between those with special configuration, for which inelastic dynamic analysis is in most cases the method of choice, and simpler bridges, for which two methods have been thoroughly explored: the Modal Pushover Analysis (MPA) method (Università di Roma La Sapienza) and the Secant Mode Superposition (SMS) method (Università di Pavia). Finally research has also focussed on two more issues, namely the always debated problem of directional combination rules (Università di Chieti-Pescara) and the non linear modelling of seismic protection devices (Università di Cosenza). m = 0.3mpila + mpulv + mimp (1) (m + 0.3mpila)Hp + mimpHimp H pulv m (2) y = 1 yH2 / 3 (3) u = y + (u – y) lp(H–lp / 2) (4) T = 2 mi / k = 2 miy / Vy (5) max= SDe(T) max= SDe(T) 1+(q–1) Tc q T [ ] T Tc o q 1 (6) T < Tc The guidelines and application manual give a detailed description of the method, of the safety verifications of bearings, piers and foundations, and a complete worked-out example. 4.2.2 VERIFICATION OF APPLICABILITY OF MPA METHOD TO BRIDGE STRUCTURES 4.2.1 SIMPLIFIED NON LINEAR METHOD FOR BRIDGES WITH SIMPLY-SUPPORTED DECKS For these bridges it is possible to set up an ad hoc assessment procedure which represents a convenient trade-off between simplicity and accuracy. The reference model is that of a vertical cantilever with a continuous distribution of mass, on top of which rest the pier cap and the deck masses. As long as the pier height is not such as to make higher mode contributions significant, in the transversal direction each pier represents a single-degree of freedom oscillator (see Figure 2a). In the longitudinal direction the entire bridge can also be represented as a SDOF system if seismic restrainers are provided that minimise the relative movements of adjacent decks on top of the pier caps (see Figure 2d). In this case the system has mass equal to the sum of the tributary masses of the piers and resisting force sum of the resisting forces of the piers (assuming that maximum displacements are permitted by the abutments joints). The method consists of a simplified non linear static analysis in which the force-displacement laws are constructed based on the results of moment-curvature analysis of the pier bases (see Figure 2b). The following equations give the tributary mass, Eq.(1), the effective height in the transversal direction, Eq.(2), the yield and ultimate displacement (see Figure 2b and c), Eq.s (3) and (4), the period, Eq.(5), and the corresponding demand displacement, Eq.(6), as for single-mode conventional pushover analysis. The effective height equals the pier’s height in the longitudinal direction. Displacement capacity follows from ultimate displacement with appropriate safety factors. RESEARCH - Seismic behavior The MPA method by Chopra and Goel (2002) has been devised for the analysis of tall buildings. Its applicability as an alternative to inelastic dynamic analysis and adaptive pushover methods for the assessment of a b c d Fig. 2- Simplified non linear method for the assessment of bridges with simply-supported decks. 35 Fig. 3- Longitudinal profile of the Rio Torto viaduct (A1FiBo). • The variation of the lateral load distribution, from one based on the modal (elastic) displacement shape to another based on the (plastic) displacement shape at failure, does not affect appreciably the results. • The best estimate of the displacements by the MPA (i.e. the one derived taking the optimal reference DOFs) matches reasonably well that from TH. It is worth noting that a comparable amount of approximation on the response of the structure is obtained both in the elastic and in the plastic response regimes. This observation, together with the previous one, indicates that the main approximation of the method, i.e. being based on the initial elastic modal vector, may not represent a major limitation. • Differences between the nodal displacements estimated by the MPA with respect to those by the TH are found to be in the order of 15%, independently of the intensity level of the ground motion. Analogous results are observed also for the curvatures at members end-sections, resulting in almost coincident patterns of plastic hinge location and predictions of members failures. Fig. 4- Two piers of the Rio Torto viaduct (A1FiBo). bridge structures has been investigated through its application to the Rio Torto viaduct (see Figures 3 and 4), one of the case studies selected for the project. The structure, built at the end of 50’s, is characterized by thirteen-span twin decks realized with two girders and top slab. The twelve supports consist of a pair of framed piers, one under each deck. Each pier is a multi-storey reinforced concrete frame with variable height, realized with two circular columns of diameter D =120÷160 cm. The results from inelastic dynamic analysis have been taken as benchmark for the purpose. The response has been compared for several intensity levels (to assess the influence on accuracy of the level of nonlinearity in the response) and in terms of different response quantities, both local and global (section curvatures and element displacements). The comparison provided the following indications: • The location of maximum modal displacement is the best choice as the reference degree of freedom (DOF) for estimating the demand on the structure. Each significant mode is therefore characterized by its own reference DOF. 36 For the considered case, the application of the MPA method has shown to lead to fully acceptable results. Such a favourable conclusion still awaits substantiation from a larger number of applications. These results have led to the introduction of the method among the allowed methods in the draft guidelines. 4.2.3 SMS METHOD The Secant Mode Superposition method consists essentially of an iterative multi-modal response spectrum analysis on a structural model with secant stiffness properties and equivalent viscous damping. The procedure can be summarised in the following steps: • Step 0: A starting displacement profile and stiffness distribution are assumed; • Step 1: The stiffness matrix of the equivalent linear structure is assembled; • Step 2: Modal analysis is carried out; • Step 3: Displacement in each vibration mode are obtained either from an over-damped elastic or from an inelastic displacement spectrum; • Step 4: Modal contributions are combined to yield displacement proRESEARCH - Seismic behavior file and moment distribution (different combinations rules were examined); • Step 5: Two response indices are computed, that evaluate convergence on displacement profiles and force distributions, while checking that the structural capacity is not violated. • Step 6: A final response index is obtained as an average of the first two and checking the convergence of the proposed iterative procedure. The method has been thoroughly tested on the six “typological” bridges, with regular and irregular configurations, and different number of spans and span length. Verification of the method is versus non-linear timehistory analysis in terms of maximum deck displacement, and maximum pier shear forces has been carried out. 4.3 Task 3: Retrofit measures The experimental part of the research activity of Line 3 has been carried out at the University of Pavia and of Roma Tre. The two experimental campaigns have focussed with different goals on the testing of piers. The tests performed in Pavia were aimed at ascertain the effectiveness of FRP retrofit measures in order to confine hollow-core piers with insufficient lap-splices, while those performed in Roma Tre were aimed, using large-scale specimens, at the characterisation of the response of frame piers built in the ‘60s. Finally, as it regards masonry bridges, a comprehensive survey of the existing retrofit techniques for this type of structures has been carried out by the University of Genova. 4.3.1 EXPERIMENTAL ACTIVITY ON FRP STRENGTHENING FOR INSUFFICIENT LAPSPLICE Four 1:2 scaled bridge piers were designed with an insufficient overlapping length of the longitudinal bars across the critical zone that should lead to an early loss of the lateral strength due to bar slippage. The built specimens (see Figure 5 left and middle) have the following characteristics: • Hollow-core rectangular cross-section (see Figure 5, right) with external dimensions 800x1500mm and wall thickness of 150mm; Table 2. Considered retrofit materials Material Description SRP 3x2 High Density SRP 12x High Density CFRP High Modulus GFRP Alkali Resistant AFRP High Modulus RESEARCH - Seismic behavior Fig. 5- Pier section and specimens built at the University of Pavia. • Pier height of 6 m (aspect ratio equals 4); •Longitudinal reinforcement: 8010 (rL = 1.05%) with an overlapping length equal to 20 diameters (200mm) at the base of the pier; •Transversal reinforcement: stirrups 6/150mm (rV = 0.38%); • Axial load equal to 1000kN ( = 4.3%) or 2000kN ( = 8.6%); • Concrete Rck400; • Steel FeB44K. The retrofit intervention aimed to restore the tensile stress path from the pier section to the foundation, avoiding at the same time any plasticization of the overlapping region. The new stress path created using longitudinal FRP strips applied to the overlapping region is expected to cause the plastic hinge shift upwards where the longitudinal steel is well anchored allowing for an efficient energy dissipation. During the design phase different possible solutions have been considered concerning the retrofit materials (carbon, aramid or glass FRP), the retrofit geometry (width and length of the region to be retrofitted), the techniques to be used for the anchoring of the FRP strips to the foundation. This was possible employing a numerical FE model developed to predict/reproduce the tests results. Regarding the materials, the final choice was to use carbon FRP (CFRP): the analyses indicated that this material is the only one able to sustain the acting tension forces. Too many FRP layers would have been needed to carry the same force using glass or aramid fibres, affecting the effectiveness of the retrofit intervention. For what concern the geometry of the retrofit intervention, the final solution was to apply longitudinally two C-FRP layers on the four sides of the specimen. As far as the exploitation of the material strength is fu[MPa] 1167 948 3000 1700 2800 e[MPa] 77773 64811 390000 65000 105000 eult[%] 1.50 1.46 0.77 2.62 2.67 Layer thickness [mm] 1.1938 1.1938 0.165 0.23 0.214 37 concerned this choice appears to be questionable since the fibres applied to the pier sides parallel to the imposed motion will not have the same stress as those on the other two sides, but the adopted solution seemed to be the only possibility to assure the maximum stress diffusion across the pier section. It is worth mentioning that even though anchoring 1500kN force to the foundation of the scaled specimen would have been probably feasible using a steel collar fixed to the foundation with some high-strength steel bars taking advantage of the deep foundation of the specimen, moving back to real structures the anchoring to the foundation of the tensile force induced in the FRP by a seismic excitation would have been much more difficult, if not unfeasible. Spreading the tensile force on the four sides of the pier, the anchoring is clearly easier. Between different possibilities initially considered to anchor such force, final choice was to use an anchoring system realised with FRP too. The idea was to employ aramid connectors, normally used to transfer shear stresses. If this solution will be found to be effective, as it seems from its design, multiple advantages will arise both on the economic and technologic sides. Due to external constraints only two piers have been tested within the duration of the project, those without the FRP retrofit in the lap-splice region. The tests confirmed that, as expected, lap-splice with an overlapping length equal to 20 times the diameter of the spliced bars is insufficient to assure the anchoring of the bars (see Figure 6a). The tests also underlined that the effectiveness of the lap-splice decreases while the axial load increases: that is because of the higher stresses and damages (such as partial concrete spalling) in the overlapping region. Figure 7 shows the base shear-top displacement diagrams derived from the performed tests: here the lateral load carrying capacity drops quite quickly because of the bars sliding. The red curves are the result of the numerical model. 4.3.2 FINITE ELEMENT MODELLING CALIBRATED TO THE EXPERIMENTAL TESTS RESULTS Given the large number of seismically under-designed bridges, that need to be assessed and potentially retrofitted due to insufficient lapsplicing, the development of an efficient analytical model to simulate the response of FRP-retrofitted elements was deemed critical. A quite simple though effective finite element model was developed using Seismostruct (Seismosoft, 2006). Figure 8 shows the adopted numeric model. The longitudinal FRP layers have been represented like an element itself. Rigid links have been used to place the FRP at the right distance from the longitudinal axis of the retrofitted member in order for them to be able to give the right contribution to the flexural strength of the pier. Furthermore, each FRP element has pinned connection at both ends in order to be subjected to pure axial load. On the other hand, the FRP wrapping can be modelled in approximation without adding elements to the model, since its main effect is the increased concrete confinement that can be represented by the confinement factor already present in adopted concrete stress-strain representation (Mander, 1988; Martinez-Ruenda and Elnashai, 1997). To tests the effectiveness of the Fig. 8- FRP retrofitted pier model. Fig. 6- Test Set-up (a) and open crack at the pier base during the test with 2000kN axial load (b). adopted finite element model, the behaviour of 1:4 scaled square hollow section piers from previous experimental campaigns (Calvi et al., 2005 and Pavese et al., 2004) has been reproduced through push-over analysis. Fig. 7- Base shear-top displacement diagrams of the two “as-built” pier (a) N = 1000kN (b) N = 2000kN. 38 4.3.3 EXPERIMENTAL ACTIVITY ON LARGE-SCALE SPECIMENS OF FRAME PIERS Large-scale tests on framed piers have been undertaken at the Università of Roma Tre. This typology, characteristic of many old viaducts of the Italian highway system, has been chosen for its high RESEARCH - Seismic behavior Fig. 9- The viaduct “Rio Torto”. beam, (see Figure 11a), a suitable grid of displacement transducers has been placed on this beam, in order to measure the cracks amplitude, in the other two specimens. In the second two mock-up’s a different failure mechanism occurred on the same transverse beam. In particular, during the second test both beam-column joints collapsed (see Figure 11b-c), while in the third one, only the left end of the beam failed in shear (Figure 11d), with a simultaneous failure of the right beam-column joint (Figure 11e). This outcome was a nice experimental verification of the effect of material fluctuation on determining which amongst similarly resistant failure mechanisms actually occurs in reality. Fig. 10- The viaduct “Rio Torto”. seismic vulnerability. Among the representative bridges, a framed pier from the “Rio Torto” viaduct has been chosen (see Figures 3, 4 and 9). For the experimental program three mock-up’s of pier 12 without retrofit have been realized and tested, with the goal of characterizing its cyclic response and relative collapse mechanism (see Figure 10). Subsequently, one or more reinforcing systems were meant to be applied to the tested piers, for repeated testing to check the efficiency and the reliability of the proposed reinforcing solutions. A ductile flexural failure was predicted with formation of plastic hinges for this pier while, on the contrary, all three specimens failed in shear, either in the transverse beam or the joints, suggesting that the formula employed for the evaluation of the shear strength tends to overestimate the ultimate shear. Since the first test has shown a premature shear failure of the transverse a b c Fig. 12- Experimental force-displacement cycles. d e Fig. 11- Failure mechanisms of the transverse beam in the three tests. RESEARCH - Seismic behavior 39 4.4.1 A SIMPLIFIED NON LINEAR DYNAMIC MODEL FOR THE ANALYSIS OF ABUTMENTS Fig. 13- left: Comparison between theoretical and numerical force-displacement curves; right: base column rotations. The differences between the failure mechanisms of the three piers, however, have a little influence on the global behaviour, as shown in Figure 12, which compares the global force-displacement cycles of the three specimens. The experimental results have been compared with the results of a numerical model, which was set up using the non-linear code “OpenSEES”. Shear failure has been introduced using a shear forcedeformation relationship with a tri-linear backbone and an appropriate degradation law, included in a fiber non-linear element, using the section aggregator command. The yield-penetration at the base of the column effect is particularly relevant due to the presence of plain steel bars. This phenomenon, if neglected, can induce an overestimation of the structural stiffness. This effect has been taken into account using a zero-length element placed at the column base with a properly modify stress-strain law of the steel bars. Finally, the buckling phenomenon has been taken into account using a corrected constitutive law of steel. The FE model used was able to reproduce accurately both the global as well as the local behaviour, as shown in Figure 13. A simplified model for the dynamic analysis of diaphragm walls retaining dry cohesion-less soils with horizontal back-slope subjected to seismic excitation has been developed (Franchin et al, 2007a). The model is based on the well-known one-dimensional Winkler approximation and on the non-linear shear-beam model for the ground layers on both sides of the wall (see Figure 14). The model can include anchor-ties and can account for non-linearity in all of its elements (retained soil, anchors and wall). According to preliminary numerical applications, which include validation of the proposed model results versus those of a refined plane-strain nonlinear finite-element analysis carried out with a commercial code, the model appears to yield quite accurate predictions of static and dynamic bending moment distributions and permanent wall displacements. Next the developed model has been applied for the analysis of the response of a diaphragm abutment prior and after upgrading intervention with change of the support conditions and insertion of tie-backs (Franchin et al 2007b). The analysed structure is represented in Figure 15. The application of the model has shown its versatility in assessing the system response in its existing state and in progressive states of upgrad- 4.4 Task 4: Abutments and foundations The activity under this task has been carried out at University of Rome La Sapienza, and has dealt with two distinct problems: a) the development of an efficient non linear method for the analysis of diaphragmtype abutments, free standing and retrofitted with tie-backs; b) the review of the literature on soil-foundation-structure interaction with the goal of providing detailed indications for practitioners to be included into the assessment guidelines. Fig. 15- Diaphragm abutment retrofitted with anchor ties. Fig. 14- The developed model for diaphragm type. 40 Fig. 16- Results of the abutment analysis: left, moment diagrams; right, top displacement time-histories. RESEARCH - Seismic behavior ROTATION TRANSLATION CAMPING A comprehensive review of the literature on the treatment of the response of deep foundations has been carried out. This has led to identifying the available methods and their pros/cons. After the survey a selection has been made of those procedures considered suitable for practical application and some numerical applications have been carried out to assess the relevance of the phenomenon (input motion modification by kinematic interaction and foundation flexibility), in terms of the response of the superstructure. One example is the bridge structure shown in Figure 17. It is a simplysupported prestressed concrete deck of span length 30.0m typical of the Italian highway construction practice of the ’50s-‘70s with piers consisting of a single-stem with hollow-core circular section. The dimensions are in the figure. The foundation consists of a mat on 5 piles of STIFFNESS Kq REVIEW AND RECOMMENDATIONS ON METHODS FOR THE ANALYSIS OF SOIL-FOUNDATION-STRUCTURE INTERACTION CAMPING Cq 4.4.2 CRITICAL soil-foundation system, consisting of the stiffness and damping functions (of the frequency) to be assigned at the pier base. This impedance includes the evaluation of the frequency dependent “dynamic” group effect, i.e. the modification of the impedance obtained as a simple summation of the individual pile impedances to account for the interaction of the wave-fields produced by each pile. – Evaluation of the response in the frequency domain. This has been done both with a purpose-made code and with a commercial finite element software that implements frequency-domain analysis (Sap2000). The resulting power-spectrum of the displacement components can be integrated to yield the root-mean-square (RMS) or standard deviation of response, from which maxima to be used in verification are readily STIFFNESS ing, in terms of both forces (Figure 16 left) and dynamic displacements (Figure 16 right). To the extent that it has been validated at present, the model represents a very efficient tool for realistic design and assessment purposes. Fig. 17- Simply-supported deck on single-stem hollow-core pier founded on piles. Fig. 18- Complex impedance at the pier base: stiffness (top), camping (bottom), translation (left) and rotation (right). 1.5m diameter. Pile length is 20m. The bridge has 6 spans and a pier of height 20m has been considered. Soil can be classified based on the available information as type D. The structure has been modelled as shown in Figure 17e, i.e. as a three-degree of freedom system (including horizontal and rocking component of the base). The analysis has been carried out in the frequency domain using the substructuring approach. The steps of the analysis include: – Evaluation of the modification of the surface free-field motion (supplied as an acceleration response spectrum) due to the kinematic interaction between soil and pile group. This step provides the power spectrum of input displacement at the pier base. – Evaluation of the complex frequency-dependent impedance of the obtained by multiplication for the peak factors. RESEARCH - Seismic behavior Figure 18 shows the real (stiffness, top) and imaginary (damping, bottom) parts of the complex impedance at the base of the pier, for the translation (left) and rocking (right) displacement components. These are reported for two different values of the shear wave velocity Vs, both compatible with the soil type D. The figure also reports the stiffness/damping obtained by simple summation of the single pile contributions. Comparing the latter with those of the group allows to appreciate the frequency-dependent effect of the pile-to-pile interaction. This effect reduces, by more than 50% in this case, the total stiffness. Finally, Figure 19 shows the power spectral densities of the response in 41 STRUCTURAL DEFLECTION (m) TOTAL DISPLACEMENT Us (m) Fig. 19- Results of SSI analysis on a bridge pier: power spectral densities of the response in terms of total displacement (left) and structural deflection (right). terms, on the left, of total displacement (relative to input motion, i.e. sum of the foundation translation, the structure deflection and the translation due to rigid foundation rotation), and on the right of the structural deflection only. Results are reported for the two Vs values and, for reference, for the fixed-base response. As it can be seen, as expected, the fundamental period of the system elongates considerably due to the introduction of the foundation flexibility: it starts at T=0.83 s in the fixed base case, and reaches about 1.5s and 1.75s for Vs=200m/s and 100m/s, respectively. This increases the total displacements. The drifts, however, are considerably reduced as shown in Figure 19b. The above application, as well as the others carried out, allowed to introduce in the guidelines quantitative indications on the need for inclusion of SSI into the modelling. 4.5 Task 5: Numerical application to case-studies All research units have contributed in producing a vast amount of casestudies that have been of considerable usefulness in checking consistency and practicality of the indications that now form the guidelines for assessment. In this section only a limited overview of the applications is given to illustrate the work done. A more detailed description can be found in the final report for the Line 3. Table 3 reports all the analysed bridges. 4.6 Guidelines and Application manual The activity only briefly summarised in the previous sections has represented a necessary support for undertaking the task of writing what was the final product expected from Research Line 3: a proposal for a guidance document on the seismic assessment of existing bridges, and a companion set of example applications. The task, carried out by University of Rome La Sapienza, has gone through several rounds of scrutiny by all the units. In its final version it represents the first European document on the topic and could be envisaged to form the basis for a future addition to the Eurocodes system. Indeed, the document is fully in line with Eurocodes and reflects to some extent the experience on the seismic assessment of existing structures gained with the use of Eurocode 8 Part 3 on buildings. It is also in line with the relevant chapters of the DM2008, related to seismic design of bridges, and incorporates its most recent developments on the definition of seismic action. The document produced consists of four chapters and two appendices: • Chapter 1: gives an introduction to the problem of seismic assessment of existing bridges; • Chapter 2: contains the guidelines; • Chapter 3: is an overview of the most common retrofit measures and criteria employed, without entering into the specifics of their design, making reference for this purpose to specialised texts on the topic; Table 3. List of case-studies analysed according to the assessment guidelines Unit Case-study Description 4 simply supp. spans, circular hollow-core piers Torino Narbareto (PLS) 7 simply supp. spans, polygonal bi-cell. piers Torino Rio Barcalesa (PLS) Hollow-core slab deck, highly irregular plan, Figure 21 Torino Borgotaro (PLS) 9 spans, steel deck with hollow-core RC piers Torino Rio Verde (PLS) 5 spans, box-section, steel pier Torino Ramat (TBF) 15 spans, frame piers Chieti Vasto Marina (SS16) 10 spans, box-section, single-stem hollow-core piers Chieti Della Valle (A25) 13 spans, inelastic time-history analysis Roma Tre Rio Torto (A1FiBo) 13 spans La Sapienza Rio Torto (A1FiBo) 5 spans, simply-supported, and continuous after section La Sapienza Standard viaduct (E45) widening widening 4 simply supp. spans, retrofitted with “link system” Cosenza Follone (A3) 5 simply supp. spans, retrofitted with oledynamic devices Cosenza Val di Leto 42 Analysis Elastic RS analysis + q-factor Elastic RS analysis + q-factor Elastic RS analysis + q-factor Elastic RS analysis + q-factor Elastic RS analysis Elastic RS analysis + q-factor Elastic RS analysis + q-factor Inelastic time-history analysis Modal pushover analysis Simplified Simplifiednon-linear non-linearmethod, method,pushover, pushover, linear dynamic linear dynamic Inelastic time-history analysis Inelastic time-history analysis RESEARCH - Seismic behavior Fig. 20- The Narbareto viaduct. North carriageway South carriageway Fig. 21- The Borgotaro viaduct. • Chapter 4: contains the numerical examples that illustrate the application of the methods presented in the guidelines. There are four applications covering: – assessment, by means of the simplified non linear method, of a typical simply-supported bridge with single-stem cantilever piers in its present state; – assessment, by means of linear and pushover analyses, of the previous bridge in two different configurations, with a new continuous, wider, RESEARCH - Seismic behavior composite steel-concrete deck, with and without seismic isolation; – assessment of the Rio Torto viaduct by means of inelastic time-history analysis. • Appendix A: presents the fundamentals of the response to multiplesupport excitations and reviews a number of methods that can be employed to analyse bridge structures for this effect; • Appendix B: presents the fundamentals of the soil-foundation-structure interaction phenomenon and reviews a number of methods that can 43 STATIC SCHEME Fig. 22- The Della Valle viaduct. RETROFIT VIA STEEL BARS AND NEOPRENE PADS Fig. 23- The Follone viaduct. 44 RESEARCH - Seismic behavior be employed to analyse bridge structures for this effect. The main body of the manual is represented by chapters 2 and 4, as well as by the appendices. In the following the most significant or problematic aspects are briefly reviewed and commented. 4.6.1 CHAPTER 2, GUIDELINES: DEFINITION OF THE SEISMIC ACTION The seismic action is defined, in line with DM2008, by means of an elastic acceleration or displacement response spectrum characterized by an average return period specified as a function of the limit state of interest. The return period TR is obtained from the probability of exceedance PVR over the reference life VR. The latter is given in DM2008 as the product of two factors, the nominal life VN and the “use factor” CU. The minima for PVR for each limit state are given in DM2008. In the tentative applications of the guidelines it was raised the problem of the value to be attributed to VN and CU, especially with reference to the first one. The uncertainty may arise in the choice between 50 and 100 years for VN, when considering bridges over highways. The DM2008 indicates 50 years for bridges of ordinary dimensions, typology and importance, and 100 years for bridges of large dimensions and “strategic” importance. One would then be probably directed towards 100 years, in consideration of the importance of the bridge (it is on a highway). The next choice is that of CU which leads unambiguously to 2.0, since highways are roads of type A according to the Italian classification of roads (i.e. considering, again, the functional importance of the road on which the bridge is located). The above choices would imply a reference life of 200 years and, for the life-safety limit state, a TR of about 2000 years. It is observed that this conclusion would not to be in line with the safety criteria contained in Eurocode 8 Part 2 (Bridges) which indicates for highway bridges an importance factor I=1.3 to be applied to the action with TR = 475 years. This multiplication leads in most of Italy to an action with a return period of about a 1000 years. This latter in turn is consistent with a reference life of about a 100 years, which is also the design life specified in the Eurocodes for other actions (e.g. corrosion). the possibility of defining the concept of “residual” reference life. Though it is admitted that in our Country it seldom occurs that the decision to demolish a bridge can be taken several years in advance, it may happen that, due to planned substantial modification of the traffic capacity of the link, it will be economically more convenient at a future date to replace the bridge. In this case, if seismic upgrade must be undertaken, the concept of residual reference life may be invoked to assign to VR a more realistic reduced value. This possibility is not currently included in the guidelines, though it is regarded as being in line with the possibility allowed for existing structures to derogate from standard safety levels dictated for new structures. 4.6.2 CHAPTER 2, GUIDELINES: METHODS OF ANALYSIS With respect to classification of methods in static and dynamic, linear and non linear, now common to all modern seismic design codes and giving rise to the usual four alternatives, the guidelines restrict somewhat the field of applicability of linear analysis. This is not unexpected. For new well-designed structures the role of analysis is a relatively minor one, due to the many constraints (arising mainly from global and local capacity design) that guide the design. On the other hand, when assessing an existing structure, the accuracy in the analysis may have a major economic impact on the retrofit, possibly avoiding it altogether. An official response to the mentioned problem, whose relevance needs not to be underlined, cannot but come from the competent authorities, which are in charge of choosing the safety levels. The guidelines admit linear analysis of two types only: modal analysis with unreduced elastic spectrum and verifications in terms of deformation/forces (subject to stringent conditions on the response regularity), and modal analysis with a spectrum reduced by a limited value of the behaviour factor of q=1.5. The main methods put forward by the guidelines are non linear static and dynamic analyses. As already anticipated in § 4.2.1, a simplified non linear static method is proposed for the very frequent case of bridges with simply supported decks. For continuous irregular bridges the use of more recent pushover variants (adaptive and/or multi-mode) is introduced as an alternative to full-fledged inelastic time-history analysis. The allowance for more than single-mode invariant pushover represents a small step forward with respect to Eurocode 8 Part 2, which builds upon the results of recent wide-ranging studies on the performance of such methods in the analysis of bridges [see for ex. (Casarotti 2005), (Kappos et al, 2005), (Isakovic and Fischinger, 2005), (Lupoi et al, 2007), (fib, 2007), as well as the draft document “Inelastic methods for seismic design and assessment of bridges” by Task Group 11 of the European Association of Earthquake Engineering]. Within the framework of the definition of the reference life one aspect that deserves particular consideration in the case of existing bridges is 4.6.3 CHAPTER 2, GUIDELINES: SAFETY VERIFICATIONS The guidelines introduce a format for bi-directional verification for both RESEARCH - Seismic behavior 45 deformations and forces. In particular the format reads: Dx 2 Dy 2 + 1 Cx Cy ( )( ) (7) where Dx and Dy denote the demand quantities along the two orthogonal axes x and y, with Cx and Cy denoting the corresponding capacities. This format becomes, in terms of chord rotations and shear forces: (x/u,x) + (y/u,y) 1 (8) (Vx/Vu,x) + (Vy/Vu,y) 1 2 2 2 2 (9) In the above equations the demand terms are understood as the combined effect of both orthogonal components of the seismic action. For example, with reference to chord rotation, for the case of multi-modal non linear static analysis one has: N x=xG± [( xEx,i–G) + (xEy,i–G) ] i=1 2 2 (10) where the directional combination is of the SRSS type and the summation is over the modes. dent motions at the supports representative of the local soil conditions, which can be applied using currently available commercial finite element codes (Monti and Pinto, 1998); For what concerns soil-foundation-structure interaction the guidelines give a classification of the approaches and present with some detail the substructuring method, in its application to pile (Novak 1974, Makris and Gazetas, 1991 and 1992) and caisson foundations (Gerolymos and Gazetas, 2006a,b). In this method the structure and the soil-foundation system are separated and studied accordingly. The study of the soilfoundation system consists of the solution of so-called kinematic interaction and inertial interaction problems, leading to the modified input motion for the structure and to (complex) impedance to be put at the structure base, respectively. Then the structure is analysed, with a flexible support condition, under the previously determined modified motion. All the formulas necessary to perform this procedure are present in the Appendix. 5. DISCUSSION 4.6.4 APPENDICES The matter covered in these two appendices, i.e. the response of bridge structures to different motions at the piers’ bases and the effect of the soil-foundation system deformability in modifying the input motion as well as the response of the structure, has been always mentioned in codes without, however, neither precise quantitative indications on the instances in which these phenomena have to be accounted for, nor of physically sensible yet practically applicable methods to do it. The reason for this resides clearly in the insufficient advancement on basic research. In drafting the guidelines, however, it was considered appropriate to provide a presentation of selected state-of-the-art approaches which are susceptible of practical application. For what concerns the effect of multiple-support excitation, the guidelines indicate that the phenomenon should be accounted for whenever soil conditions along the bridge belong to different soil categories. The guidelines also present: • A stochastic model of the motion at the supports (Der Kiureghian, 1996) that can be used either to generate samples of correlated motions to be used in time-history response analysis or in linear random vibration analysis; • The multiple response spectrum method (Der Kiureghian and Neuenhofer, 1992), which provides a solution for the random vibrations problem of a system subjected to multiple inputs based on the use of the corresponding input displacement response spectra; • A simplified proposal for time-history analysis employing indepen46 The main objective of the project, which was the production of the draft guidelines and their application manual, has been met. In this respect the Research Line was successful, since the product has been delivered and its quality is believed to be high. Though it wasn’t explicitly included into the remit for the Line, it must be noted that the research group initially intended to cover in the guidelines both structural concrete and masonry bridges. In spite of the research carried out, however, this more ambitious goal could not be achieved. Research on this front was essentially under the responsibility of the unit of Genova. This unit has produced during the three years of the project a considerable amount of high-quality research that has been regularly documented in the annual as well as the final reports, and it is also available in research reports from the unit uploaded on the project website. Quoting from the final report the issues dealt with by the unit cover the following: “i) statistical characterization of the Italian bridge population; ii) mechanical models for solid clay brickwork, needed for detailed and simplified structural models; iii) in field testing of masonry bridges, aiming at the identification of the main mechanical properties of the materials and of the bridge as a whole; iv) laboratory testing of brickwork prisms; v) reduced scale testing aiming at identifying the load carrying capacity and the collapse mechanisms of shallow and deep arches taking into account the fundamental collaboration of the so called “non structural elements”; vi) reduced scale testing aiming at identifying the dynamic properties of shallow and deep arches RESEARCH - Seismic behavior taking into account the collaboration of the so called “non structural elements”; vii) Limit Analysis procedures for the analysis of masonry bridges taking into account the contribution of all the bridge elements; viii) retrofitting techniques for the bridge and its components.” As it may be seen all of the investigated topics are of clear scientific interest, though not specifically relevant to seismic assessment of bridges. This is simply the unavoidable consequence of the international lack of fundamental knowledge on the seismic behaviour of masonry bridges. tion of expected loss related to any given bridge. Looking now at the problem of bridge protection from an higher perspective, the attention should be directed at the bridges as components of road links forming a transportation infrastructure. The seismic performance of the single bridge would then be put in relation with the performance of all other bridges to be able to estimate the overall decrease in functionality of the whole infrastructure. In this respect the very challenging problem of determining the loss in traffic capacity of a damaged bridge represents an essential element. 6. VISIONS AND DEVELOPMENTS 7. MAIN REFERENCES The research carried out within Research Line 3 has included the stateof-the-art into a document usable for assessing the protection level of bridges against a number of limit-states. There are certainly several areas where improvement is possible and desirable, and in particular these are: • The non-linear static analysis for bridges of complex geometry; • The ultimate strength and deformation capacity of structural members such as those encountered in bridge structures (e.g. polygonal multicell. hollow-core cross-sections) • The generation of ground motions for multiple-support excitation. While generated motions are being progressively replaced with recorded ones for the analysis of buildings, their use appears unavoidable for the analysis of bridges whenever different motions must be considered at the supports. Currently available procedures are in need of considerable improvement. • The vast literature on SSI needs to be acquired and digested by structural engineers to become a practical tool. This a crucial aspect in view of the displacement-based framework of the guidelines and the corresponding need for more accurate evaluations of deformations. The guidelines do not cover the seismic isolation technique. The reason for this choice is that the design of seismic isolation does not vary between new and existing bridges. Seismic isolation, however, will certainly see much further diffusion in the coming years, for new as well as existing bridges, while isolation device technology continues to evolve rapidly with the ensuing need of developing appropriate analysis and design techniques. In this respect this can be regarded as an ongoing research topic. To the extent that solutions to the problem of assessing the protection of a bridge against its ultimate state can be considered to be sufficiently mature, the next important passage is that of being able of estimating structural and monetary damage as a continuous discrete function of seismic intensity. Achievement of this goal would allow for the estimaRESEARCH - Seismic behavior - Casarotti C. (2005), “Adaptive pushover-based methods for seismic assessment and design of bridge structures” PhD thesis ROSE School, Pavia, Italy. - CEN (2005), “Eurocode 8 Part 2: Seismic design of bridges” European Committee for Standardization, Brussels, Belgium. - CEN (2005) “Eurocode 8 Part 3: Assessment and retrofitting of existing structures” European Committee for Standardization, Brussels, Belgium. - Chopra A.K., Goel R.K. (2002), “A modal pushover analysis procedure for estimating seismic demands for buildings” Earthquake Engineering & Structural Dynamics Vol 31(3), pp. 561-582. - Der Kiureghian, A. (1996), “A coherency model for spatially varying ground motions” Earthq. Eng. & Struct. Dyn. Vol. 25, pp. 99-111. Der Kiureghian, A., Neuenhofer, A. (1992), “Response spectrum method for multi-support seismic excitations” Earthq. Eng. & Struct. Dyn., 21: 713-740 - DM2008 (2008), “Nuove norme tecniche per le costruzioni” Decreto Ministeriale del Ministero delle Infrastrutture 14/1/2008. - FHWA (1995), Seismic Retrofitting Manual for Highway Bridges, Publ. FHWA-RD-94 052, Federal Highway Administration. - FHWA-ATC (1983), “Retrofitting guidelines for Highway Bridges” Report ATC-06-2, Applied Technology Council, Redwood City, California. - FHWA-MCEER (2006), Seismic retrofitting manual for Highway Structures. Part 1- Bridges. - fib (2007) “Seismic bridge design and retrofit – structural solutions” Bulletin 39, International Federation for Structural Concrete. - Franchin P., Pinto P.E., Noto F (2007), “A nonlinear dynamic model for seismic analysis of earth-retaining diaphragm-walls” Proc 4th Int. Conf. Earthquake Geotech. Engng, Thessaloniki, Greece. - Franchin P., Pinto P.E. (2007), “Analysis Of Diaphragm-Type Bridge Abutments Before And After Seismic Upgrading” Proc 1st US-Italy workshop on seismic design and assessment of bridges, Pavia, Italy. 47 - Gerolymos N., Gazetas G. (2006), “Winkler model for lateral response of rigid caisson foundations in linear soil” Soil Dyn. & Earthq. Engng Vol.26, pp. 347-361. - Gerolymos N., Gazetas G. (2006), “Development of Winkler model for static and dynamic response of caisson foundations with soil and interface nonlinearities” Soil Dyn. & Earthq. Engng Vol.26: 363-376. - Isakovic T., Fischinger M. (2005), “Higher modes in simplified inelastic seismic analysis of single-column bent viaducts”, Structural Engineering International. - Kappos A.S., Paraskeva T.S., Sextos A.G. (2005), “Modal pushover analysis as a means for the seismic assessment of bridge structures” Proc. 4th European workshop on the Seismic behaviour of irregular and complex structures, Thessaloniki, Greece (Paper 49). - Lupoi A., Franchin P., Pinto P.E. (2007), “Further probing of the suitability of push-over analysis for the seismic assessment of bridge structures” Proc. of COMPDYN’07, Crete, Greece - Makris N., Gazetas G. (1991), “Dynamic pile-soil-pile interaction. Part I: Analysis of Axial Vibration” Earthq. Eng. & Struct. Dyn. Vol.20, pp115-132. - Makris N., Gazetas G. (1992), “Dynamic pile-soil-pile interaction. Part II: lateral and seismic response” Earthq. Eng. & Struct. Dyn. Vol.21, pp 145-162. - Monti G., Pinto P.E. (1998), “Effects of multi-support excitation on isolated bridges” Tech. Rep. MCEER 98/0015 pp. 225-247. - Novak M. (1974), “Dynamic stiffness and damping of piles” Canadian Geotech. Jnl Vol.11: 574-598. III - INNOVATIVE MATERIALS FOR THE VULNERABILITY MITIGATION OF EXISTING STRUCTURES 1. INTRODUCTION The use of fiber reinforced polymer (FRP) materials for the strengthening of masonry and concrete structures, represents a valid alternative to traditional techniques. Indeed, many advantages are provided by using FRPs: lightweight, good mechanical properties, corrosion-resistant, etc. In Italy, the use of FRP materials for reducing the seismic vulnerability of existing structures has been allowed for the first time through O.P.C.M. 3274 and more recently by the D.M. 14.01.2008, that refer to the Italian National Research Council Design Guidelines (CNR-DT 200/2004) for the external strengthening of existing structures with FRP materials. These guidelines provide, within the framework of the Italian regulations, a document for the design and construction of externally bonded FRP systems for the strengthening of existing structures. In particular, several issues concerning the seismic rehabilitation of Reinforced Concrete (RC) and masonry buildings have already been dealt but a further investigation is still required. Within this context, the main aim of this research line has been the experimental validation of design indications provided by the CNR-DT 200/2004 guidelines. The main topics investigated in this research task can be summarized as follows: - the mechanical behaviour of FRP materials; - the cyclic behaviour of RC elements strengthened by means of FRP; - the mechanical and chemical anchorage devices for FRP systems; - the ductility increasing of RC columns confined with FRP; - the RC joint strengthening with FRP; - the masonry strengthening with FRP; - the historical structure strengthening with FRP; - the quality control and monitoring of FRP applications; - the innovative fibers (steel fabrics, natural fibers, FRP grids, etc.) and matrices (organic and inorganic); - the mechanical behaviour of concrete structures reinforced with fiber reinforced polymer bars; - innovative strengthening techniques (near-surface mounted (NSM) technique, FRP prestressed systems). 2. BACKGROUND AND MOTIVATION The research activity has been performed through experimental tests and theoretical studies mainly devoted to the development of simple methods of analysis and design rules in order to improve the indications 48 RESEARCH - Seismic behavior provided by CNR-DT200-2004. FRP are ideal products for structural retrofitting and seismic upgrading. Nonetheless the small knowledge on the durability of the system is one of the main drawbacks to the use of FRP reinforcement in Civil Engineering. In particular, structural adhesives usually represent the weakest point of the reinforced system and their mechanical behaviour and durability performance need to be investigated. The first problem in using composite materials for structural reinforcement is the determination of their mechanical properties. The bond between FRP and concrete is a very important issue because the debonding is a very brittle failure mechanism and must be avoided. According to performance-based design or seismic evaluation of RC buildings, it is crucial to provide a correct evaluation of the strength and ductility capacity of the RC columns and beams as well as of beam-column joint. Experimental and direct observation of damages occurred during recent earthquakes strongly highlighted this need. The effectiveness of FRP systems for seismic vulnerability mitigation of masonry structures is still in debate, despite it has moved a huge interest, becoming the outstanding system in the market for this type of applications. Indeed CNR DT 200/2004 has been the first guideline to provide design criteria for the FRP seismic strengthening of masonry buildings. However, the retrofit design of masonry structures is still not a completely solved problem. This is due to the fact that the masonry structure is load dependent and thus the FRP could be placed in an inactive area of the resistant mechanism. Furthermore, masonry can activate a large number of local mechanisms which interact with global behaviour of masonry buildings. The non linear seismic assessment of FRP reinforced masonry structures is included also in the D.M. 2008 rule. The non linear analysis requires the knowledge of the constitutive law of the masonry material both in the unreinforced or strengthened situations. In the recent years, the scientific research has been focused on the safeguard of historical buildings. Accordingly, CNR DT 200/2004 has been published in order to provide design criteria for the use of FRP systems for strengthening existing structures and to avoid their incorrect application. The Guidelines deal with different types of FRP applications to masonry and reinforced concrete structures and take into account the important phases of quality control and monitoring that should follow a strengthening application. Several aspects affect the effectiveness of FRP systems such as the surface preparation and FRP installation. Moreover, once FRP strengthening intervention has been carried out, monitoring by non-destructive or semi-destructive tests should be performed to ensure the quality and effectiveness of the strengthening system. It is worth noting that due to the increased number of composite material applications and in order to get a better understanding of the RESEARCH - Seismic behavior interaction force between FRP materials and the masonry substrate, experimental tests are needed. In this research line, semi-destructive and non-destructive techniques have been also investigated for the quality control and monitoring of FRP applications to masonry structures, according to CNR DT 200/2004 Guidelines. 3. RESEARCH STRUCTURE In order to guarantee an optimal organization of the research, the Research Units have been grouped into the following ten Tasks, each one with a specific topic: - Task 8.1: the mechanical characterization of FRP systems at fixed environmental conditions under cyclic actions; - Task 8.2: the delamination under cyclic actions and design of anchorage mechanical devices for FRP systems; - Task 8.3: the confinement of RC and masonry columns subject to combined flexure; - Task 8.4: the strengthening in flexure and in shear of RC structural elements with FRP fabrics and near surface mounted (NSM) rods; - Task 8.5: the beam-column and beam-foundation joint reinforcement with FRP; - Task 8.6: the design criteria for the seismic retrofit of RC and RCmasonry composite structures with FRP; - Task 8.7: the design criteria for the seismic retrofit of masonry structures with FRP; - Task 8.8: the strengthening of masonry structural elements with FRP systems; - Task 8.9: the strengthening of masonry vaulted elements with FRP systems; - Task 8.10: the quality control and monitoring of FRP applications to existing masonry and RC structures. 4. MAIN RESULTS 4.1 Task 8.1: the mechanical characterization of FRP systems at fixed environmental conditions under cyclic actions The aim of the sub-task was to mechanically characterize FRP systems. The study has been focused on durability and mechanical behaviour of structural adhesives and FRPs, the mechanical characterization of FRP bars and strips, the values of the safety factors proposed in CNR DT 200/2004 and the effects of elevated temperatures and freeze-thaw cycling on FRP. Durability and mechanical behaviour of structural adhesives and FRPs Several tests to determine the mechanical properties of composite mate49 Fig. 1- a) Execution of the punch-tool test and specimen after collapse, b) execution of the torsion test and specimen after collapse. Fig. 2- a) Anchor system for large diameter GFRP bars, b) numerical analysis. rials and structural adhesives have been performed. Conforming to the ASTM requirements, the glass transition temperature (ASTM D3418), porosimetry and the coefficient of thermal expansion (ASTM D360) were determined. Adhesives were also tested under tensile (ASTM D360), compressive (ASTM D695) and flexural loading (ASTM D790). Adhesive shear strength was determined by punch tool tests (ASTM D732). Finally adhesive cylinder specimens were tested under pure torsion load. Adhesive dumb-bell specimens were prepared for tensile testing and then artificially aged in an environmental chamber in order to analyze possible detrimental effects on the adhesive mechanical properties. Exposition to deicing salts, freeze-thaw cycles and moisture may in fact deteriorate the mechanical properties with consequences on the durability performances of strengthened structures. Tensile tests were performed conforming to the requirements of ASTM D360. In all the conditioning treatments, significant losses in adhesive stiffness and tensile strength were measured. The stiffness and tensile strength reductions after exposure to salt spray fog solution may be approximated by straight parallel lines as described in the Arrhenius life-temperature relationship. Fatigue tests on adhesive dumb-bell specimens were finally performed to attain the fatigue failure curves for the adhesive joint. riences for testing steel ropes and prestressing steel tendons and the shape of the resin head from test investigation. Numerical analyses were also performed to investigate the effects of anchor parameters such as cone slope angle, thickness of resin head and friction coefficient between the anchor body and the resin head. Pull-out and beam tests were also executed. Experimental studies and numerical analyses were developed to define practical tests for the characterization of FRPs and adhesives mechanical properties. The main aim of this action was to provide the “Composites Kit Test - COKIT”; a practical tool for professionals and engineers operating in the field of FRPs applications and dealing with FRP materials for structural retrofitting and rehabilitation. The technical document “Istruzioni per la caratterizzazione ed il controllo di accettazione di materiali fibrorinforzati per il rinforzo strutturale – COKIT ” was thus published and could represent an annex of the CNR DT 200/2004 Recommendations. Refinement of the safety factors proposed in Design Recommendations The environmental conversion factors provided in the guidelines of the Italian National Research Council (DT200) were analyzed on the basis of the results of artificially aged adhesive specimens tested under tension. Exposition to deicing salts, freeze-thaw cycles and moisture leads Mechanical characterization of FRP bars and strips Tensile and relaxation tests were performed on FRP bars with particular attention to the gripping system. Then, experimental tests and numerical simulations were performed to develop simple, economical and effective systems for the characterization of composite materials and adhesives. In particular, an anchor system for tension testing of unidirectional fiber reinforced plastic (FRP) bars of large diameter was developed. In the system suggested each end of the bar is embedded in a conical polymeric head that fits a conical hole inside the anchoring device. In the anchor system, the anchor body shape came from expe50 Fig. 3- Stiffness and tensile strength retention for the structural adhesive subject to freeze-thaw cycles of five hours each between –18° and +4°C for a total duration of about 2 months (FT), to salt spray fog for one month or three months (SF) and to one month humidity (HU). RESEARCH - Seismic behavior Effects of elevated temperatures and freeze-thaw cycling on FRP laminates behavior Fig. 4- a) Steel-CFRP specimen b) Reduction in stiffness of retrofitted specimens during fatigue tests; c) S-N curve and comparison between the fatigue resistance of the steel-CFRP bond for a stiffness reduction of 5% (blue circles) and of 15% (red squares) and that of EC3 welded detail categories. to the deterioration of the mechanical properties of composite materials and in particular structural adhesives. On the basis of the experimental results, the safety factors suggested in the CNR DT 200/2004 recommendations may be considered as appropriate, but in aggressive environments the use of a slightly lower conversion factor seems to be more suitable. Tests were performed to refine the safety factor of FRP-steel systems: the fatigue behaviour of steel structures retrofitted by using FRP materials was investigated, S–N curves were defined and the fatigue resistance of the steel-CFRP bond was compared to the one of welded detail categories described in the Eurocode 3. After performing pull-pull delamination tests on FRP-concrete specimens, cylinders were obtained from each concrete prism. Based on Eurocode 2 compressive and splitting tests were carried out to determine the conditioning effects on concrete degradation. As a consequence of the environmental conditioning, concrete characteristic strength is assumed to increase by 16% for salt spray fog conditioned specimens and to decrease by 3% for specimens subject to freeze-thaw cycles. The performances at elevated temperatures and/or at freeze-thaw cycling exposure of structural members strengthened by using externally bonded FRP laminates are mainly related to two aspects: the bond behaviour between FRP and the member substrate; the mechanical properties of laminates themselves. The latter aspect has been very limited experimentally investigated; only few tests have been performed to evaluate the residual tension strength of FRP coupons after exposure to elevated temperatures or freeze-thaw cycling. Thus, experimental tension tests on carbon FRP (CFRP) laminates both under controlled temperature and relative humidity conditions or after freeze-thaw cycles exposure have been carried out. In particular, due to reduced capacity that commercially available resins have to transfer loads over fibres around glass transition temperature, Tg, two new systems based on epoxy resin have been formulated and characterized by dynamic mechanical analysis (DMA). The main goal of the new formulated systems was to increase Tg, the elastic modulus in the rubber region of the resin and to improve their performances under freeze-thaw cycles. Two different approaches were investigated. First a new epoxy system (namely neat epoxy) was formulated and cured at 60°C after an hour at room temperature. Secondly, in order to improve the mechanical properties of epoxy matrix by curing at room temperature, a nanocomposite system was obtained by direct dispersion of preformed nanodimensioned silica particles to the neat epoxy resin. Fig. 6- Specimen geometry; Temperature and relative humidity exposure profiles; test setup. Fig. 5- Statistical distribution of the coefficient kG for specimens subject to a) salt spray fog and b) freeze-thaw cycles. RESEARCH - Seismic behavior The experimental results point out that the developed formulations of epoxy resins provide a significant increase of ultimate strength and strain of CFRP coupons both at room and elevated temperatures with respect to commercial systems, without significant change of the elastic modulus. Negligible influence of a low number of freeze-thaw cycles was observed on the mechanical properties of coupons independently of matrices. Experimental outcomes strongly confirmed that the use of matrices characterized by higher values of Tg and elastic modulus in the rubber region with respect to those traditionally available on the mar51 4.2 Task 8.2: the delamination under cyclic actions and design of anchorage mechanical devices for FRP systems Different experimental set-ups can be found in the scientific literature dealing with FRP-concrete bond tests and it has been observed that different test methodologies may give different values of the debonding force. This task research intended to define a standard FRP-concrete bond test to be used to evaluate the maximum transmissible force by an FRP anchorage, to be included in the new version of the Italian code for design of strengthening interventions with FRP. single shear push-pull test. All the tests have been performed under displacement control of the FRP free end. In order to evaluate the variability of the results when different set-ups are adopted, the coefficient of variation (COV) for each set of homogeneous experimental tests has been calculated. The scatter of the results is in general small (COV about 10%), lower than that of the tension strength of the concrete, usually equal to 20-30%. For the plates, the scatter of the results is similar for the different Labs, whilst for the sheets the dispersion is usually higher. The results obtained by Lab 3 are very stable in both cases and close to the mean values. This study allowed to define a set of rules for the standardization of bond tests to be used to evaluate the maximum transmissible force by an FRP – concrete anchorage. Experimental Round Robin test on FRP concrete bonding Cyclic tests of FRP-concrete debonding under cyclic loadings An extensive experimental campaign on FRP-concrete debonding has been carried out by five different Italian Laboratories (University of Bologna, University of Naples Federico II, University of Sannio, Polytechnic of Milan and University of Calabria). The tests were devoted to the definition of a standard test procedure for the bond strength evaluation. According to the Round Robin procedure, 50 concrete prisms (same batch) strengthened with CFRP plates and sheets have been prepared by the same operator and subject to bonds test in five different Laboratories. The sets of homogeneous specimens have then been subject to bond test by five laboratories of the University partners using different test set-ups (Figure 7). Many strengthened structures are subjected to fatigue loads (i.e. roads and railways bridges) or to shorter but more intense cyclic actions as seism: in this cases, the FRP-concrete interface is subject to cyclic stress regimes which can lead to premature debonding of the FRP laminate from the concrete substrate and cause the FRP failure in most cases, unless appropriate local measures are taken to prevent it. In order to develop a more economical design for FRP-strengthened structures, research line investigated the debonding phenomenon of the FRP reinforcements (both plates and sheets) from the concrete substrate under cyclic actions. In particular, tests on little prismatic specimens have been performed by applying FRP plates and sheets on concrete prisms and testing them under both monotonic and cyclic actions without inversion of sign. The experimental results of Single Shear Test (SST) performed on CFRP reinforcement applied on little prismatic concrete specimens and characterized by high bond length values (400mm) showed that: - the influence of load-unload cycles up to 70% of Pmax,M was negligible for CFRP sheets and plates; - a low number of load-unload cycles (40) up to 90% of Pmax,M reduced the debonding load of about 10% in the case of CFRP plates but did not affect particularly the bonding behaviour of CFRP sheets; - by increasing the number of load-unload cycles (up to 300) between 70% and 90% of Pmax,M, the debonding load of concrete specimens reinforced with CFRP sheets decreased by a percentage factor equal to 10%; - the transfer of shear stresses at the FRP-to-concrete interface due to the CFRP reinforcement bond length larger than effective one, allowed to mitigate noticeably the effect of cyclic actions imposed up to 90% of Pmax,M; - a degradation of interface behaviour has been recorded after the onset ket, could allow to overcome one of the main limit of FRP laminates related to their poor performances under elevated temperatures. Twelve specimens (6 strengthened with sheets, 6 strengthened with plates), with two different bonded lengths (100 mm and 400 mm), have been tested by each laboratory, repeating three times the same type of test. As for the test set-ups (Figure 7), all the Laboratories adopted a LAB4 Fig. 7- Experimental set-ups adopted by the five different Laboratories. 52 RESEARCH - Seismic behavior of debonding, with reduction of maximum shear stress; - the effects of cyclic actions were more significant on plates rather than sheets and its influence increased with number of cycles; Moreover similar SST tests performed on CFRP reinforcements characterized by lower bond length values (50-250mm) allowed to observe that: - design relationships provided by Teng et Al. and by main international codes for evaluating the effective bond length values are conservative for both sheet and plate reinforcements; - referring to plates the effective bond length values, experimentally evaluated by means of the monotonic tests, were noticeably lower than predicted; - even if reinforcement bond length values were significantly low, the cyclic tests outcomes confirmed that the influence of load-unload cycles up to 70% of Pmax,M was negligible for CFRP sheets and plates due to elastic behaviour characterizing FRP-concrete interface up to such load level; - Also a further low number of load-unload cycles (10) up to 90% of Pmax,M did not affect particularly the bonding capacity of CFRP reinforcement due to the transfer of shear stresses at the FRP-to-concrete interface. Such transfer was more significant on plates rather than sheets: nevertheless, bond lengths particularly conservative for plates allowed to better mitigate cyclic action effects; - in order to better predict design bond length values, using two different relationships for sheets and plates, respectively, could be worthwhile. 4.3 Task 8.3: the confinement of RC and masonry columns subject to combined flexure The main goal of this research task has been to validate the design equations provided by CNR DT200 for the confinement of RC and masonry members. In particular, experimental tests have been carried out on both real scale and scaled columns wrapped by using traditional FRP (CFRP and GFRP) or an innovative typology of FRP system made of basalt material fiber. Confinement of real scale RC columns subject to axial load An experimental campaign has been carried out on full scale reinforced concrete (RC) columns concentrically loaded and confined by means of FRP (Glass FRP and Basalt FRP). Five series of tests were planned, for each series a reference unconfined column was tested and used as benchmark. The test matrix has been designed to assess the confinement effectiveness: applying the same reinforcement ratio and checking the effect of the shape, the side aspect ratio and the area aspect RESEARCH - Seismic behavior Fig. 8- Debonding force for sheets with anchorage length (a) L=400 mm, (b) L=100 mm, and for plates with anchorage length (c) L=400 mm, (d) L=100 mm. Fig. 9- Coefficient of variation (COV) of the debonding force for (a) sheets and (b) plates. ratio; applying different FRP reinforcement ratios and checking the confinement sensitivity to the number of plies. Tested specimens represent real scale building columns designed according to dated codes for gravity loads only. The design concrete strength is 23.1 MPa to simulate concrete mixes used in past decades. Concrete cylinder specimens per each casting have been prepared in order to characterize the concrete with standard procedures. The used steel is characterized by a yield strength of 414 MPa and a modulus of elasticity of 200 GPa. Particular care has been devoted to construction details, namely: hooks, longitudinal and transverse steel reinforcement ratios and concrete cover specifications. Special care has been taken to avoid local failure at the top and the bottom ends of the columns placing steel ties with reduced spacing. Internal steel (bars and ties) reinforcement ratio is the same for each group of specimens, designed per minimum code requirements. The minimum specimen dimensions are 360 x 510 mm2. The load has been applied concentrically under a displacement control rate. The load has been conducted in five cycles in increments of one fifth of the expected capacity for each specimen. Each loading-unloading cycle has been repeated once. Strain gages, potentiometers and LVDTs are used for strain and displacement data acquisition. In particular, strain gages have been applied on column surface and internal bars whereas LVDTs have been placed in order to obtain vertical and horizontal column displacement. Strain data acquisition have been obtained by strain gages applied on FRP sheets too. 53 Fig. 10- Test Matrix. (a) Column S-1-5GA (b) Column R-1-8H Fig. 11- Columns strengthened by means of glass (a) and basalt (b) FRP. The data have been elaborated in order to investigate on volumetric strain and Poisson ratio as a function of load level. The main results of the experimental campaign can be summarized as follows: a significant increasing in the axial displacement and a little increase in the ultimate load of the FRP strengthened columns compared to their benchmark. The hollow columns have shown a failure mode characterized by bulging, followed in such case by the rupture of the fibers. A more evident failure mode has been shown by the remaining columns for which the fiber rupture has always accompanied the concrete spalling. Confinement of RC cylindrical specimens strengthened by means of basalt fibers and inorganic matrix The effectiveness of such system as a confinement technique has been analyzed by means of an experimental campaign on concrete cylindrical specimens. The effectiveness of the proposed technique is assessed by comparing different confinement schemes: 1) uniaxial Glass Fibre Reinforced Polymer laminates; 2) alkali-resistant fibreglass grid bonded with a cement based mortar; 3) bidirectional basalt laminates pre- Fig. 12- Load versus vertical and horizontal strains. 54 RESEARCH - Seismic behavior Fig. 13- Typical failure modes. impregnated with epoxy resin or latex and then bonded with a cement based mortar; 4) cement based mortar jacket. The main objectives of the experimental program were: a) to investigate on the effectiveness of confinement based on basalt fibres pre-impregnated in epoxy resin or latex and then bonded with a cement based mortar (BRM); and b) to compare the performance (in terms of peak strength and ultimate axial strain gains) of different confinement techniques using advanced materials with respect to GFRP laminates jacketing. The investigation was carried out on 23 concrete cylindrical specimens with a diameter of D = 150 mm and a height of H = 300 mm. Fig. 15- Failure modes. schemes were experimentally analyzed in order to evaluate and compare the effectiveness of the proposed strengthening techniques: 1) uniaxial glass FRP laminates (GFRP) wrapping; 2) uniaxial carbon FRP (CFRP) laminates wrapping; and 3) uniaxial basalt FRP (BFRP) laminates wrapping. In particular 9 tests, were performed on square tuff masonry (external tuff blocks and inner core filled with tuff chips and mortar) scaled columns (mass density equal to about 1530 kg/m3): side average dimension equal to 220mm; and average height of about 500 mm corresponding to 8 courses of tuff bricks (height-width ratio equal to 2.27). Masonry was made by scaled yellow Neapolitan tuff bricks (50x50x100mm) and a pozzolan (local volcanic ash) based mortar (thickness of 12mm). Further 9 tests were performed on square clay brick masonry scaled columns (mass density equal to about 1700 kg/m3): side average dimension equal to 260 mm, and average height of about 560 mm corresponding to 8 courses of clay bricks (height-width ratio of 2.20). Masonry was made by clay bricks (55x115x255 mm) and a pozzolan (local volcanic ash) based mortar (thickness of 13 mm). Fig. 14- BRM wrapping installation procedure. Experimental outcomes showed that: • BRM confining system could provide a substantial gain both in compressive strength and ductility of concrete members inducing a failure mode less brittle than that achieved in the GFRP wrapped members; • lower performance were observed by concrete confinement provided by a primed glass fiber grid bonded with cement based mortar with respect to BRM and almost no influence was generated by the jacketing with mortar only. • maximum ultimate axial strain increases were provided by GFRP laminates wrapping. Confinement of rectangular masonry columns subject to axial load An experimental campaign dealing with 18 square cross-section both listed faced tuff and clay brick masonry scaled columns subjected to uniaxial compression load. In particular, three different confinement RESEARCH - Seismic behavior Fig. 16- Specimen details (dimensions in mm): (a) tuff masonry; (b) clay brick masonry. Masonry columns were tested through monotonically applied axial compressive loading under displacements control mode with a rate of 0.005 mm/s. The experimental outcomes showed that: • GFRP and CFRP jackets led to similar compressive strength gains on tuff masonry columns under axial loads. • GFRP and BFRP confining system led to similar compressive strength gains of brick masonry columns under axial loads. BFRP wrapping was more effective in terms of global ductility increase (i.e. ulti55 a significant increase in load carrying capacity and ductility after FRP strengthening, which identified the columns as ductile elements despite the brittle nature of the unconfined masonry. Differences in mechanical behavior, due to the geometry of the columns, to the nature of different materials, to different strengthening schemes, and to the amount of reinforcement, have been taken into account. The calibration of design equations recently developed by Italian National Research Council, CNR was conducted to compare analytical prediction and experimental results. Fig. 17- Stress-axial strain relationships and specimens’ failure mode: (a),(c) and (e) tuff masonry; (b),(d) and (f) clay brick masonry. mate strain gain equal to 413% and 259% for BFRP and GFRP wrapping, respectively) even if the mechanical external reinforcement ratio of FRP laminates was lower then GFRP ones; such result could be explained by the higher values of ratios efl/efu recorded on BFRP laminates. • The use of high values of laminates unit height may significant reduce the effectiveness of FRP wrapping systems since it could be detrimental to the quality of confinement execution. • The presence of voids and protrusions on masonry members reduces the ultimate transverse strain on FRP reinforcement with respect to that typically achieved on concrete members. Another experimental campaign has been carried out in order to show the behavior of columns built with clay or with calcareous blocks, commonly found in southern Italy, especially in historical buildings. Rectangular masonry columns were tested for a total of 33 specimens; uniaxial compression tests were conducted on columns taking into account the influence of several variables: different strengthening schemes (internal and/or external confinement), curvature radius of the corners, amount of fiber-reinforced polymer (FRP) reinforcement, cross-section aspect ratio and material of masonry blocks. Materials characterization was preliminarily carried out including a mechanical test on plain masonry. For all cases the experimental results evidenced 56 Fig. 18- Limestone and clay brick masonry specimens. The results obtained from the experimental campaign confirmed that innovative strengthening techniques, using FRP sheets and bars, are effective when confinement of masonry compressed elements is needed. Two types of masonry were investigated: the first made with clay bricks, the second made with limestone blocks. Even if the properties of the constituent materials were different, in both cases a significant increase was measured in terms of peak load and ultimate axial deformation. Two construction schemes were considered: full core and hollow-core columns; the last type reproduces the patterns often found in historical buildings. External and internal FRP confinement were tested, separately and combined. The proposed techniques are strongly recommended when a seismic retrofit is needed, since the external confinement introduces a plastic behavior of the compressed masonry which indicates a large capacity in storing elastic energy which is taken by the fibers placed in the transverse direction. The presence of interRESEARCH - Seismic behavior nal bars used as an internal confinement system is recommended in addition to external FRP layers if ductility constitutes a main issue, since in columns strengthened only with bars the ultimate load was increased but brittle behavior of unconfined masonry remained. Columns with hollow core also showed a significant increase of mechanical properties when confinement was applied, especially in the cases of GFRP external sheets combined with internal bars. Confinement of circular masonry columns subject to axial load An extended experimental investigation has been performed in order to show the mechanical behavior of circular masonry columns built with calcareous blocks that may be commonly found in Italy and all over Europe in historical buildings. Different stacking schemes were used to build the columns, aiming to simulate the most common situations in existing masonry structures. Carbon FRP sheets were applied as external reinforcement; different amounts and different schemes of confining reinforcement were studied. The experimental program included a new reinforcement technique made by using injected FRP bars through the columns cross section. The structural behavior of masonry columns damaged under different levels of load and strengthened by using FRP reinforcements has been also investigated. Fig. 20- Specimens after failure. • Displacement capacity resulted increased in all cases; strengthened columns tested showed an extended postpeak plastic branch in the load versus displacement curves; • Columns confined with three 100 mm wide sheets showed higher mechanical properties with respect to the same columns confined with two 150 mm wide sheets; • Damage caused by overloads applied in the precracking stage before strengthening did not reduce the mechanical properties of FRP-confined columns; • Presence of internal FRP rebars acted as an effective confining system for cross sections composed by four blocks; • Application of design equations by Italian CNR furnished conservative results for complete FRP wrapping, whereas prediction of strength for masonry confined with CFRP strips showed a reduced scatter with respect to experimental results. 4.4 Task 8.4: the strengthening in flexure and in shear of RC structural elements with FRP fabrics and near surface mounted (NSM) rods. A new technique for the shear and flexural strengthening of RC structural elements has been investigated in this research task. In particular, the use of Near Surface Mounted rods (NSM) for structural upgrading has been deeply analysed by both analytical and experimental investigations. Further, the effectiveness of FRP laminates, traditionally used to strengthen RC or masonry members, has been investigated with reference to full scale prestressed concrete (PC) girders. Fig. 19- Geometry and dimensions (mm) of columns. Important remarks follow: • High increase in ultimate strength and strain were evident after strengthening; • Complete FRP jacketing was much more effective than discontinuous wraps; RESEARCH - Seismic behavior NSM bars shear contribution: a calculation procedure A calculation procedure suitable for practitioners has been developed by simplifying a more sophisticated predictive model recently developed (Bianco 2008; Bianco et al. 2009a-b). That procedure briefly consists of: a) evaluating the average structural system composed of the 57 average-available-bond-length NSM strip confined to the corresponding concrete prism whose transversal dimensions are limited by the spacing between adjacent strips and the beam cross section width (Figure 20); b) determining the comprehensive constitutive law of the average system above (Figure 21); c) determining the maximum effective capacity that the average system can attain during the loading process of the strengthened RC beam by imposing a kinematic mechanism and d) determining the NSM shear strength contribution by summing the contribution provided by each strip. The constitutive law (Figure 22) and in turn the equations to determine the maximum effective capacity assume different features depending on the main phenomenon characterizing the ultimate behaviour of the average structural system of the specific case at hand. Hereinafter, for the sake of brevity, the main features of that computational procedure are shown only for the case of shallow concrete fracture (u = 4) and a resulting resisting bond length whose value is equal to the effective bond length (Figure 23). Further details can be found elsewhere (Bianco 2008). The predictions obtained by that calculation procedure were also appraised on the basis of experimental results (e.g. Dias et al. 2007). The maximum effective capacity for the case of shallow concrete fracture and a resulting resisting bond length whose value is equal (u = 4) to the effective bond length can be evaluated by: A Csf max sf 2 Vfi,eff = 1 A1C1 Ld f,max+ 2 2 arcsin(1–A3f,maxLd)+ Ld 2A3f,max +(1–A3f,maxLd) 1–(1–A3f,maxLd)2 – 2 [ { ]} where: L J l3sin(q+ ) A1= p 3 ; 40J1 J sf C1=1– 0 2 1 ; l f,max=1= 21 Ldsin(q+ ) A2=LpJ3l; A3= C2sf = 0J1 l2 (1) l2sin(q+ ) ; 20J1 (2) (3) Actual Vf and design value Vfd of the NSM shear strength contribution can be obtained as follows: max 1 1 l Vfd= Vf = (2Nf,int Vfi,eff sin ) (4) Rd Rd where Rd is the partial safety factor divisor of the capacity that can be assumed equal to 1.1-1.2 according to the indeterminateness of the input parameters. Bond between NSM bars and surrounding concrete: experimental and analytical investigation Fig. 21- Main features of the calculation procedure: a) average-length NSM strip and concrete prism of influence, b) adopted local bond stress slip relationship, c) NSM strip confined to the corresponding concrete prism of influence and semi-pyramidal fracture surface, d) sections of the concrete prism. Fig. 22- Possible comprehensive constitutive law of an NSM CFRP strip confined within a prism of concrete: (a) concrete that reaches the free extremity (u=1) or strip tensile rupture (u=2), (b) superficial and/or absent concrete fracture and ultimate resisting bond length smaller (u=3), equal (u=4) or larger (u=5) than the effective bond length and (c) deep concrete fracture (u=6). Fig. 23- Maximum effective capacity along the CDC for the case u=4: a) comprehensive constitutive law; b) capacity Vfi,CDC (;); and c) imposed end slip Li,CDC (;); distribution along the CDC for different values of the CDC opening angle and d) effective capacity as function of the angle . 58 Pull-out test were carried out to investigate both the qualitative and quantitative influence of some of the involved parameters on the bond performance (De Lorenzis and Galati 2006, Galati and De Lorenzis 2006). Those parameters encompass: ratio between depth and width of the slit, kind of epoxy-based adhesive used as binding agent, distance of the NSM bar from the edge of the concrete prism, distance between adjacent bars and employment of external FRP strips used to confine the joint. Tests were carried out by means of a tangential-pull device to apply the load, LVDT transducers to measure the slip at both the loaded and unloaded extremity and strain-gauges throughout the adhered length of the bar to measure the deformations along the joint. The measured quantities were processed to obtain the local bond stress-slip relationship for the different values of the test parameters. Cyclic tests were also carried out subjecting the joint at a limited number of cycles whose maximum load was assumed equal to different percentages of the peak static load. The cyclic tests were useful to evaluate the joint residual strength such as the one following a seismic action. An analytical investigation has followed the experimental program above (Rizzo and De Lorenzis 2007-2009b). In fact, the local bond RESEARCH - Seismic behavior stress-slip relationship obtained in the pull-out tests has been modelled by suitable analytical functions whose unknowns were calibrated for the different values of the test parameters. The local bond stress-slip relationship obtained by the cyclic tests was also modelled by analytical functions. Then, the numerical solution of the governing differential equation has allowed the peak pull-out load be determined as function of the available bond length. The pull-out tests were also simulated by a FE model, both in the Linear and Non Linear range. The Linear FE model was adopted to evaluate the bond-induced stresses on a plane transversal to the bar, evaluating the maximum stresses for different values of the geometrical and mechanical parameters of the joint and estimating so, local tangential stress inducing the first-cracking in both resin and concrete. After that, a Non Linear model was developed by modelling: a) the several materials according to the fracture mechanics and b) concrete/adhesive and adhesive/FRP interfaces by employing interface elements. Experimental and analytical investigation on the shear strengthening contribution provided by NSM FRP bars on RC beams Four points bending tests were carried out on RC beams strengthened in shear by NSM FRP bars (De Lorenzis and Rizzo 2006, Rizzo and De Lorenzis 2006-2009a). Those beams were designed in such a way that the theoretical failure mode, for both the strengthened and un-strengthened beams was due to shear-tension. Parameters investigated were: spacing, type and inclination of the NSM bars and the shear-span-todepth ratio. Some beams strengthened by NSM strips were also tested in order to assess the relative effectiveness of the two techniques. The system of FRPs was extensively equipped to measure the deformations in the bars crossing the CDC. Tests have highlighted the possibility of a global failure modes consisting in the detachment of the strengthened cover from the underlying beam core. Such mechanisms had not been pointed out by previous investigations. Two models were developed to predict the NSM shear strength contribution: a) one more simplified and b) a more sophisticated one. The former was based on the Mörsch truss and the employment of a perfectly plastic local bond stress-slip relationship. The latter takes into account a more realistic local bond stress-slip relationship and the interaction between existing steel stirrups and NSM bars. The different local bond stress-slip relationships obtained in the former phase of the investigation were employed to carry out some comparison. From those comparisons it was possible to point out the great importance of the fracture energy as opposed to the shape of the local bond stress-slip relationship. This phase of the investigation has led to the development of useful formulae for the evaluation of the NSM FRP shear strengthening RESEARCH - Seismic behavior contribution to a RC beam. Experimental investigation on full-scale prestressed concrete beams strengthened by means of CFRP Every year, several prestressed concrete (PC) bridge girders are accidentally damaged by over-height vehicles or construction equipment impact. Although complete replacement is sometimes deemed necessary, repair and rehabilitation can be far more economical, especially when the time and the social cost of the method are drastically reduced. The numerous advantages provided by the use of FRP laminates are leading in a sharp increase on their use for bridge construction strengthening. Experimental investigations were conducted in order to validate such strengthening technique on PC damaged members and accurately assess the upper limit of damage amount beyond which FRP laminates are no longer adoptable as repair solution. Starting from such purposes, an experimental campaign was conducted on five full-scale (13.0m long, 1.05m high) PC double T-beams with a reinforced concrete slab, designed according to ANAS (Italian Transportation Institute) standard specifications. One beam was used as control, and the other four were intentionally damaged in order to simulate a vehicle impact by removing the concrete cover and by cutting a different percentage of tendons (17% on two specimens and 33% on the remaining two). The repair, by using externally bonded carbon FRP (CFRP) laminates, aimed at restoring the ultimate flexural capacity of the member, taking particular attention to the laminates anchoring system. In particular, one test was performed on the control beam (referenced as S1), two tests were carried out on intentionally pre-damaged, to simulate an over-height vehicle collision, beams (named S2 and S3, respectively) and the remaining two on pre-damaged specimens upgraded by using two and three plies of CFRP laminates anchored by using U-wraps (named S4 and S5, respectively). In Figure 24 and Figure 25 the test setup and experimental load deflection curves are reported. The experimental study has shown that: 1) a loss of strands equal to 17% and 33% caused a flexural capacity decrease equal to 20% and 26%, respectively; 2) to restore the ultimate flexural capacity of the undamaged PC specimen by using CFRP laminates it is necessary to prevent fibers debonding; 3) U-wraps (width wf= 100mm spaced at pf=150mm) were able to significantly delay debonding but if damaged existing concrete is patched by cementitious mortar, a perfect bond has to be guaranteed during the cross section restoration to prevent localized debonding of longitudinal reinforcement and thus fully exploit the potential effective FRP strain increase; 4) CFRP laminates increased 59 Fig. 24-- Test setup. Fig. 25- Experimental load deflection curves. both stiffness and flexural moment capacity of PC damaged beams (maximum moment recover equal to about 12% and 20% for specimens with 17% and 33% of strands loss, respectively; 5) the strengthening intervention led to weak failure mode with a global ductility loss. The experimental outcomes qualify the application of FRP technique, already adopted in several cases of impacted PC bridges, as an effective tool to restore the flexural capacity of PC girders; however the calibration of theoretical expressions for the computation of the design FRP strain level considering the benefits provided by anchoring systems is strictly necessary. 4.5 Task 8.5: the beam-column and beam-foundation joint reinforcement with FRP According to performance-based design or seismic evaluation of RC buildings, it is crucial to provide a reliable evaluation of the strength and ductility capacity of the beam column joints: experimental and direct observation of damages occurred during recent earthquakes highlighted this. This task focused on some aspects: namely, cracking of the joint panel, longitudinal reinforcement bars slipping are deformability sources and they could alter the capacity and interaction of beam and column members and the joint itself. F.E.M. modeling was adopted as an assessment tool. The finite element code TNO DIANA 9.1 was adopted to simulate and to analyze numerically some real beam column joint sub assemblages, characterized by nonlinear mechanical properties and geometrical detailing, smooth bars, structural deficiencies, as commonly found 60 in existing buildings. Such deficiencies were analyzed by means of parametric analyses to evaluate the possibility to apply external strengthening on members characterized by poor concrete quality, low transverse reinforcement ratios, inadequate confinement due to lacking stirrups (especially in external joints), low bond performance of smooth and ribbed longitudinal reinforcement in columns and beams. Numerical analyses evidenced typical failure modes, crack patterns, influence of mechanical and geometrical properties on the behavior of joints. Some numerical/experimental comparisons were made based on significative tests available in scientific literature (for instance performed by Prof. Shiohara working group) or tested, during the RELUIS Project, by UNIBAS R.U., allowing the numerical F.E.M. model to be validated. The behavior of the joints controls the global seismic behavior of an entire structure and a building in particular, so that its assessment is a crucial task in the strengthening design. Based on such analyses, the validity of analytical models for unstrengthened joints, available in scientific literature, was checked. Such check was supported by local information provided by the detailed, refined, F.E.M. analyses. This numerical tool was a primary tool to understand the damage evolution and to assess the reliability of the main assumptions, equations and procedures according to the “Quadruple flexural resistance in reinforced concrete beam-column joints” (Shiohara, 2001) proposed by Prof. Shiohara working group. To provide a direct, practical tool, oriented to the profession more than a nonlinear refined F.E.M. analysis, it was evaluated the opportunity to extend such consolidated model to the case of externally bonded FRP strengthening of beam column joints. This model is based on the solution of a system of equilibrium equations referred to the four rigid bodies in which the joint can be ideally divided, sometimes neglecting compatibility. This model is able to account for different failure modes and for the contribution of externally bonded FRP strengthening. The main assumptions can be recalled: • Diagonal cracks in the joint form an angle of about 45° • Normal concrete stresses acting on the main cracks can be reduced to an equivalent force • Longitudinal reinforcement provides only axial forces, so that any dowel action is neglected • There is a global symmetry both on the horizontal and vertical plane The joint shear can be evaluated according to the sketch in Figure 26. Vf = T + C's + C'c – Vc Vf = T + T' – Vc (1) (2) where T and T'are the tractions in the longitudinal bars at the joint section, respectively; C'c is the compression force in concrete, while C's is the compression force in the bars. Vj is the joint shear; and Vc is the colRESEARCH - Seismic behavior Fig. 26- Details of the forces due to the elements converging in the joint panel. Fig. 28- The joint system and the external forces. umn shear. In Figure 27 the joint division is shown: there are four rigid and interacting bodies. Each body can be associated to three equilibrium equations. The symmetry of the joints allows the system to be reduced to six equations. Moreover, Figure 28 shows the relation between the column shear, Vc, and joint shear, Vb, based on the equation Vb = m Vc, where m = lc / lb. umn length; and lb is the beam length. (a) Forces in reinforcement and FRP (b) Forces in concrete Fig. 27- Internal forces. The independent equilibrium equations are five. Horizontal and vertical forces equilibrium and moment equilibrium based on point o (the middle of the joint panel) can be expressed as follows: Fx=0, Fy=0, Mo=0, –F1–F2–F3+C1sinq+C2sinq–Nb–F6=0 –F3–F4+C1sinq–C2sinq+mVc=0 1 1 lj lb mV + j (F –F )+ j (F –F )– C =0 2 c 2b 1 2 2c 3 4 2 2 (3) (4) (5) Where Nb is the horizontal force in the beam; F1, F2 are tractions in the longitudinal bars of the beams at the joint section; F3, F4 are tractions in the longitudinal bars of the columns at the joint section; F5 is the traction in the stirrups spread along the height of the joint and reduced to an equivalent force; F6 is the traction in the FRP reinforcement in the x direction and reduced to an equivalent force; C1, C2 are compressions as shown in Figure 27b; jb, jc are the internal lever arms in the beam and column respectively; q is the inclination angle of the main cracks and assumed equal to 45°; Vc is the column shear; lc is the colRESEARCH - Seismic behavior Horizontal and vertical equilibriums of forces follow: Fx=0, Fy=0, F1–F2+C1sinq–C2sinq+Vc=0 –F3–F4+C1sinq+C2sinq–Nc–F7=0 (6) (7) Where Nc is the vertical force in the column; F7 is the traction in the FRP reinforcement in the y direction and reduced to an equivalent force. To evaluate the column shear capacity of an unstrengthened joint, the F1, F2 and F5 forces can be assumed equal to the yielding forces of the corresponding steel reinforcement while F6 and F7 are equal to zero. The five unknowns are Vc , F3, F4 , C1 and C2 and can be evaluated solving the system (3)-(7). To evaluate the column shear capacity of a strengthened joint, the F6 and F7 forces can be equal to the strength capacity of the external FRP reinforcement both in the x and y direction, respectively. To account for both the tensile failure of the strengthening or for a possible FRP debonding, the FRP capacity is given by the minimum between tensile strength and debonding force evaluated, for instance, according to CNR DT200. 4.6 Task 8.6: the design criteria for the seismic retrofit of RC and RCmasonry composite structures with FRP. The applications of Carbon FRP (CFRP) and Glass FRP (GFRP) materials have grown during last years; at present, seismic applications have become comparable if not more frequent than those related to lacks due to gravity loads. The Italian guidelines for FRP interventions (CNR-DT 200, 2004), deal with the use of composite materials to seismically upgrade under-designed RC and masonry structures. From seismic standpoint, FRP strengthening is regarded as a selective intervention technique. Based on the main deficiencies of the existing structure, the driving principles of the intervention are based on two main strategies: 61 1) preventing potential brittle failure mechanisms (i.e. shear failure, lap splice failure, buckling of longitudinal reinforcement in compression) and “soft story” collapse mechanism, and 2) increasing global deformation capacity of the structure, either by enhancing the ductility of plastic hinges without their relocalization or establishing a correct hierarchy of strength by relocalizing the plastic hinges according to capacity design criteria. The retrofit strategy is obtained by combining the above principles; the definition of the retrofit scheme depends on the gap between actual and target performance of the specific structure, costs, functional characteristics and importance of the structure. Experimental studies, aimed at validating the effectiveness of FRP to achieve the above goals, are reported in the following. Seismic strengthening of an under-designed RC structure with FRP The outlined seismic strengthening strategy effectiveness was experimentally investigated within the European research project SPEAR (Seismic PErformance Assessment and Rehabilitation). The structure under examination was designed and built with the aim of creating a structural prototype featuring all the main problems normally affecting existing structures: plan irregularity, dimensions of structural elements and reinforcement designed by considering only gravity loads, smooth reinforcement bars, poor local detailing, insufficient confinement in the structural elements and weak beam column joints (see Figure 29). The structure was subjected to pseudo-dynamic tests, both in its original configuration and retrofitted by using GFRP. tively. The design of the rehabilitation was based on deficiencies underlined by both the test on the ‘as-built’ structure and the theoretical results provided by the post-test assessment. They indicate that a retrofit intervention was necessary in order to increase the structural seismic capacity; in particular, the theoretical results showed that the target design PGA level of 0.30g could have been sustained by the structure if its displacement capacity was increased by a factor of 48%. In order to pursue this objective, the retrofit design strategy focused on two main aspects. First it was decided to increase the global deformation capacity of the structure and thus its dissipating global performance; such objective was pursued by confining column ends with two plies of GFRP laminates. Moreover, the second design key aspect was to allow the structure to fully exploit the increased deformation capacity by avoiding brittle collapse modes. To achieve this goal corner beam column joint panels were strengthened by using two plies of quadri-axial GFRP laminates as well as a wall-type column for its entire length with two plies of the same quadri-axial GFRP laminates used for the above joints (see Figure 30). Fig. 30- Column confinement and shear strength of corner joints (a); shear strength of wall-type column and retrofitted structure overview (b). Fig. 29- (a) Plan view and (b) 3D view of the SPEAR structure. The structure in its original configuration was subjected to experimental tests with maximum peak ground acceleration (PGA) of 0.20 g. Since both theoretical and experimental results showed that the ‘as-built’ structure was unable to withstand a larger seismic action, a retrofit intervention by using FRP laminates was designed. Once the design of the GFRP retrofit was provided, the structure was subjected to a new series of two tests with the same input accelerogram selected for the ‘as built’ specimen but scaled to a PGA value of 0.20g and 0.30g, respec62 Fig. 31- Base shear – top displacement curves for ‘as-built’ and FRP retrofitted structure. The assessment of structural global performance, before and after the strengthening intervention, was performed by nonlinear static pushover analysis in longitudinal direction (positive and negative X-direction, PX and NX, respectively) and in transverse direction (positive and negative Y-direction, PY and NY). In Figure 31, the theoretical base shear-top displacement curves for the RESEARCH - Seismic behavior Fig. 33- Details of the designed rehabilitation system. Fig. 32- – Theoretical seismic performance comparison at 0.3g PGA between ‘as-built’ and FRP retrofitted structure. ‘as built’ and FRP retrofitted structure are depicted with reference to direction NX (where the maximum capacity-demand gap was recorded for the ‘as-built’ structure at the significant damage limit state LSSD). Figure 31, clearly shows that the FRP retrofit is able to greatly increase the global deformation capacity of the structure, slightly affecting its strength. The comparison between the seismic structural capacity and both elastic and inelastic demand is reported in Figure 32 (for direction NX) by using the Capacity Spectrum Approach (CSA) (Fajfar, 2000). Figure 31 clearly shows that column confinement provides the structure with significantly enhanced ductility, allowing it to achieve the theoretical inelastic demand by only modifying the plastic branch of the capacity curve. After that columns and joints were wrapped with GFRP, the retrofitted structure was able to withstand the higher (0.30g PGA) level of excitation without exhibiting significant damage. After tests, FRP was removed and it was shown that the RC core was neither cracked nor damaged. The comparison between the experimental results provided by the structure in the ‘as built’ and GFRP retrofitted configurations highlighted the effectiveness of the FRP technique in improving global performance of under-designed RC structures in terms of ductility and energy dissipation capacity. Seismic rehabilitation of PC bridges by using FRP and SRP materials An innovative strengthening technique based on the combined use of Fiber Reinforced Polymer (FRPs) and Steel Reinforced Polymer (SRPs) RESEARCH - Seismic behavior has been investigated with reference to a PC bridge, named “Torrente Casale” which is part of the Salerno-Reggio Calabria motorway. The bridge, built in the seventies, has been recently enlarged (2001) in order to satisfy the new traffic demands. Due to the recent issuing of a new seismic Italian code, it was decided to assess the bridge capacity, both for gravity and seismic loads, in relation with the new design provisions. The bridge existing documentation has been investigated and both destructive and non-destructive tests have been performed in order to determine concrete and steel reinforcement mechanical properties. Once the bridge geometry and the material mechanical properties were determined, a theoretical analysis was performed showing that the bridge piers (circular cross-section, diameter D=1m, and total height H=6m) were not adequate to sustain the seismic actions. Thus use of SRPs spikes as columns’ flexural reinforcement combined with CFRP laminates wrapping of columns ends has been investigated to increase both member strength and ductility; the structural upgrade was completed by increasing the shear capacity of column cap through CFRP U-wraps (Figure 33). The effectiveness of such technique with respect to a traditional one, based on RC jacketing, has been assessed. The main construction phases of the rehabilitation intervention are reported in Figure 33. 4.7 Task 8.7: the design criteria for the seismic retrofit of masonry structures with FRP. The main design problems concerning the seismic vulnerability mitigation of masonry structures are the strengthening of masonry panels for in plane and out of plane actions, the improvement of FRP action by means of clamping and connection mechanical devices and procedures for the definition of the reinforcement layout in seismic analyses. In order to test the design methods proposed by CNR DT200/2004, sev63 eral seismic studies of complex monumental masonry buildings have been completed by carrying out detailed linear dynamic seismic analyses and FRP retrofit design. In the design several combinations of strengthening techniques were explored in order to point out the real applicability of the cited guidelines. The obtained results cover the following areas: a) Verification of the feasibility of a FRP design through simple modifications of the normal design activity; b) Definition of the feasibility bounds for this retrofit technique in case of monumental buildings; c) Detail types and level of detailing required in real applications; d) Open FRP design problems not covered by the guidelines or lacking of necessary information; e) Comparison of different modelling techniques making use of plate, shell, beam, truss elements to represent the masonry structure; f) Comparison of different material constitutive assumptions for the non linear analysis of strengthened walls and buildings. The main results of the completed research are summarized in the following: a) The FRP reinforcement net design is easily implemented by a simple modifications of the normal design activity. The only needs are: integration of the stress distributions in order to obtain the stress resultants and preparation of a verification sheet including the design rules for bending and shear of a FRP reinforced masonry panel. Actually many companies have implemented DT 200/2004 rules in freeware software which can be helpful in this activity. b) The feasibility bounds for this retrofit technique checked for three monumental buildings analysed, are very different if stuck or mechanically fastened reinforcement is used. In fact, only slight diffuse increase of resistance is obtained by using externally bounded FRP nets. Owing to increase significantly the safety of the building, mechanical devices are mandatory. In this last case true building retrofit is possible. c) The set of the detail types needed for practical applications is very large and many connection types are not yet fully investigated although practically employed. Fibre ropes, bars, fasteners, metallic inserts are mixed in a way almost never covered by existing experiments and guidelines. d) Open FRP design problems include cement matrices, thermal cycling, delamination in compression, real bond of the regularization primer to rough masonry surfaces, behaviour of the mechanically fastened FRP elements after internal delamination. e) Several modelling techniques have been employed in order to carry out the seismic studies. Plate elements in linear dynamic analysis allow for both in plane and out of plane evaluation, but non linear static 64 analysis with this type of discretisation is not a viable solution. Studies on discrete representation of masonry walls by using a refined truss structure to represent the compressive load paths inside the masonry panels showed that this type of discretisation is very simple, allows for complicated constitutive laws, allows easily equilibrium checks, and produces very reliable load – displacement curves. f) The basic choice of associate Mohr – Coulomb or Drucker – Prager elastic plastic constitutive laws can be effective only in limited cases, where dilatancy is not dominant. More effective analyses require a non associate zero dilatancy rule, which is however not common in the professional engineering software. More refined damage rules are actually under way, but not for normal design activity. Truss elements however, allow to introduce complex behaviour by means of geometric discretisation, and by this way, crack tracking can be pursued, even if in a very rough representation. 4.8 Task 8.8: the strengthening of masonry structural elements with FRP systems. The research activity has been performed through experimental tests and theoretical study. In particular, the experimental program has been carried out with reference to masonry panels strengthened with FRP and with SRG and subjected to in plane loads, while the theoretical study concerns the modelling of masonry walls strengthened with FRP. Masonry panels and building strengthened with FRP Several experimental tests have been performed with reference to masonry panels strengthened with different FRP materials (carbon and glass) arranged according to various configurations. In-plane shear–compression tests have been performed on full-scale tuff masonry panels consisted of two-layered walls with the inner part filled with mortar and chips from yellow tuff blocks, considering different FRP materials and strengthening configurations. In particular, two sets of panels have been strengthened with grid pattern carbon fibre unidirectional strips (CFRP), made with three horizontal and vertical strips on each face and two sets of panels have been strengthened with the same layout, but doubling the number of plies. Similarly, four sets of panels have been symmetrically strengthened with a grid pattern on both sides of the panels, but with glass bidirectional fibre strips (GFRP). A further set of panels has been made selecting a different geometric configuration by arranging FRP laminates along the diagonals of both sides of the panels and considering both a CFRP and a GFRP cross layout with either one or two FRP plies. Important experimental evidences have emerged from the performed tests underlying the role of the configuration of the FRP strengthening RESEARCH - Seismic behavior system on the failure mechanism of the tested panels. In fact, while in some cases it has been observed that the debonding of the FRP strips has been the main responsible of the panels failure, in few cases the tensile rupture of the FRP strips has occurred. The different observed failure mechanisms have particularly influenced the behaviour of the strengthened panels both in terms of strength increase and post-peak behaviour (fracture energy). Further tests have concerned square masonry panels composed of clay bricks, strengthened with different FRP configurations and subjected to compression diagonal load. In particular, some of the panels have been strengthened considering both vertical and horizontal CRFP and GFRP strips, while other panels have been strengthened arranging FRP strips along diagonal directions of the panels. Different levels of the strength increase and different failure mechanisms have been observed. In particular, while localized cracks pattern have characterized both the case of un-strengthened panels and the case of panels strengthened by FRP only on one side, a more diffuse crack distribution has been observed in the case of panels strengthened on the two opposite sides. In several cases the debonding of the FRP strips has been also observed. From the experimental studies conducted on FRP strengthened masonry panels, considerations useful for improving the Document CNRDT200/2004 have been deduced. In particular, it has been observed that for the evaluation of the design shear strength of FRP strengthened masonry panels (eqn. 5.16 of the CNR-DT200/2006), the contribution of the masonry component can be evaluated through the eqn. 5.17 (used in the case of reinforced masonry elements) only if the FRP shear strengthening is coupled with FRP vertical elements fixed both at the base and at the top of the panel. For this reason it has been suggested to include in the CNR-DT200 specific design indications concerning this aspect. In fact, it is important to underline that, when the FRP shear strengthening system is not coupled with a flexural FRP strengthening system with efficient anchor elements, the contribution of the masonry material in terms of shear strength is the same of the case of un-reinforced masonry elements. A further aspect deduced with reference to tests on masonry panels strengthened by FRP has concerned the case of fibres arranged along to the diagonal directions of the panel. From the experimental evidences and from global analyses it has been possible to affirm that the contribution of the FRP can be evaluated only considering the component parallel to the shear load. A scale model of a typical tuff masonry buildings has been constructed and tested on the seismic simulation shaking table at the structural laboratory of CESI, Bergamo, Italy. In particular, the test procedure has consisted in three phases: in the first phase dynamic tests have been conducted on the un-strengthened prototype in order to induce some RESEARCH - Seismic behavior damages; in the second phase the prototype has been repaired by selecting GFRP strips arranged according to the Italian Code (Ordinanza 3431/2005, CNR DT 200/2004); in the third phase, dynamic tests have been performed on the strengthened prototype. Experimental evidences have shown that the applied GFRP strips allow to perform fast repair interventions in order to make operational masonry structures severely damaged by earthquake and at risk of aftershocks. In fact, the repaired prototype has showed reduced openings at the horizontal joints (about one-third of the maximum opening observed in the case of un-strengthened prototype) and an increasing of the lateral strength (about +34%). A further aspect emerged from this tests has concerned the importance to provide effective anchorages for FRP strengthening elements in order to avoid the delamination phenomenon which is particularly influenced by cyclic actions. Masonry panels strengthened with SRG Beside the “traditional” Fiber Reinforced Polymers (FRP), the research investigated the possibility of application of innovative composite materials, called Steel Reinforced Grout (SRG), based on high strength steel wires (Ultra High Tensile Strength Steel) forming that are assembled into a fabric and embedded within a cementitious grout. This application in fact could combine, to the traditional advantages proper of FRP, the performances of this new material, reducing installation and material costs, and inducing an increase of ductility. Both composites, FRP and SRG, can be used with perforated or solid brick to form a new strengthening system, called LATLAM ring – beam, that can be used to effectively construct the roof ring beams of a masonry structure. This new system, can be also subjected to a pretension force. The following conclusions may be drawn from the developed research: - the analytical model developed to determine the mechanical behaviour of LATLAM ring – beams has shown good agreement with experimental results and can be incorporated in design provisions; - the experimental tests, performed on full – scale prototypes of LATLAM ring – beams, demonstrated good results in terms of load carrying capacity; - LATLAM ring – beams proved to be a good substitute, either under a technical and economical perspective, of “traditional” reinforced concrete ring – beams. Modelling and analysis of masonry walls strengthened with FRP A further subject of the task research activity has concerned the modelling and the analysis of masonry elements strengthened with FRP. Indeed, recent codes extended the use of displacement-based design 65 methodologies, such as the pushover analysis, to the case of masonry buildings. Thus, different modelling approaches able to capture the structural behaviour of masonry panels strengthened with FRP have been examined: a macro-micro modelling approach; a macro modelling approach; a frame model approach. The first model relies on a homogenization approach combined with limit analysis suitable for the evaluation of the collapse loads and failure mechanisms of FRP reinforced masonry panels. The application of FRP strips on masonry has been treated adopting a simplified multi step approach. In the first step the un-reinforced masonry, regarded as a periodic heterogeneous material, has been substituted with a homogeneous macroscopic material using a homogenization technique. In particular, an estimation of the homogenized unreinforced masonry strength domain has been obtained by means of a micro mechanical model based on the lower bound theorem of limit analysis. In the second step, FRP strengthening has been introduced on the already homogenized masonry material. The second model is based on the use of both 2D or 3D nonlinear behaviour finite elements and interface elements. In particular, special yield criteria coupled with nonlinear constitutive laws characterized by softening response have been selected in order to simulate the behaviour of masonry material both in tension and compression. A special nonlinear constitutive law has been also considered for the interface elements in order to simulate the debonding mechanism of FRP which characterizes in several cases the failure mechanism of masonry elements strengthened with FRP. Finally, the third modelling approach consists of a simple but effective 1D frame element able to predict the response of masonry structures, eventually reinforced with FRP materials. In fact, the proposed elements presents some peculiarities both for converting the geometry of a masonry panel in the geometry of the equivalent frame and for accounting the nonlinear behaviour of masonry and FRP materials. Special components have been also provided in the developed model in order to account for the shear failure modes. Several numerical applications have been carried out using the proposed modelling approaches and considering experimental cases deduced from literature. The obtained results, regarding both unstrengthened and FRP-strengthened simple panels and masonry façades, have shown the reliability of the proposed models to reproduce the experimental behaviour of masonry elements underlying some peculiarities due to the presence of the FRP strengthening system. In fact, the micro-macro and the macro modelling approaches have particularly underlined the role of the FRP strengthening system to change the stress path and, consequently, to induce different damage states characterized by a diffuse crack path along the strengthened elements. 66 This aspect has revealed the important role of the FRP system to increase the energy dissipation capacity of masonry structures. The increase both in terms of strength and ultimate deformation capacity of strengthened elements has been confirmed by all the modelling approaches evidencing the capability of the simple frame model to capture the global response of masonry elements strengthened with FRP and consequently the possibility of using this simple model in a design process of the FRP strengthening system for masonry structures. 4.9 Task 8.9: the strengthening of masonry vaulted with FRP systems. The aim of the research task is the development of models and procedures for the analysis of vaulted structures reinforced with FRP. In particular the behaviour of arches, vaults and domes subjected to seismic action is studied in order to investigate the behaviour of these typologies as built and strengthened with FRP materials. The study is performed with simplified analytical procedure and with numerical methods. Experimental tests are further expected for the validation of the models. The research activity has been focused on the experimental tests on the topic available in literature for a comparison with the analytical and numerical results. On the basis of the acquired data, a simplified analytical model for the evaluation of the ultimate load of arches and portal frames reinforced at the intrados and/or extrados has been developed. The main results are related to the definition of a methodology for the evaluation of the ultimate load of one-dimensional vaulted structures reinforced with FRP and subjected to vertical and horizontal forces. Starting point of the procedure is the assessment that the FRP presence does not allow the formation of the collapse mechanisms, which characterise the ultimate behaviour of the un-reinforced structure. As a consequence the cinematic approach of the limit analysis, usually adopted for this kind of structure cannot be applied. The proposed analytical model, starting from the analysis of the ultimate behaviour of the unreinforced structure, identifies the location of the hinges, up to make the structure statically determined, and then to be solved with equilibrium condition. Obviously in this case and contrarily to the limit analysis, the mechanical characteristics of the masonry and of the FRP and mainly the debonding phenomenon of the composite material, significantly influence the structural response. The model has been developed and applied to assigned geometries of arches and portal frames, subjected to static vertical and horizontal loads, with FRP reinforcement at the intrados. The obtained results have been expressed in terms of interaction domains in the plane of the vertical and horizontal forces. Afterwards, the procedures for the evaluation of the ultimate behaviour RESEARCH - Seismic behavior of masonry arches reinforced with FRP have been extended to other typologies, such as the masonry portal frames reinforced at the intrados or extrados. In particular has been defined the formulation of a secant linear relationship defined by the maximum load and by the related displacement at the brittle failure, to be adopted for the estimate of the seismic behaviour of the structure. This model, even if simplified, can be suitable for simulating the response of vaulted structures subjected to vertical and horizontal loads, strengthened with FRP sheets. In this case, indeed, if the FRP is applied at the intrados, the failure is due, generally, to its delamination, while if the composite material is glued at the extrados, the failure is due to compression of shear crisis of the masonry. Anyway the global behaviour of the structure is often characterised by an almost linear response up to the maximum load, ad generally with a brittle failure. Numerical FEM procedures in bidimensional field, have been further developed. The comparison between the results obtained with the two methodologies has allowed the validation of the simplified models. Parallel to the analytical-numerical models, an experimental program has been set up, on vaulted structures reinforced with FRP. Three circular arches, subjected to a key load, have been tested. The first one represents the reference un-reinforced, the other two have been strengthened with FRP at the intrados. The tests have been performed in displacement control, with the aim of evaluating the postpeak behaviour and the softening branches. The results obtained have allowed the preliminary validation of the model related to arches reinforced at the intrados. The last phase of the research was devoted to the validation of the developed models, through experimental tests on masonry vaulted elements. In particular, besides the preliminary tests in masonry arches reinforced with FRP at the intrados, a test has been performed on a masonry portal frame, in full scale, reinforced with FRP and subjected to vertical and horizontal loads. The obtained results allowed the validation of the analytical models and assessed the validity of the assumed simplified hypotheses. Fig. 34- Portal frame under construction. RESEARCH - Seismic behavior Fig. 35- Portal frame during the test. In the Laboratory of Structures and Materials of the Department of Civil Engineering of the University of Rome “Tor Vergata”, has been realized a masonry portal frame, constituted by two columns with rectangular section (24cm x 49cm) and height of 2m, and an arch with internal radius Ri = 130cm and square section with side equal to 24 cm. The portal frame was constructed with masonry block on mortar beds, and then reinforced with a layer of FRP at the intrados of the arch and on the internal surface of the columns. No anchorage of the composite has been given at the foundation level. A constant vertical load (v) has been applied on the arch key and two horizontal increasing loads, with equal intensity (H/2) are given at the arch abutments, which simulate a seismic action. The experimental results on both the arches and a portal frame appear to validate the simplified models and the procedures developed in this research program for the design and check of masonry vaulted systems reinforced with FRP. 4.10 Task 8.10: the quality control and monitoring of FRP applications to existing masonry and RC structures. Several masonry and reinforced concrete structures have been utilized for the application of fiber reinforced composite materials, with the aim of carrying out quality control and monitoring tests, in accordance to CNR DT 200/2004. For each structure, special working sheets have been developed for a proper characterization of the building from a geometrical, mechanical and logistic point of view. On these structures semi-destructive tests, non-destructive tests and delamination tests have been performed. Semi-destructive tests This test consisting in pull-off and shear tearing tests conducted on different types of FRP materials, applied on the in-situ structures. Moreover, pull-off tests and shear tearing tests have been conducted in the laboratory of the Department of Structural Engineering of University of Calabria on concrete elements as well, reinforced by carbon fiber sheets and laminates. The latter tests results have been utilized for a comparison with a number of experimental tests conducted at the Universities of Bologna, Naples, Sannio and Milan, in the framework of Task 8.2 Round-Robin tests, with the aim of obtaining a standard test procedure for delamination tests and evaluating the scattering between experimental results derived from tests conducted on specimens realized by the same worker, but tested in different laboratories. The tests have been conducted using the same device used for outdoor tests. Pulloff tests, used to assess the properties of the strengthened substrate, have been carried out attaching a thick circular 75 mm diameter steel 67 plate to the FRP and isolating it from the surrounding FRP with a core drill, taking particular care in avoiding heating of the FRP system while a 1-2 mm incision of masonry substrate was achieved. The test consists in pulling off the steel plate by means of an ad hoc device (Figure 36a), obtaining the ultimate pull-off strength value expressed in kN (Figure 36-c). Whereas, shear tearing tests are used to assess the quality of bond between FRP and masonry substrate. These tests can be conducted only when it is possible to pull a portion of the FRP system in its plane located close to an edge detached from the masonry substrate. The tests have been carried out using the same ad hoc device used for pull-off tests. In particular, metallic elements have been set up onto the masonry wall and through the FRP strip, with the aim of connecting the entire test device. Then, the FRP element has been tightened until collapse (Figure 36-b), obtaining the failure tearing force, expressed in kN (Figure 36-d). For what concerns in situ tests, 16 reinforced concrete structures and 17 brick and stone masonry building have been considered, for a total number of more than 300 tests. The FRP materials have been applied in the form of strips having the dimensions of 500x200 mm and 50x200 mm in the case of r.c. structures and the dimensions of 500x300 mm e 50x300 mm in the case of masonry structures for the execution of pull-off and shear tearing test, respectively. Both carbon, glass and natural fiber composites have been utilized. According to CNR DT 200/2004, FRP application may be considered acceptable if at least 80% of the tests return a pull-off stress not less than 10% of masonry support compressive strength, or not less than 0.9-1.2 MPa in the case of reinforced concrete structures, provided that failure occurs in the support itself. For what concerns shear tearing tests, FRP application may be considered acceptable if at least 80% of the tests return a peak tearing force not less than 5% of masonry support compressive strength, whereas it has to be not less than 24 kN in the case of reinforced concrete structures. For what concerns masonry structures, taking into account the compressive strength of the support, both pull-off and shear tearing experimental results respect the limit values suggested in CNR DT 200/2004. In the case of concrete structures, pull-off results are in accordance to CNR DT 200/2004, whereas in shear tearing test results the limit value of 24 kN suggested for reinforced concrete structures, has never been reached. This is probably due to the small dimensions of the FRP strips. In fact, CNR DT 200/2004 Guidelines don’t provide any instruction about the FRP dimensions that should be utilized to reach the above mentioned limit value. In the case of pull-off tests, failure has always occurred in the substrate, for each type of FRP material applied, as expected. The semi-destructive tests conducted in the laboratory on concrete ele68 Fig. 36- Pull-off test (a) and shear tearing test (b); Pull-off test result (c) and shear tearing test result (d). ments reinforced by CFRP sheets and laminates have been realized. From mechanical characterization tests, a value of 25 N/mm2 for concrete compressive strength was found. The Research Unit of University of Calabria tested 3 prisms reinforced by 3 CFRP strips and CFRP laminates applied on their surfaces. Pull-off and shear tearing tests have been conducted, with the aim of studying the failure mode and debonding of FRP from the substrate. The results of pull-off tests conducted on both strips and laminates respected the limit values suggested in CNR DT 200/2004, and also in these cases failure occurred in the substrate, showing the effectiveness of the FRP application. On the other side, shear tests showed a different behaviour of the composite materials for strips and laminates. In particular, in the case of laminates, the collapse occurred suddenly and the whole composite debonded from concrete, with an ultimate value of the shear force higher than 24 kN (limit value suggested in CNR DT 200/2004). In the case of CFRP strips, a partial delamination of the composite occurred and the limit value was never reached. Non-destructive tests Non-destructive tests, consisting in thermographic tests were conducted on both brick masonry elements built in the laboratory and on the same real masonry structures used for the above mentioned semidestructive tests, reinforced with different FRP materials. These tests are usually carried out to characterize the uniformity of FRP application. Both, the active and the passive thermography technique have been adopted, in which thermal energy is applied externally onto the test object or the natural infra-red radiation emitted by the object due to a sufficient exposure to sun light can be utilized, respectively. RESEARCH - Seismic behavior The first Infra-Red thermographic tests have been conducted in the laboratory of the Department of Structural Engineering of University of Calabria on brick masonry macro-elements, which have been reinforced by carbon fiber strips placed in different directions onto the specimen surfaces. From the test a mortar joint was clearly visible due to the non plane substrate surface. The in situ masonry and reinforced concrete structures have been utilized for thermographic tests as well, to verify the quality of bond between FRP and the substrate, before and after the conduction of the described semi-destructive tests. For instance, some tests have been conducted on a reinforced concrete structure on which FRP strips have been previously applied for shear tearing tests. From the thermograms, a crack could be noticed corresponding to the strip subjected to the semi-destructive test. Such a technique is then useful for the detection deterioration and damage in the structures. Influence of roughness surface on the debonding force of FRP In order to investigate the effect of the concrete surface preparation method on the roughness surface and debonding force of FRP, an experimental campaign has been carried out. The specimens have been produced with different formworks (staves, panels) and different compaction types (beating, vibration). Moreover, two different concrete strengths have been used in realizing the specimens in order to evaluate also their influence on the surface preparation method efficacy. Thirty 15 cm-length standard cubes have been also poured and used to evaluate the mechanical properties of concrete (according to Italian standards). Mean compressive strength (Rcm = 15 or 20 MPa) from the compression tests has been obtained by standard cube at an age of 50 days, corresponding to same period of the first profilometer tests. The number of specimens considered in the present experimental campaign and the two different casting processes are shown in Table 1. After curing, four different methods for surface preparation have been applied on concrete prisms in order to study the effect of the treatment on the FRP-concrete bond strength: Grinding – the upper surface of the concrete block has been grinded with a stone wheel to remove the top layer of mortar, just until the aggregate was visible; Sand Blasting – the concrete surface has been sand blasted in order to remove the whole mortar over the aggregates, so obtaining a very rough concrete surface; Brushing – the surface has been brushed with a twisted steel cord bonded to a rotating disc; Scabbling – impacting the substrate at variable angle with a metallic tip to create a chipping and powdering action. The driving mechanism is compressed air. In order to examine exhaustively the concrete surface, an extensive campaign of laser profilometer analysis was carried out before and after RESEARCH - Seismic behavior the surface preparation. The profilometer used is the DRSC produced by Miami University, which gives quality and quantity information. This instrument using laser striping, highlights the rough concrete surface by thin slits of red laser light at an angle of 45 degrees, and the surface is observed at 90 degrees by an high-resolution (tiny) board CCD camera (Figure 38a). The video image of the laser stripes is digitized with a PCMCIA frame-grabber. The projected slit of light appears as a straight line if the surface is flat, and as a progressively more undulating line as the roughness of the surface increases. Lasers with one to eleven stripes were used. The roughness degree can be identified by several parameters obtained by laser profilometry and each one can give specific information on roughness and its particular properties. They can be classified in amplitude parameters (Ri of Figure 37) and slope parameters (ia of Figure 37a). The first group is sensitive to roughness morphologies, where the surface is either stepped or slotted and might be described as a discontinuous roughness, the second group is insensitive to roughness morphologies and is more useful for characterizing continuous roughness. Table 1 Specimens and summary of test sample N° Specimen Dimension Mean Compressive (mm) Strength (N/mm2) 20 ? 15 160 x 400 x 600 20? 20 Formwork Type of (wooden) Compaction staves beating panels vibration Fig. 37- Roughness parameters. Figure 37b shows some output parameters provided by the profilometer: Rmax – maximum peak and valley, rough measure of the vertical distance between the highest peak and the lowest valley; Re measures the vertical distance between the highest peak and the centerline of the profile; Rv measures the vertical distance between the lowest valleys and the centerline of the profile; R measures the average of all individually measured peak to valley heights, Rp – roughness profile index, defined as the ratio of the true length in the fracture surface trace to its projected length in the fracture plane; iA is the micro-average inclination angle, representing the average of the pixel to pixel angles of the stripe profile. In order to define a unique parameter for describing the surface roughness, profilometer parameters were analyzed and correlated. For each parameter given by the profilometer, average value and covariance have 69 Fig. 38- (a) Laser profilometer, (b) geometry of FRP-strengthened prism and (c) experimental set-up. Fig. 39- Average values (a) and covariance (b) of IR parameter for different surface preparations. been calculated for evaluating the quantity and quality factors of roughness. The covariance can provide for information on surface homogeneity; both quantities are interesting especially regarding the efficiency of concrete surface preparation methods. In the following, the roughness is described by coefficient IR = Ria, where R and ia have been described before. The parameter IR is used to give information on the absolute value of the roughness and on its specific shape. Profilometer analysis allows to correlate the casting methods with various degrees of roughness. In fact, the specimens casted with staves are more rough because the disconnection of the staves increase the surface irregularity. The specimens compacted by means of the vibration are more rough due to different positions of aggregates and the presence of vacuum produced by air bubbles. The roughness of the concrete surface has been investigated before and after the preparation; its difference is a way to evaluate the efficiency of each surface preparation method. In Figure 39a,b are shown the average values and the covariance of the IR parameter for all the different surface preparation methods. Figure 39a shows that all the surfaces prior to the treatments have very similar roughness while after them the mean value of the IR parameter is particularly high in the case of scabbing and sand-blasting. On the contrary, all the surface preparation methods strongly reduce the statistical dispersion of IR parameter (Figure 39b); the scabbing and sand-blasting provide for the higher level of homogeneity. been conducted on two half bricks placed inside a properly designed steel frame and connected between them by means of two carbon, glass or natural FRP strips glued on both sides of the specimens. The frame has been designed in such a way as to avoid any hindrance to the specimen collapse. The specimens have been subjected to uniaxial tensile tests under displacement control by means of an electro-mechanic testing machine, with a capacity of 100kN, connected to a personal computer. Some specimens have been also monitored by means of unidirectional strain gauges applied both on the brick surface and on the fibres. From the experimental tests, the specimens failure mode has been analysed. Collapse has occurred for delamination in almost all cases. However, some specimens have reached failure due to fibres crack, as in the case of glass fibers and natural ones due to the different stiffness of the FRPs. More than 30 specimens have been tested. In the case of specimens reinforced by carbon and glass fibers, the load-displacement curve relative to failure for delamination obtained from the strain gages applied on FRP and brick surfaces was almost linear until failure which occurred suddenly and for debonding of the fabric from the reinforced bricks, with consequent removing of part of the substrate surface. The presence of relevant traction stresses is observed at the attachment of the FRP strip with the bricks where the delamination phenomenon begins. For what concerns the tests conducted on bricks reinforced by natural fibers, the results, obviously, cannot be compared to the ones derived from brick reinforced by CFRP or GFRP; however, the tests have shown interesting properties of natural fibers for not bearing applications such as on ancient masonry structures where FRP mechanical behaviour sensibly affects the global behaviour of the structure. Finally, for each tested specimen, an accurate study of the substrate after failure has been conducted for the exact definition of the delaminated surface dimensions; the crack begins at a depth of about 10 mm Delamination tests Delamination tests have been carried out on bricks reinforced with FRP materials, with the aim of studying both the collapse load value and the failure modes that can occur if FRP materials applied during strengthening interventions collapse. In particular, delamination tests have 70 Fig. 40- Failure mode of bricks reinforced with CFRP strips subjected to delamination tests. RESEARCH - Seismic behavior and this distance obviously depends on the experimental equipment, whereas the depth and the form of delaminated substrate appear almost constant and dependent on the testing modality (Figure 40). From both in-situ and laboratory tests, important information were obtained regarding composite materials behaviour and experimental procedures. In particular, it was noticed that shear tearing tests are extremely affected by instrumental errors that can take place during the test conduction. In fact, while FRP laminates allow a perfect alignment of the composite with respect to the hydraulic pull machine, in the case of FRP strips the applied force is not perfectly aligned with the FRP – concrete interface, and peeling stresses are generated, so causing a significant reduction of the debonding force. Then, on the basis of the above described experimental results and in accordance to workshops organized during the Research Activity, some variations to the CNR DT 200/2004 guidelines, with particular regard to shear tearing limit value and experimental procedure, were proposed. In particular, shear tearing test should be carried out following two different procedures, namely direct and indirect procedures. The direct procedure is preferred if the load can be directly applied on the FRP glued onto the specimen surface, especially in the case of laminates. If the FRP system is made of strips to be prepared in-situ, the indirect test procedure is preferred, in which load is applied by means of steel plates glued onto the FRP surface. 5. DISCUSSION In this research task a large number of experimental tests has been performed in order to validate the design equations provided by CNRDT200/2004 and to calibrate some coefficients included in these equations to better fit theoretical predictions and experimental results. Experimental tests have been carried out on both real scale or scaled members by using traditional FRP systems or innovative typologies of FRP systems and advanced materials. The experimental tests have RESEARCH - Seismic behavior been focused on both masonry and reinforced concrete members. In particular, advanced FRP materials made of basalt fibers (bonded with traditional or inorganic cement matrix) have been used for the confinement of RC and masonry columns. In addition, the mechanical properties of several FRP systems at fixed environmental conditions and/or under cyclic actions, the behaviour of RC members confined or strengthened in flexure and shear as well as of beam-column and beam- foundations joints have been deeply analyzed. Design criteria for the seismic retrofit of masonry members and structures have been also provided. The outcomes of experimental activities have, in most cases, confirmed the reliability of CNR-DT200/2004 provisions, especially for RC members. Regarding to masonry members, test results indicate that some coefficients of theoretical expressions provided by CNR-DT200/2004 have to be refined and some other experimental results could be necessary to derive theoretical relationships specifically targeted at different masonry substrates and failure modes. 6. VISIONS AND DEVELOPMENTS Innovative materials for the vulnerability mitigation of existing structures have been largely analysed in the research activity. Further, new typologies of FRP systems, also made of several fibers and matrices types are spreading; on these new typologies further investigations are strongly necessary in the future. The study of the feasibility of using composite systems made of inorganic matrix strengthened with natural fibers fabrics is needful. In fact, the idea of using natural fibers is due to economic and environmental sustainability suggested by the use of such materials. These studies could allow new FRP systems to be inserted in the actual guidelines in order to increase their use in the civil engineering applications. The indications provided by CNR-DT 200/2004 for the vulnerability mitigation of existing structures have been accepted by recent Italian guidelines, but further experimental tests will need, especially to mitigate the vulnerability of existing masonry structures. 71 7. MAIN REFERENCES - Aprile A., Benedetti A., Cosentino N., (2006), “Seismic Reliability of Masonry Structures Strengthened with FRP Materials”, 100th Anniversary Earthquake Conference, San Francisco, paper n° 1677. - Aprile A., Benedetti A., Steli E., Mangoni E., (2007), “Seismic Risk Mitigation of Masonry Structures by Using FRP Reinforcement”, FRPRCS-8 University of Patras, Patras, Greece, paper n° 424. - Anselmi V., Aprile A., Benedetti A., (2005), “Safety and reliability of structures including ductile and brittle elements”, ICOSSAR 2005, Augusti, Schuëller, Ciampoli (eds), pp. 2183-2188, Rotterdam, ISBN 90 5966 040 4. - Ascione F., Feo L., Olivito R.S. and Poggi C., “La qualificazione dell’esecuzione degli interventi di rinforzo strutturale con FRP a margine delle recenti ”Istruzioni per la progettazione, l’esecuzione ed il controllo di interventi di consolidamento statico mediante l’utilizzo di compositi FRP””, Proceedings of National Italian Conference “Ambiente e Processi Tecnologici – La certificazione di Qualità dei materiali e dei prodotti da costruzione” (in Italian), Naples (2005). - Bastianini F., Olivito R.S., Pascale G. and Prota A. (2005), “Controllo di qualità e monitoraggio dei rinforzi in FRP”, L’Edilizia (in Italian), 139, 66-71. - Benedetti A. and Steli E. (2007), “Analytical Solution of the Shear – Displacement Curve for Reinforced Masonry Panels”, The Tenth North American Masonry Conference, St. Louis, Missouri, ISBN 1-929081-286. - Benedetti A., Camata G., Mangoni E., and Pugi F., (2007), “Out of Plane Seismic Resistance of Walls: Collapse Mechanisms and Retrofit Techniques”, The Tenth North American Masonry Conference, St. Louis, Missouri, ISBN 1-929081-28-6. - Benedetti A., Mangoni E., Montesi M, Steli E. (2007), “Verifiche di Sicurezza ed Interventi di Consolidamento Della Chiesa di S. Martino in Casola”, INARCOS, 680, pp. 411-423. - Benedetti A., Steli E., (2008), “Analytical models for shear–displacement curves of unreinforced and FRP reinforced masonry panels”, Construction and Building Materials, 22, pp. 175-185, doi:10.1016/j.conbuildmat.2006.09.005. - Bianco V. (2008), “Shear strengthening of RC concrete beams by means of NSM CFRP strips: experimental evidence and analytical modeling”, PhD Thesis, Dept. of Struct. Engrg. And Geotechnincs, Sapienza University of Rome, Italy, submitted on December 2008. - Bianco V., Barros J.A.O., Monti G. (2009a), “Bond Model of NSM FRP strips in the context of the Shear Strengthening of RC beams”, ASCE Journal of Structural Engineering, in press. - Bianco V., Barros J.A.O., Monti G. (2009b), “Three dimensional 72 mechanical model for simulating the NSM FRP strips shear strength contribution to RC beams”, Engineering Structures, Vol. 31 n. 4, Elsevier. - Bruno D., Greco F., and Lonetti P. (2005), “A 3D delamination modelling technique based on plate and interface theories for laminated structures”, European Journal of Mechanics A/Solids, 24, 127-149. - CNR DT 200/2004, “Guide for the Design and Construction of Externally Bonded FRP Systems for Strengthening Existing Structures”, Italian National Research Council, Rome (2004). - De Lorenzis L., Rizzo A., (2006), “Behaviour and capacity of RC beams strengthened in shear with NSM FRP reinforcement”, 2nd Int. fib Congress, Napoli-Italy, June 5-8, Paper ID 10-9 in CD. - De Lorenzis L., Galati D. (2006), “Effect of construction details on the bond performance of NSM FRP bars in concrete”, Proceedings fib Congress, Napoli, Giugno 2006. - Dias S.J.E., Bianco V., Barros J.A.O. (2007), “Low strength concrete T cross section RC beams strengthened in shear by NSM technique”, Workshop Materiali ed Approcci Innovativi per il Progetto in Zona Sismica e la Mitigazione della Vulnerabilità delle Strutture, University of Salerno, Italy, 12-13 February. - Galati D., De Lorenzis L. (2006), “Experimental study on the local bond behavior of NSM FRP bars to concrete”, Proceedings CICE 2006, Miami, USA, December 2006. - Galati D., De Lorenzis L. (2008), “Effect of construction details on the bond performance of NSM FRP bars in concrete”, Advances in Structural Engineering, Multi-science, in stampa. - Milani G., Rotunno T. , Sacco E. and Tralli A. (2006), “Failure Load of FRP strengthened masonry walls: experimental results and numerical models”, Structural Durability & Health Monitoring, 2 (1), 29-50. - Olivito R.S. and Zuccarello F.A. (2006), “Indagine sperimentale per il controllo dell’applicazione di materiali FRP a strutture murarie mediante prove semi-distruttive e non distruttive”, Proceedings of National Italian Conference on Materials and Structures Experimentation (in Italian), Venice. - Rizzo A., De Lorenzis L. (2006), “Analytical Prediction of Debonding Failures in RC Beams Strengthened in Shear with NSM FRP Reinforcement”, Proceedings CICE 2006, Miami, USA, December 2006. - Rizzo A., De Lorenzis L. (2007), “Modelling of debonding failure for RC beams strengthened in shear with NSM FRP reinforcement”, Proceedings FRPRCS8, Patras, Luglio 2007. - Rizzo A., De Lorenzis L. (2009a), “Behavior and capacity of RC beams strengthened in shear with NSM FRP reinforcement”, Construction and Building Materials, Elsevier, Vol. 23, No. 4, pp. 15551567. RESEARCH - Seismic behavior - Rizzo A., De Lorenzis L. (2009b), “Modeling of debonding failure for RC beams strengthened in shear with NSM FRP reinforcement”, Construction and Building Materials, Elsevier, Vol. 23, No. 4, pp. 15681577. RESEARCH - Seismic behavior - Savoia M., Ferracuti B. and Mazzotti C. (2003), “Delamination of FRP plate/sheets used for strengthening of r/c elements”, Proceedings of Second International Structural Engineering and Construction (ISEC02), Rome, Italy. 73 Experimental Research on Seismic Behavior of Precast Structures ver the last two decades an extensive experimental and theoretical research activity aimed to investigate the seismic behaviour of precast structures has been carried out at European scale. The results of this activity allowed to consolidate a good knowledge of the seismic behaviour of precast structures and contributed to the achievement of prefabrication in Europe with outstanding realizations in terms of both quality and reliability. O The research was developed within six research programmes. The first stage developed between 1992 and 1996 during the drafting of the first ENV version of Eurocode 8 (EC8). The initial draft of the specific rules for precast structures gave them the presumption of a very Dimensionless values Fig. 1- Prototype of precast column. bad seismic behaviour. Industrial one storey precast buildings were defined as inverted pendulum systems to which a very low value of the behaviour factor was recognised. This was in conflict with the national codes that did not make any difference between cast-in-situ and precast frames. This was in conflict also with the experience of past earthquakes, where precast structures, except for the dry supports, showed a very good ductile behaviour despite their non seismic design. The lack of experimental data was adduced to justify the heavy penalisation of precast structures in this code. In order to verify the validity of this penalisation the Italian Association of prefabrication industry promoted a campaign of analytical investigations that have been developed at Politecnico di Milano. The investigation have been started with a set of cyclic tests on precast columns. Figure 1 shows one of the prototypes of precast columns tested at ELSA Laboratory of the Joint Research Center of the European Commission at Ispra, Italy. Cyclic and pseudodynamic tests were performed for different reinforcement amount and axial actions. An example of force-displacement diagrams obtained from cyclic tests is shown in Figure 2.a. The energy dissipated over the halfcycles was compared with the maximum value of dissipated energy associated to a perfect elastic-plastic cycle, as shown in Figure 2.b. The results of these tests confirmed: - a good ductile behaviour with specific dissipation around 0.4, as typical for cast-in-situ columns; - a more reliable behaviour due to the absence of bar splices and to the stable position of stirrups during the casting of concrete (precast columns are cast in an horizontal position); Half-cycles (a) (b) Fig. 2- (a) Force-displacement diagrams obtained from cyclic tests. (b) Energy dissipated over the half-cycles compared with the maximum value of dissipated energy associated to a perfect elastic-plastic cycle. 74 RESEARCH - Seismic behavior Fabio Biondini, Giandomenico Toniolo Department of Structural Engineering, Politecnico di Milano, Milan, Italy Fig. 3- Energy dissipation in one-storey frames: (a) monolithic and cast-in-situ; (b) hinged and precast. - the fundamental importance of a narrow spacing of the stirrups against the early buckling of longitudinal bars; - displacement ductility ratios between 3.5 and 4.5 consistent with the code provisions for cast-in-situ frames. The ENV EC8 was therefore published with precast structures no more treated as inverted pendulum, but still penalised with a lower behaviour factor with respect to cast-in-situ systems. The seismic behaviour of cast-in-situ and precast structures has been also investigated by means of proper numerical models on probabilistic bases. This investigation was carried out by means of non linear dynamic analyses reproducing the real vibratory behaviour of the structures under earthquake conditions. The aim was to demonstrate that, under the same seismic action, the monolithic frame shown in (a) Figure 3.a, with four critical cross-sections dimensioned for a moment mFh/2, may dissipate the same amount of energy which the hinged arrangement shown in Figure 3.b dissipates in its two critical crosssections, dimensioned as they are for a double moment M=Fh2m. In fact it is the global volume involved in dissipation, and not the number of plastic hinges, that gives the total amount of energy dissipated by the structure. To demonstrate this assumption, the two prototypes shown in Figure 4 were considered, the first cast-in-situ with monolithic connections, the second precast with hinged connections. They have the same overall dimensions, with the size and reinforcement of the columns chosen to achieve the same vibration periods and the same design seismic capacity in terms of base shear strength. With the combination of the different heights and cross-sections (Figure 5) a number of types of frame were selected for both the frames. The seismic response of the prototype was investigated in probabilistic terms for lognormally distributed material strengths and under artificial accelerograms, randomly generated so to comply with the design response spectrum. A Monte Carlo simulation based on a large (b) Fig. 4- Prototypes of one-storey frames: (a) monolithic and cast-in-situ; (b) hinged and precast. (a) (b) Fig. 5- Cross-sectional details of the columns. RESEARCH - Seismic behavior Fig. 6- Statistical distribution of overstrength ratio k: (a) monolithic and cast-in-situ; (b) hinged and precast. 75 (a) (b) Fig- 7- View of the structural prototypes with (a) monolithic and (b) hinged beam-column connections. sample of incremental nonlinear dynamic analyses taken up to collapse was therefore carried out for each prototype to compute the statistical parameters of the overstrength , ratio of the computed value over design value of the seismic capacity. Figure 6 shows the distribution of overstrength computed for the two prototypes for a set of 1000 accelerograms in one of the cases studied. These results prove that precast structures have the same seismic capacity of the corresponding cast-in-situ structures, and confirm the correctness of the values given by the code to the behaviour factor of concrete cast-insitu frames (q=4.5). Fig. 8- Displacement time-histories for one of the pseudodynamic tests: numerical (thick lines) versus experimental results (thin lines). 76 RESEARCH - Seismic behavior (a) (b) Fig. 9- View of the structural prototypes with roof elements with axis (a) parallel to the direction of the seismic action (Prototype 1), and (b) orthogonal to the direction of the seismic action (Prototype 2). The third stage of research developed during the revision of EC8 for its conversion to the final EN version. The preceding analytical demonstration was effective, but an experimental confirmation was still necessary. Therefore, taking advantage of the Ecoleader programme for the free use of the large European testing facilities, two pseudodynamic tests on full scale prototypes have been performed at ELSA Laboratory. The aim was the direct experimental comparison (a) of the seismic capacities of cast-in-situ and precast structures, and at the same time the validation of the analytical model used in the previous numerical investigation. Figure 7 shows a view of the full scale prototypes. The comparison of the results obtained for these prototypes highlights the expected large seismic capacities (about ag=1g) of this type of structures and confirms the overall equivalence of the seismic behaviour of precast and cast-in-situ structures (see (b) Fig. 10- Experimental tests carried out on a connection. (a) Test set up. (b) Failure mechanism. RESEARCH - Seismic behavior 77 (b) (a) Fig. 11- Tree-storey full-scale prototype. (a) Transversal and (b) longitudinal section. Figure 8). The fourth stage of research was developed within the Growth programme. Two further prototypes consisting of six columns and a mesh of beams and roof elements were designed to investigate the seismic behaviour of precast structures with roof elements placed side by side. Figure 9 shows a views of these prototypes and of the testing plants. The prototypes differ only for the orientation of the beams and roof elements with respect to the seismic action. Common hinged connections are used between roof elements, beams and columns. The control of the pseudodynamic test is based on two degree of freedoms, associated with the top horizontal displacements of the lateral frames, and of the central frame. Also the effects of cladding panels on the structural response has been investigated. The measured top displacements of lateral and central columns during the pseudodynamic tests resulted practically coincident. This result proves that double connection between beams and roof elements gives a rotational restraint in the roof plane which enables the activation of an effective diaphragm action, even if the roof elements are not connected among them. After the pseudodynamic tests both prototypes have been subjected to a cyclic test under imposed displacements up to collapse. With a ultimate displacement du360 mm and a yielding displacement dy80 mm, a global displacement ductility equal 4.5 is deduced, as assumed by the new final version of EC8 for the behaviour factor of precast frame systems. The results of the investigations carried out under the Ecoleader and 78 Growth research projects showed the good seismic performance of precast structures under condition that the connections are properly over-dimensioned. The last aspect to be still clarified is therefore the actual behaviour of connections under seismic excitation. Based on these needs, the European research program Safecast has been recently launched to investigate the seismic performance of connections in precast systems. This project will involve a large campaign of experimental static tests carried out on single specimens, such as the connection shown in Figure 10, as well as pseudo-dynamic tests on a three-storey full-scale prototype shown in Figure 11. The results of the Safecast project are expected to complete the large research program developed in Europe over the last two decades which provided significant advances in the understanding of the seismic behaviour of precast systems and in the definition of reliable design criteria for this type of structures. ACKNOWLEDGEMENTS A number of partners participated to the research, coming from the principal European countries subjected to seismic hazard. The national associations of prefabrication industry were involved (ANIPB for Portugal, ANDECE for Spain, ASSOIBETON for Italy, SEVIPS for Greece, TPCA for Turkey). Also the Italian associations of cement industry AITEC and ready-mix concrete ATECAP participated to some stages. The “research providers” were: JRC – Joint Research Centre of Ispra (of the European Commission), LNEC – Laboratorio Nacional de Engenharia Civil of Lisbon, Politecnico di Milano, University of Ljubljiana, NTUA – National Technical University of RESEARCH - Seismic behavior Athens, ITU – Istanbul Technical University, and the private laboratories LABOR and LUGEA (I). The “users” were some producers of precast structures (Magnetti Building – I, Gecofin – I, Civibral – P, Prelosar– E, Proet – GR), and some auxiliary companies (Halfen – D, DLC – I). What described in the present report refers to the series of European RESEARCH - Seismic behavior researches coordinated by prof. Giandomenico Toniolo of Politecnico di Milano. Many other theoretical and/or experimental researches have been performed on precast structures by initiative of single companies for their specific interests. And this wide activity qualifies the prefabrication industry as one of the most advanced sectors in growth and innovation. 79 State-of-the-art on the Research on Structural Concrete in Italy 1.INTRODUCTION he research activity carried out in Italy on the structural concretes is very busy in both the academic compartments and in the industrial operations. The present report summarizes some of the most important works in this area including three aspects of this activity: - shrinkage compensating concrete in the absence of wet curing; - properties of concretes with recycled aggregates; - use of bottom ash from municipal solid wastes incinerators. T lary tension caused by the formation of water menisci developed in capillary pores and responsible for the shrinkage of the cement paste (Figure 1). 2. SHRINKAGE COMPENSATING CONCRETE IN THE ABSENCE OF WET CURING Shrinkage-compensating concretes have been extensively used in the last forty years to minimize cracking caused by drying shrinkage in reinforced concrete structures. The first and most diffused system to produce shrinkage-compensating concretes involves the use of expansive cements, according to ACI 22398, instead of ordinary portland cement. All these special binders are based on a controlled production of ettringite. Another effective method to produce shrinkage-compensating concretes, not covered by ACI 223-98 but commonly used in some countries, like Italy or Japan, lies in the use of a CaO and/or MgO based expansive agent. This technology seems to be more advantageous with respect to that based on the ettringite formation from an economical as well as from a practical point of view. Recently, the addition of a shrinkage-reducing admixture (SRA) has been found to improve the behavior of CaO based shrinkage-compensating concretes especially in the absence of an adequate wet curing [1]. Although the actual cause of this synergistic effect has not been completely explained, the use of this technology in construction industry has been increased, in the last five years, particularly in Italy, with very interesting results. In the present report three remarkable examples of special reinforced concrete structures are presented in which the use of CaO-SRA based shrinkage-compensating concretes was successfully carried out in order to prevent shrinkage related cracks and/or joints excessive opening in the presence of adverse curing conditions which are normally not suitable for the use of this technique. SRAs (Shrinkage-Reducing Admixtures), are generally based on propylene-glycol ether, neo-pentyl glycol or other similar organic substances, that are able to reduce the drying shrinkage of concrete up to 50% if used in 1-2% by mass of cement. According to Berke et al. [2] the effectiveness of SRA must be ascribed to the decrease in the surface tension of water .This reduces the capil80 • Fig. 1- Water menisci interact with C-S-H fibers determining the shrinkage on cement paste,The New Concrete. Recently [3], the combined addition of a shrinkage-reducing admixture with a CaO-based expansive agent has been found to be very successful in producing restrained expansion of laboratory specimens protected from water evaporation for just 1 day by using a plastic sheet and then exposed to air (60% R.H). The influence of the SRA on the length change behaviour of a shrinkage-compensating concrete includes two different aspects: - the effect in Fig. 2 due to a reduction in shrinkage when the concrete is exposed to drying, as expected for the presence of a shrinkagereducing admixture; - the unexpected effect, which is an increase in the restrained expansion when the concrete is protected from drying with respect to that obtained without SRA, all the other parameters being the same. By using a combination of CaO and SRA, then, it is possible to reduce the amount of expansive agent needed to obtain a fixed restrained expansion. This reduces the risk of residual un-reacted lime in the concrete. Furthermore, the performance in terms of initial restrained expansion and final restrained shrinkage (or residual expansion), of SRA + CaObased shrinkage-compensating concretes is less dependant on the curing efficiency so that the practical use of this technique is easier and the results are more reliable. The synergistic effect in Figure 2 has been confirmed by Maltese et al [4] who have found that the use of a CaO-based expansive agent with a shrinkage reducing admixture allows to obtain mortars less sensitive to drying. These authors hypothesize that the synergistic effect of the RESEARCH - Concrete Mario Collepardi* * ENCO, [email protected] SRA-CaO combination must be ascribed to the massive formation of CaO elongated crystals during the first hours of curing. The same authors in [5] propose another mechanism of action: since the SRA is an organic hydrophobic molecule, it could reduce the water solubility of CaO, retarding its reaction and, then, increasing the restrained expansion according to Chatterji [6]. Otherwise, Tittarelli et al. [7] have found that SRA doesn’t affect the speed of CaO reaction with water. • Fig. 2- Schematic view of the influence of SRA on the length change behavior of a shrinkage-compensating concrete. Although this synergistic effect has been confirmed by several authors, the actual mechanism of action needs further investigations in order to be completely understood. Notwithstanding this lack of knowledge, the use of this technology, in the construction industry, has been growing in the last 5 years with many successful and very interesting results. In the second part of this paper, three remarkable case histories of special reinforced concrete structures are presented in which the use of CaO + SRA-based shrinkage-compensating concretes was successfully carried out in order to prevent shrinkage-related cracks and/or joints excessive opening in the presence of adverse curing and thermal conditions. The difficulties encountered in using this technique, in each case, will then highlight describing the countermeasures which have been taken to overtake them. London, U.K.) had proposed the construction of several architectural concrete walls (20 meters high and 60 meters long) having a sinuous shape and no contraction joints (Figure 3). A special CaO-SRA based shrinkage-compensating self-compacting concrete (SCC) was studied in order to assure a marble-like look, as required by the designers, even in the presence of a very congested reinforcement (Figure 4) and, in the same time, to avoid the formation of shrinkage related cracks along the surface. • Fig. 3- View of bent and joint-less walls of the MAXXI, Rome, Italy. 2.1 Case History of shrinkage compensating concrete in the absence of wet curing: MAXXI of Rome The Museum of Arts of XXI century (MAXXI) in Rome was the first relevant Italian construction in which a SRA + CaO-based shrinkagecompensating concrete has been used (2004-2006). For this very prestigious building, the designers (Zaha Hadid Limited, RESEARCH - Concrete • Fig. 4- Example of steel congestion in a typical wall of MAXXI, Rome, Italy. 81 Figure 5 shows the strength development with time of the three compared SCCs (CaO-SRA, only CaO and Plain). The strength of the expansive concretes was higher than that of the plain mix. This is probably due to the consumption of a small part of mixing water caused by the transformation of CaO into Ca(OH)2 which happens when the concrete is still in the plastic state and to the consequent reduction of the actual w/c. On the other hand, a slight decrease in the compressive strength of the SRA + CaO mix was recorded if compared to that of the CaO mix due to the presence of SRA as experienced in [8]. Although it was specified to protect the concrete surface for at least three days (to assure a correct hydration of the concrete cover) shrinkage compensating concrete was designed in order to warranty a residual restrained expansion of about 200 mm/m even in case of deficient curing consisting in just 24 hours of protection by the formwork. Figure 6 shows the length change of the reinforced prismatic specimens manufactured with the three different SCCs according to ASTM C 878. Specimens were not put under water for 7 days as specified in ASTM C 878 test method but were protected with a plastic film for just 24 hours (to simulate the protection offered by the formwork) an then exposed to unsaturated air (60% R.H.) at 20°C. This curing condition was later introduced as “curing method B” in the last version of the Italian standard UNI 8147 in addition to the “curing method A” previously specified, consisting in a total immersion in water for 7 days as in ASTM C878. Actually, the curing method B appears to be more realistic and similar to jobsite conditions. Even under these un-favourable conditions of curing, the CaO-SRA shrinkage-compensating concrete performed very well since the restrained expansion after 24 hours of protection with a plastic film was as high as 560 mm/m and, even after 140 days of exposure to unsaturated air, a residual restrained expansion of about 250 mm/m was recorded. On the contrary, the conventional CaO-based shrinkage compensating concrete showed a lower initial expansion (at lest 320 mm/m) which completely disappeared after a week of exposure to air after which, the concrete started to shrink. Obviously, the plain concrete showed the worst performance reaching a restrained shrinkage of about 550 mm/m after 60 days when some cracks appeared on the specimen surface. Comparing the behaviour of the CaO+SRA-based mix to that of the conventional shrinkage-compensating concrete, both the and effect of Figure 6 can be detected. On the basis of the above results, the customer and the contractor decided to adopt the SRA+CaO-based shrinkage-compensating SCC • Fig. 5- Strength development of three different SCCs. • Fig. 6- Length change with time of the three different SCCs. In order to demonstrate the effectiveness of this type of concrete in offset the formation of shrinkage cracks, its performances were compared to those of an ordinary CaO-based shrinkage-compensating concrete (without SRA) and of a plain SCC mixture without expansive component and SRA. Table 1 shows the composition of these three SCCs having the same w/c (0.48) and approximately the same cement dosage (350 kg/m3). Table 1 – Composition of three different SCC Mix Cement CEM II A/L 42.5R CaO+SRA (kg/m3)* CaO Plain 350 348 347 Limestone filler (kg/m3) 150 149 183 Gravel 4-16 mm (kg/m3) 847 884 871 Sand 0-4 mm (kg/m3) 908 916 903 Water (kg/m3) 167 167 166 Acrylic superplasticizer (kg/m3) 6.3 6.2 6.3 CaO-based Expansive Agent 35 35 \ 4.2 4.1 4.3 4.0 \ \ Viscosity modifier (kg/m3) SRA (*) Blended Portland-limestone cement according to EN 197/1 82 RESEARCH - Concrete for the manufacturing of all the architectural concrete walls of MAXXI. Since it was the first time the contractor used an SCC, it was decided to carry out several field tests, before starting with the manufacturing of the actual walls, in order to optimize all the casting procedures and test the suitability of formwork. It was, then, a good chance to test on a real scale the effectiveness of the expansive technique. Two field tests were successfully carried out in March and April of 2004 with no cracks formation in two long minor walls of the basement. A third test carried out in June in order to verify the behaviour of the expansive concrete in the presence of high temperature failed since after two weeks, some cracks appeared on the wall surface. The maximum temperature during the casting operation was as high as 35°C and checking the transport documents of the trucks mixer it was verified that, because of the congested traffic of Rome, the time elapsed between the starting of mixing, in the batching plant, and the casting of concrete into the forms had been in the range of 60-90 minutes, notwithstanding the batching plant were located near the jobsite. For this reason the cause of the failure was ascribed to a combined effect of the high temperature and of a too prolonged mixing time. This hypothesis was confirmed by laboratory tests in which some ASTM C878 prismatic specimens were manufactured at 20°C (with raw materials kept at 20°C for 24 hours before the use) whereas other similar specimens were manufactured at 30°C (with raw materials kept at 30°C for 24 hours before the use). In both cases, some specimens were put into the forms after 5 minutes of mixing whereas the others were kept in the mixer (in movement) for 60 minutes before casting at the same temperature of manufacturing (20 or 30°C). After setting time (about 6 hours) the specimens were demoulded and protected with a plastic film till 24 hours, at the same temperature of manufacturing (20 or 30°C). Successively, the specimens were exposed to unsaturated air (60% R.H.) at the temperature of manufacturing (20 or 30°C). Figure 7 shows the behavior, in terms of restrained expansion or shrink- • Fig. 7- Restrained expansion or shrinkage in different manufacturing and curing condition. RESEARCH - Concrete age, of the various specimens manufactured. As expected, the specimens manufactured and cured at 20°C performed well showing a residual restrained expansion in the range of 210÷280 mm/m after 28 days of exposure. The prolonged mixing (at the same temperature of 20°C) caused a decrease of the initial as well as in the residual expansion as reported in [2]. A little higher decrease was recorded in the expansion of the specimens manufactured and kept at 30°C and cast after 5 minutes of mixing. Anyway the behaviour of these specimens can be considered acceptable. On the contrary, the combination of a high temperature of manufacturing and curing and a prolonged mixing cause a strong reduction in the initial restrained expansion which was completely cancelled after just one week after which the concrete started to shrink. The problem was not eliminated by increasing the amount of expansive agent up to 45 kg/m3 so that, being impossible to assure a transportation time lower than 60 minutes, the contractor decided to delay the begin of the main wall construction to the autumn and to stop it during the whole next summer. 3. PROPERTIES OF RECYCLED CONCRETES The problem of recycling industrial wastes is of vital importance for a sustainable progress in order to avoid disposals in the environments and possibly to save resources for the next generations. Such a problem has already been faced in using fly ash, silica fume and blast furnace slag, all wastes coming from industries other than cement and concrete. During the last decade a similar problem has been found for wastes coming from the construction industry and from the concrete in particular [9] [10]. These wastes can be recycled as aggregates for concretes with two advantages: – first, to save the environment specially in countries, like Nederland and Belgium, where the available area to build is very limited; – second, to recycle this waste as aggregate specially in areas where natural or artificial aggregates are scarce. Therefore, concrete recycling, by using the readily available concrete as an aggregate source for new concrete or pavement subbase layers, is gaining importance because it protects natural resources and eliminates the need for disposals. Concrete recycling is a relatively simple process. It involves breaking, removing, and crushing the existing concrete into a material with a specified size and quality. The quality of concrete with recycled aggregate depends on the quality 83 of the recycled material used, the most important aspect being the origin of the recycled material such as concrete or demolition, the latter including waste from brick walls and other type of rubbles. The crushed and sieved material, must be deprived by contaminating products such as wood, paper, plastic, and bitumen. This recycled material can be used for pavement subbase layers. The process of recycling demolished concrete is based on four steps: – selection of wastes; – crushing concrete blocks; – removing of contaminating products; – mixing with virgin aggregates. Reinforcing steel and other embedded items, if any, must be removed, and care must be taken to prevent contamination by other materials, such as: asphalt, soil and clay balls, chlorides, glass, gypsum board, sealants, paper, plaster, wood, and roofing materials which can be troublesome. The mechanical plants where to recycle concrete structures are not very different from those adopted to treat crushed virgin aggregates. If the material is devoted to concrete production, further crushing and sieving are needed before mixing it with virgin aggregate [11]. The crushing characteristics of hardened concrete are similar to those of virgin rock and are not significantly affected by the quality of the original concrete. Recycled aggregates can be expected to pass the same tests required for conventional aggregates. The recycled concrete can be batched, mixed, transported, placed and compacted in the same way as conventional concrete. Special care is necessary when using recycled fine aggregate. Only up to 10% to 20% recycled fine aggregate is beneficial. The aggregate should be tested at several substitution rates to determine the optimal rate. 3.1 Properties of recycled fresh concretes The amount of mixing water of the coarse recycled aggregate is about 5% more with respect to that of virgin aggregate at given size. This value becomes as high as 15% when the recycled aggregate contains also the fine fraction. This effect is due to the rough texture of the aggregate and the cement paste surrounding the recycled aggregate. However, the use of superplasticizers and mineral additions can completely overcome this drawback [12]. 3.2 Properties of recycled hardened concretes Due to the higher porosity, related to the lower density, the recycled aggregates are responsible for the lower strength of the concrete with respect to the concrete manufactured with virgin aggregates. Due to the lower rigidity, recycled aggregates are responsible for the 84 lower modulus of elasticity of the concrete with respect to the concrete with virgin aggregates. For the same reason, drying shrinkage and creep of concretes with coarse recycled aggregates are much higher (25-50%) with respect to the virgin aggregates. The difference can be still higher if also fine recycled aggregate is used. The permeability of a concrete with recycled aggregate is higher than that of the corresponding concrete at a given water-cement ratio. Again, the cement paste of the recycled aggregate is responsible for this drawback because the cement paste is more porous and permeable of the virgin stone. The frost-resistance of the concrete with recycled aggregate is strongly reduced by the amount of fine fraction of the recycled aggregate. Therefore, in concrete exposed to freezing and thawing cycles the fraction of recycled aggregate smaller than 4 mm should be removed. The fine fraction of recycled concrete smaller than 4 mm is responsible for all the above mentioned limits of the concrete with respect to the corresponding concrete manufactured with virgin aggregates. However, if the fine fraction is ground very finely (smaller than 0.1mm) it can be used advantageously in manufacturing self-compacting concrete as filler to improve the cohesiveness of the concrete [13, 14]. 4. USE OF BOTTOM ASH FROM MUNICIPAL SOLID WASTES INCINERATORS Mineral solids in form of fly ash and bottom ash are produced by burning municipal solid wastes in incinerators (MSWI). Fly ash is negligible and it is so chloride-rich that it cannot be used as mineral addition in cement-based mixtures for reinforced concrete structures. On the other hand, bottom ash is about 25% with respect to MSWI and its chloride content is negligible, so that it could be potentially used as mineral addition for manufacturing concrete mixtures. However, ground bottom ash (GBA) from MSWI does not perform as well as other mineral additions (silica fume or fly ash produced by coal burning) due to the presence of aluminium metal particles which react with the lime formed by the hydration of Portland cement and produce significant volume of hydrogen in form of gas bubbles which strongly increase the porosity of concrete and reduce its strength. Due to this drawback, a new process was developed to completely separate the aluminium metal particles through a mechanical removal of metals and a special wet grinding of bottom ashes. At the end of the process GBA was used as an aqueous slurry to replace Portland cement. Some researches have actually shown the pozzolanic activity of ground MSWI bottom ashes showing their reactivity with lime or portland cement clinker [15,16]. Nevertheless, no successful use of MSWI botRESEARCH - Concrete tom ashes as mineral addition in concrete has been reported, because of the side effects of this addition. According to Bertolini et al [17], the main side effect is related to the evolution of hydrogen gas after mixing due to the presence of metallic aluminium. In the alkaline environment produced by the hydration of portland cement (pH around 13), corrosion of some metals (mainly aluminium) produces a great amount of gaseous hydrogen. After placing and compaction of concrete, this gas is entrapped in the fresh material, producing a network of bubbles that leads to significant reduction in the strength and increase in the permeability of the hardened concrete. The present report summarizes the results of a research [18] aimed at developing suitable treatments to allow the use of MSWI bottom ashes as mineral additions for the production of structural concrete without the evolution of hydrogen gas due to the presence of metallic aluminium particles. Ground bottom ashes (GBA) from municipal solid waste incinerators (MSWI) were manufactured according to a new technology based on a high degree of separation of metals including the heavy ones, the wet grinding process, and other specific technical solutions to completely remove the aluminium metallic particles. At the end of the process, a fluid slurry was obtained with particle size in the range of 1-5 mm. By changing the wet grinding time three GBA were produced with a mean particle size of 5 mm, 3 mm and 1.7 mm. Compressive strength and durability measurements were carried out in concretes where Portland cement was replaced by 20% of ground bot- RESEARCH - Concrete tom ashes from MSWI in comparison with concretes containing 20% of coal fly ash or 10% of silica fume. The performances of GBA with mean sizes of 3 and 5 mm were higher than that of the coal fly ash particularly at 1-60 days. The finest ground bottom ash (with a mean size of 1.7 mm) performs as well as silica fume in terms of compressive strength, water permeability, chloride diffusion and CO2 penetration. These results appear in particular to be very interesting from a practical point of view since it will be possible to manufacture big amounts of a pozzolanic material as effective as silica fume (which is not available and very expensive) in producing high-performance concrete in agreement with a sustainable progress for the re-use of waste materials instead of a their disappointing disposal. 5. CONCLUSIONS The research on the progress of structural concrete in Italy is very active. Three sections of this activity have been illustrated in the present report: – shrinkage-compensating concrete for crack-free structures even in the absence of a wet curing; – recycled concrete with special application of a fine powder material devoted to self-compacting concrete; – bottom ash from municipal waste incinerators as pozzolanic materials for high-performance concrete. 85 MET/ACI International Conference on Superplasticizer and Other REFERENCES Chemical Admixtures, Sorrento, 2006, pp. 103-115. [9] [1] [2] M. Collepardi, The New Concrete, pp. 347-362, Second Edition, Environmental Conscious Materials and Systems for Sustainable Ed. Tintoretto, Villorba, Italy, 2010. Development, 2004, pp. 179-186. N.S. Berke, L. Li, M.C. Hicks and Bal, “Improving concrete per- MET/ACI International Conference on Superplasticizer and Other overview”, Materials and Structures, 39, pp. 655-664, 2006. [7] M. Collepardi, A. Borsoi, S. Collepardi, J.J. Ogoumah Olagot, R. gress, Naples, ID 6-19, 2006. 86 [12] V. Corinaldesi, G. Moriconi, “Role of Chemical and Mineral Compensating Concrete Under Non-Wet Curing Conditions”, Admixtures on Performance and Economics of Recycled- Cement and Concrete Composities, 6, 2005, pp. 704-708. Aggregate Concrete”, Proceedings of the Seventh CANMET/ACI C. Maltese, C. Pistolesi, A. Lolli, A. Bravo, T. Cerulli and D. International Conference On Fly Ash, Silica Fume, Slag and Salvioni, “Combined Effect of Expansive and Shrinkage Natural Pozzolans in Concrete, Editor V.M. Malhotra, ACI SP Reducing Admixtures to Obtain Stable and Durable Mortars”, 199, Vol. 2, pp. 869-884, 2004. [13] V. Corinaldesi, G. Orlandi, G. Moriconi, “Self-compacting con- C. Maltese, A. Lolli, C. Pistolesi, A. Bravo, and T. Cerulli, crete incorporating recycled aggregate”, Innovations and De- “Combined effect of expansive and shrinkage reducing admixture velopments in Concrete materials and Construction, Proceeding on microstructure of mortars and concretes”, Proceeding of the of the International Conference, Editor Ravindra Dhir, Dundee, International Conference on Durability of Concrete, Editor: V.M. UK, pp.9-11, 2002. [14] V. Corinaldesi, F. Tittarelli, L. Coppola G. Moriconi, “Feasibility S. Chatterji, “Mechanism of expansion of concrete due to the pres- and Performance of Recycled-Aggregate Concrete Containing ence of dead burnt CaO and MgO”, Cement and Concrete Fly Ash for Sustainable Building Development”, Proc. of the Research 25, 1995, pp. 51-56. Three-Day CANMET/ACI Int. Symposium On Sustainable F. Tittarelli, S. Monosi, G. Moriconi, R. Troli, “Effects of a shrink- Development of Cement and Concrete, SP 202-11, pp. 161-180, age compensating Admixture in Shrinkage-Compensating 2001. Concretes”, presented in “9th ACI International Conference on [8] M. Bassan, M. Menegotto, G. Moriconi, “Precast Structural Concrete with Recycled Aggregates”, Proceedings, the 2nd fib Con- Malhotra, Montreal, 2006, pp. 781-796). [6] [11] Malhotra, 2003, pp. 37-50. Cement and Concrete Research 12, 2005, pp. 2244-2251. [5] J.Zh. Xiao, J.B.Li, Ch. Zhang, “On relationship between the mechanical properties of recycled aggregate concrete: An Troli, “Effects of Shrinkage-Reducing Admixture in Shrinkage [4] [10] formance with Shrinkage-Reducing Admixtures”, 7th CAN- Chemical Admixtures in Concrete, Berlin, Germany, Ed. V.M. [3] N. Kashino and Y. Ohama, RILEM International Symposium [15] K.A. Paine, R. K. Dhir, V.P.A. Doran, “Unprocessed and Superplasticizer and Other Chemical Admixtures”, Seville, 2009. processed incinerator bottom ash as a cement bound material” in M. Collepardi, R. Troli, M. Bressan, F. Liberatore, G. Sforza, R.K.Dhir, T.D.Dyer, K.A. Paine (Eds.) “Use of incinerator ash”, “Crack-Free Concrete for Outside Industrial Floors in the Absence Proceedings of the International Symposium organized by the of Wet Curing and Contraction Joints”, Suppl. of 8th CAN- Concrete Technology Unit, University of Dundee (UK) 20RESEARCH - Concrete [16] 21/3/2000. lepardi, “MSWI ashes as mineral additions in concrete”, Cement A. Macias, E. Fernandez, S. Goñi, A. Guerrero, “Valorizacion de and Concrete Research, 34, 1899-1906, 2004. las cenizas de inceneracion de residuos solidos urbanos en los [17] [18] M. Collepardi, S. Collepardi, D. Ongaro, A. Quadrio Curzio, M. materiales de construccion”, Papel de los sectores cementero y Sammartino, “Concrete with bottom ash from municipal solid de la construcciòn en la gestiòn y reciclado de residuos, CSIC, wastes incinerators”, paper accepted for publication on “Second Madrid, 2001. International Conference on Sustainable Construction Materials L. Bertolini, M. Carsana, D. Cassago, A. Quadrio Curzio, M. Col- and Technologies (SCMT)”, Ancona, Italy, June 2010. RESEARCH - Concrete 87 Damages of L’Aquila Earthquake 1. INTRODUCTION his chapter summarizes the main findings of a chapter of the special issue of Progettazione Sismica devoted to L’Aquila earthquake the author edited and which is about to appear. In particular, in the following the papers of Carocci and Lagomarsino (2010) regarding masonry buildings, Cosenza et al. (2010) for reinforced concrete buildings, Di Ludovico et al. (2010) about school buildings, Casarotti et al. (2010) for hospitals, Menegotto (2010), Faggiano et al. (2010) for industrial structures, Dolce et al. (2010) for lifelines, are reported. T 2. MASONRY BUILDINGS Are masonry buildings able to withstand a strong earthquake such as the one that struck L’Aquila on the 6th of April, 2009? Is it possible to repair damaged buildings, guaranteeing an adequate safety level to their inhabitants in an area with such a high level of seismic risk? These are the questions asked by researchers and government technicians, but especially by those people who lived through this tragic event and long to see the restoration of historic centers and return to their homes but are also afraid. The answer to these questions must be complex and detailed because there were so many factors that influenced the seismic behavior of Aquilan constructions. In this earthquake, more than others, the effects of localized seismic amplification played an important role. If one analyzes the macro-seismic consequences of many of the historic centers in the Aterno Valley (south-east of Aquila), one will immediately observe that the villages that were struck the hardest (Onna and Villa Sant’Angelo, I=9-10) were near other villages where the damage was limited: Onna (I=9-10) which is only 1500m as the crow flies from Monticchio (I=6). Near the town of Villa Sant’Angelo, the distance between the chief town (I=9) and the village of Tussillo (I=8) is less than 700 m. Even within the town of L’Aquila, there were zones where the damage was clearly concentrated. Especially in L’Aquila, it was noted that most victims were found in reinforced concrete (r.c.) buildings (135 versus 52 in masonry buildings). In the historic center, damage to churches was severe, in some cases with extended collapse, but the increased vulnerability of these structures is well-documented by history (in the past, churches were often found to have the highest concentration of victims). Some severe damage was rather diffuse in apartment buildings, but did not lead to collapse except for localized cases in loggias or stairwells; almost always found in abandoned or poorly maintained buildings. Modern criteria for structural safety, based on tests of differing limit states (performance-based design), state that during a rare earthquake the 88 construction may undergo severe damage but must avoid collapse in order to protect the lives of its occupants. The earthquake on April 6 of last year was of an intensity comparable to that found in the new Technical Regulations of Construction, and many buildings in L’Aquila historic center sustained damage compatible to those norms (the accelerograms recorded by instruments present in the area of the “seismic crater” revealed a spectrum only slightly higher than that in the building plans). Therefore, one can attest that well-constructed masonry buildings, in other words those built with connections that allow the structure to act as a unified organism (clamping between orthogonal walls, junctures between walls and floors) are able to sustain damage without manifesting fragility collapse. This article will not deal with monumental structures, but with minor masonry ones, common in the many historic centers in and around L’Aquila, where severe damage and collapse was diffuse. Wishing to take into consideration the number of victims as a parameter of vulnerability, outside of L’Aquila there were 97 victims in masonry buildings, compared to 14 victims in r.c. buildings (it should be said that in these towns the percentage of r.c. buildings is much lower than in L’Aquila and the buildings were also lower). What are the factors that justify the different behavior between the apartment buildings in L’Aquila and the buildings in the surrounding historic centers? Effectively, there are two reasons: construction quality and the presence of incongruous subsequent restoration. In the masonry buildings of the historic center of L’Aquila, most of which were rebuilt after the tragic earthquake in 1703, a series of structural modifications characteristic of the L’Aquila rules of thumb were easily recognizable: wooden beams (elements built into the wall thickness and connected externally by way of small tie rods), to improve connections between walls; the connection of roofs to the tops of the walls, utilizing external wooden posts. These rules were adopted even in the smaller surrounding historic villages, but often with lesser construction know-how and lower quality building materials. Even after the earthquake in 1703, the historic centers of the Aterno Valley were struck by significant earthquakes, in particular, the one in Avezzano in 1915. In fact, the repairs and seismic reinforcements are easy to discern (scarp walls, buttresses, and tie rods adjacent to masonry walls) and in many cases, the partial reconstruction of collapsed portions. These interventions often functioned well, but in others the vulnerability remained, proving once again how difficult it is to perform truly efficient seismic restorations and improvements. As far as recent restorations were concerned, (only in certain cases done for consolidation purposes) it should be said that while L’Aquila appears to be better preserved (due to both the large number of protecRESEARCH - L’Aquila Earthquake Gaetano Manfredi Department of Structural Engineering, Università degli Studi “Federico II”, Naples, Italy ted buildings as well as perhaps the number of uninhabited buildings in certain areas), the smaller historic centers were subject to frequent changes: enlargements, transformations, added floors, restored floors and roofs. These interventions were often done with building materials and techniques incompatible with the original structures: alterations in weight displacement, differing rigidity between elements, and dangerous increases in mass. The final important question is if it is possible to repair severely damaged constructions and rebuild collapsed parts of aggregates with traditional construction techniques (i.e. stone), eventually modified on the basis of the experience of this earthquake. To this end, an examination of construction damage to masonry is proposed based not only on the identification of vulnerable areas, but also on resistance (anti-seismic regulations) as a means of truly learning something from the test of an earthquake. 2.1 Typological aspects of masonry buildings in the historic centers of L’Aquila The historic centers of the L’Aquila territory are principally made up of simply organized masonry buildings. Even the grouping within connected buildings seems to be to simply follow the rules imposed by the orography of the terrain. Due to the areas extended (including seismic) history, construction peculiarities and specific characteristics for the arrangement of aggregates for each of these centers have been adopted, and deserve to be taken into consideration, but will not be dealt with in this article. Nevertheless, with reference to aggregates, one can affirm that the urban centers are characterized by smaller dimensioned blocks of buildings that develop along the morphology of the terrain where they were built. In the centers located on mountainsides (for example: Fossa, Casentino, Tussillo, Castelnuovo) or those built on plateaus (for example: Poggio Picenze, Sant’Eusanio Forconese, Villa Sant’Angelo), both cases are characterized by sloping terrain. One can observe the two types of typical aggregates: parallel blocks and blocks built orthogonally to the incline as well as a wide range of variants in between. Buildings were arranged according to the conformation of the terrain and the existing buildings, and the relation to seismic vulnerability can be listed schematically: height differences between walls on opposite sides of the street; scaling of contiguous building fronts; number and height of external exposed walls, and the placement of the building in the aggregate. In the oldest centers where the building aggregates developed along side streets, the aggregates are characterized by the continuity of the RESEARCH - L’Aquila Earthquake street front and the contextual absence of building compactness in the depth of the fabricated bodies (for example: San Demetrio Colle). Such generalized characteristics are largely identifiable in centers analyzed herein, even if in our conscience it is not possible to establish a correlation between the type of building aggregate and the damage sustained. In any case, the observations relative to the scale of the aggregate are important not only for identifying where the main vulnerability lies and differentiating it from that of single buildings, but especially for establishing the project phases for restoration and reconstruction. The diffusion of arches placed between facing walls along the streets is a repeated tendency in these villages subject to earthquakes. However, it is not possible to prove that the volume of overpasses (built onto the inhabitable surface area) though widely present in many of these centers (for example: Santo Stefano di Sessanio), is the result of the evolution of the arches, even if it is obvious that both tend to create a rather good connection between the facing blocks and constrict wall movement where they are located. Street names such as Contrada dell’Arco, Chiassetto dell’Arco, Via sotto gli Archi, present in nearly all of the centers we visited, indicate that this construction technique dates way back. Buttresses, built-on scarp walls and tie rods should be counted among the pre-modern anti-seismic defenses that systematically characterize the building range of these centers. Each technique can be identified by materials analysis, production, function and use after the many earthquakes that have struck this area throughout history. In fact, many of these elements have been utilized in restoration phases while in other cases, they seem to have become the rule of thumb for the partial or total reconstruction of buildings. Evidence of the damage done by historic earthquakes is still often visible, such as the often seen out of axis external walls of buildings, and the presence of stone elements, often hewn after being taken from older collapsed buildings and reutilized in post quake reconstruction.. Given the close relationship that links these centers to the territory (agricultural/pastoral economy), the inhabited buildings still show traces of their rural past with ground floors usually for storage or stalls and the living spaces in the upper floors accessed by means of external staircases along a balcony. The structure of these stone stairs is usually surrounded by pillared masonry that tends to create volume towards the street front; in cases where the building has another floor, the additional volume is used as a loggia while access between the two inhabited upper levels is solved by way of an internal wooden stair. In some of the centers visited, the houses showed more “urban” characteristics in how they were set up on the street front while at times 89 maintaining the external stone stairway to access the inhabited upper floor. In any case, a common peculiarity seemed to be the add-on of advancing volume on the front of the house for more living space. Along with the mono-celled buildings on the street front, which we have referred to up till this point, larger and more complex structures exist without being large enough to be considered real apartment buildings (with the exception of sporadic cases in the smallest villages). These were derived mostly from the fusion of pre-existing smaller buildings with the addition of an upper floor. The “stall-hayloft” is another very common type of building which completes the overview of the minor architecture in these centers. Its function determines its appearance, and though it is completely distinct from the living area, it is often placed contiguously to the house and therefore inserted into the building mesh. The most important difference from a construction and structural point of view is that these constructions represent the largest part of the wall structure (where some walls reach up to 10 m in length) with the presence of dilated wall light which corresponds to the systematic use of roof coverings connected to external walls. From our observations, it was possible to conclude that up until now, the wall thickness of the cell walls were adequate for the dimensions of the buildings (3 levels above ground and usual light openings); in fact these prove to be between 50 and 70 cm except at ground level or in rare cases where stone vaults are present where up to 1 m of thickness can be found. Congruous tapering was also observed in upper floors; scant wall thickness was observed only on rare occasions, always in the presence of more recent interventions. As far as horizontal diaphragms are concerned on the first floor (the division of lower floors used for storage or stalls and inhabited upper floors), there were always barrel vaults with the generatrix perpendicular to the façade. The construction technique calls for a mesh of rough hewn stone elements and the presence of compact buttresses. The upper floors usually have simple wooden flooring. However, brick covered metal beams were frequently noted, certainly from substitutions in the last century (for example after the Avezzano earthquake). Metallic beams, hollow flat blocks covered by flooring were more recent. In some cases, the beams were connected to bars or welded plates and anchored to the masonry. Another type of horizontal diaphragm is made of thinly layered brick vaults (two thin layers of interwoven bricks) which have proven to be very vulnerable; these vaults are also relatively recent (from the end of the 19th century to the first decades of the 20th century). The roof coverings are made of wood with the constant presence of overhangs made of dripstone or wooden elements. In buildings in aggregates, the ridge of the roof is parallel to the street front and may have 90 one pitch towards the street or two slopes with a central ridge (depending on the configuration of the whole aggregate). The wooden beams are always positioned without overhang; even in the case of buildings placed on corners or at the head of a block where the configuration of the pitch is a triangular pavilion shape (therefore with the presence of two directions of slope). The attention paid to not creating overhanging structures and nevertheless the wooden elements were almost always connected to the walls. The attention to the way rooms were constructed for reducing seismic vulnerability is also observed in many small details, such as the “light” eaves made from wooden and bamboo structures and the balconies entirely made of wood. Such construction measures were evidently realized in order to limit the lethal effects of damage on the lives of the inhabitants. To conclude this chapter which focuses on the characteristics of the buildings in minor centers of the L’Aquila area, it is necessary to mention two aspects that should be considered in the observation and evaluation of damage: the techniques adopted in recent restorations and the conservation state of the buildings. In relation to the first of the two aspects mentioned above, it should be observed that as long as masonry walls were the dominant technique used for building, transformations on existing buildings took into consideration this vulnerability and often brought about seismic improvements within the limits of the techniques available, eliminating weaknesses and introducing protective measures. Unfortunately, recent transformations appear mostly linked to damage after the earthquake. The most common intervention is the substitution of the original roof covering with a new one which generally followed the same configuration of the preceding one, but was at times made from an r.c. structure with hollow or infill panels or with metal beams instead of wooden ones. The result of these changes with regards to seismic vulnerability was quite often negative. As far as the second aspect is concerned, it seems clear that the conservation state of the building played an important role in whether or not it was damaged, but also with reference to the buildings near it in the aggregate. In fact, in cases where the adjacent buildings were poorly constructed due to many decades of abandon, there was less damage than expected due to the stabilizing contribution of the contiguous cells. In some of the centers visited, the presence of many restoration work zones was observed (for example at Villa Sant’Angelo). As far as we could discern, in most cases the techniques these workers were utilizing were far from those that should have been adopted for the knowledgeable recovery of historic heritage. On a positive note, also in view of the reflections in the next chapter, we also encountered that the restoration and reuse of abandoned masonry structures had been going on for some time, and was probably linked to a search for available RESEARCH - L’Aquila Earthquake living space close to the city center but also due to a slightly higher tourism interest (also foreign). 2.2 Damage observations: vulnerability and resistance The description of the damage observed will be discussed by topic according to the most important building aspects (at times re-examining the topics mentioned above) and by referring to the principal damage and collapse mechanisms. Subdivision is necessary in order to shed light on the probable causes that facilitated or more aptly limited damage. In this way, characteristics of vulnerability will be highlighted as well as the strengths which should lead to further reflection for future reconstruction. 2.2.1 Structural organization of buildings and position in the aggregate As far as the placement of the building in the aggregate is concerned, it has been revealed that the configuration of the corner or the head of the block has proven to be the most disadvantageous as widely noted before. In Figure 1, we can observe three buildings each placed at the head of a block. All of them sustained the collapse of the front wall and a great portion of the two side walls. Good organization and regularity of the vertical load elements of the building represents a point of strength with regards to seismic action. The orientation of orthogonal walls to the façade, the placement and quantity of openings and the connection with the horizontal elements determines the greater or lesser flexional trim (vertical and horizontal) of the walls. Irregularity or changes introduced in the configuration of the whole often proves fatal during an earthquake. One often noted case is that of the buildings created by the fusion of pre-existing contiguous buildings and the later addition of one or more Fig. 1- Tempera: collapse of buildings placed at the head of a linear aggregate. RESEARCH - L’Aquila Earthquake floors. At times, the new building eliminated certain walls orthogonal to the façade yet present in the lower floors when raising the height, thus altering the passage through transverse walls (and generally rotating the orientation of the floors). Figure 2 shows the case of a building where one of the walls orthogonal to the façade was absent on the top floor, yet traces can be observed on lower floors. The excessive distance between the transversal walls rendered overturning nearly inevitable in the case of seism. Such construction defects, observed on many occasions, can have easily been revealed in the buildings in the historic centers and the vulnerability derived from such configurations found and resolved preventatively. Fig. 2- L’Aquila: the absence of transverse walls on the upper floor of the building. The vulnerability derived from the absence of clamping between walls of buildings built at different times was confirmed (growth phases and evolution of the buildings in an aggregate). Figure 3 shows the collapse of the portion of a wall due to construction discontinuity by the simple placement of a wall next to the pre-existing corner. Fig. 3- Poggio Picenze: local collapse due to discontinuity. 91 Beyond typical growth or urban congestion, many violations of building codes were found in the transformations of aggregates in historic centers. In other words, demolition and reconstruction of weight-bearing walls in different positions in order to obtain small extensions or reconfigurations of the block produced negative alterations of cells. In these cases, the original clamping was lost and nearly impossible to restore on the newly placed walls, and thereby eliminated connecting elements. In the case shown in Figure 4, a cut off wooden tie rod is visible right inside the internal wall, probably during restoration of the building or its apartments. This alteration, which eliminated an anti-seismic construction norm put in place by previous craftsmen certainly contributed to the collapse that was verified in that building unit. the house, and consequently, the use of spaced trusses are necessary (Figure 5-6). From a construction point of view, it is clear that the connections between roof and walls were put into place at the time of original construction as demonstrated by the position of lintels which necessarily implies their placement before mounting the boards and the subsequent roof covering. Finally, it should be noted that the use of connecting trusses to the masonry walls by means of wooden lintels was also consistently found in churches in the L’Aquila region, and therefore one can assume that this technique was generally associated with construction configurations with great light. Connections by means of wooden lintels were also observed in larger and more important buildings like that in Figure 7 which gives an example of the positive contribution offered by the roof covering. The corner building shows systematic tie rods between floors and the top of Fig. 4- Villa Sant’Angelo: violations: the external wooden connection to the metallic tie rod was cut during fusion when the wall direction was altered. 2.2.2 Roof Coverings As already mentioned, wooden roof structures generally do not overhang, demonstrate well-placed orientation, and are usually wellconnected to the masonry walls evidenced by metallic or wooden connections visible from the external walls. Such connections are associated to the very common presence of pavilion type roof coverings or the triangular portion of the pavilion roof, where the presence of ridge rafters or slope necessitates the organization of the mesh of the wood to eliminate thrust. In roofs whose main direction is limited by masonry walls they are posed upon, it was not rare to find that an effective connection to the wall rims contributed to limiting the damage and protrusion of the external walls. The habit of connecting, often by way of wooden lintels, roofs to masonry walls seems to be linked to the dilated dimensions of the cells; in fact this modality is constantly found in uninhabited spaces such as stalls-haylofts. In the latter, the floor area is usually larger than that of 92 Fig. 5- Villa Sant’Angelo: a wooden truss leans on a wooden lintel. Fig. 6- Casentino: masonry cyma of a hayloft and the truss touching the wooden lintel (note how the internal connection is thanks to a board nailed to the actual lintel). RESEARCH - L’Aquila Earthquake the wall put into place when the masonry walls were elevated. One can also observe the presence of wooden tie rods which are connected to the trusses which create the pavilion roof structure (the presence of a tie rod may indicate the absence of an orthogonal wall to the façade). In any case, it is interesting to note how the building has cracked in the floor with walls (second mode mechanism) while initial cracking is entirely absent on external walls. Fig. 9. Villa Sant’Angelo: diffused collapse of the masonry cyma without involving the window openings. Fig. 7- Poggio Picenze: a small corner building of a block built on a slope. Below, the Figures demonstrate how damage can be attributed to a lack or modification of the roof structure. Damage caused by the poor quality or advanced state of decay of the wooden elements of the roof was very common. This was due to the lack of connection to the masonry (along with the scarce conditions of placement), the lack of connection between main and secondary elements of the roof covering, or the bad conditions of the wooden boards (which if in good condition guarantee a very limited bracing effect). In these cases, local collapse was recorded in the tympanum of the cell walls (Figure 8), in other words extended collapse to the fascia above Fig. 8- Poggio Picenze: local collapse of tympanum walls due to holes punched in the rafters. RESEARCH - L’Aquila Earthquake the external walls without involving the architrave structure of the openings on the highest floor (Figure 9). In both cases, damage may have been caused by movement relative to the placement of wooden elements and the effect of the addition of wall openings which weakened wall strength. Localized damage in the tympanum walls (which is one of the most commonly found types of limited damage observed in the L’Aquila centers) may be more or less extended depending on the surrounding conditions, where the tympanum wall was placed in the aggregate (differing height to the contiguous buildings), or in relation to the quality of the masonry pattern at the top of the wall. Extensive damage involving the top of the external walls may be attributed to where the wooden mesh elements (primary and secondary) were not interconnected which led to greater displacement at the top part of the wall during the quake. Localized collapse to a portion of the masonry cyma illustrated in Figure 10 is presumably due to thrust in the rafters of the slope of the pavilion roof. Localized cracks are also visible near the corners, perhaps caused by horizontal displacement transferred to the walls by the angular rafters of the pitch. One can also observe the collapse of the obstruction of an arched opening. It was dramatic how many cases of damage were unmistakably caused by the substitution of traditional wooden rafters with structures which although appeared to imitate the original had vast differences in weight and rigidity. Both in the cases of heavy stringcourses as in those where the weight is due to infill roof panels, the effect produced by the seism was fatal. The external walls below were seriously damaged and the roof cove93 ring structure remained on top of what remained of the building (Figure 11-12). Fig. 10- Vallecupa: localized collapse of a portion of the masonry cyma. 2.2.3 Horizontal diaphragms and vaults In the case of floors, it was generally observed that modifications played a negative role in seismic behavior; recent substitution interventions of original horizontal structures were quite diffused, in particular in the largest centers, and they seem to have led to the type of damage discussed below. The use of floors with metallic beams and brick (small brick arches or thin hollow flat blocks) was common for nearly all of the last century and may improve the overall behavior in some cases when well-made. However, such interventions require localized clamping to the masonry (of less impact than that necessary for the insertion of r.c. stringcourses) and in a certain increase in the vertical load on the masonry. These loads inevitably influence one of the masonry parameters favoring damage to the transverse connections in the wall and phenomena of localized instability. In Figure 13, observe how the portion of the wall collapsed from the ground floor up to the height of the lintel of the window on the top floor. The collapsed portion was limited to the vertical alignment of two columns of puncturing and the nesting seems to have been favored by the presence of an r.c. floor positioned over the original thin brick vault and by the presence of the addition of a staircase leading to the attic. Fig. 11- Tempera: the heavy substituted roof caused the crumbling of the walls of the floor beneath it. Fig. 13- L’Aquila: a second floor and a staircase in r.c. were placed on top of the original one. Fig. 12- Villa Sant’Angelo: the r.c. roof with infill panels induced the collapse of the masonry walls beneath it. 94 An analogous effect seems to have resulted from the presence of an r.c. floor posed in order to consolidate and increase the rigidity of the original floor in metallic beams with thin layered brick vaults (Figure 14). In this case, the wall collapsed from the base to the summit with the exclusion of the r.c. stringcourse and the roof structure which remained in position. The head of the building had a rounded corner and the collapse of the RESEARCH - L’Aquila Earthquake mon horizontal structure for most of the buildings. It is interesting to observe that in the range of current seismic damage, the vaults reacted well. In fact, even in the cases involved in extensive collapse, the vaults of the ground floors appeared intact (Figure 16). This is certainly due to the correct dimensions of the masonry piers as well as the good placement of the vault within the complete configuration of the building and the whole aggregate. Fig. 14- Paganica: a thick cement layer for rigidity was posed on the horizontal diaphragm. walls may have been determined by the rigidity of the floor panels which formed a diagonal point which tended to expel at the corner. The case documented in Figure 15, merits some attention due to the fact of its common reccurrence within the complete range of damage. The deformation localized in correspondence to the size of the horizontal diaphragms, absent at the top of the external wall, may indicate excessive floor weight and/or the lack of any connection between the horizontal diaphragms such as a barrel vault or flooring built on beams parallel to the façade. Fig. 16- L’Aquila: the vaults remained intact notwithstanding the collapse of the facade and the upper horizontal diaphragm. Both in the role of horizontal diaphragms as well as in false ceilings for inhabited attic spaces, the brick vaults were not always spared from damage (Figure 17). This fact is easily proven both in smaller constructions as well as in important and monumental buildings (the damage is visible to these types of structures in the upper floors of many buildings in the historic center of L’Aquila). To the contrary of stone vaults, the reduced thickness of the brick vaults rendered them more sensitive to even the smallest movements of the imposing walls. Obviously, for an accurate evaluation of vulnerability of this type, the many cases where Fig. 15- Poggio Picenze: evident deformation of the masonry walls of the facade with the worst damage at the level of the horizontal diaphragm. As previously mentioned, the use of vaulted structures for horizontal diaphragms is rather common in luxury buildings as well in minor ones in the Aquilan centers. In the latter, the vaults are generally in stone with thickness varying between 20 and 30 cm, while in the city of L’Aquila, there were predominantly brick head vaults (12 cm). Barrel vaults create the most comRESEARCH - L’Aquila Earthquake Fig. 17- Paganica: collapse of two thinly laid brick vaults (horizontal diaphragm on the first floor and a false ceiling on the second floor). 95 these vaults collapsed due to the fall of the roof covering structures or single elements placed above them should be excluded. 2.2.4 Out of plane and in plane response in masonry walls The topic of masonry quality in the Aquilan territory is the center of much debate, and not only technical, due to its relevance for interpreting damage but also and most importantly in the choices that must be made for reconstruction. It is the author’s opinion that judgment on the quality of masonry cannot be expressed in a univocal manner as of yet. However, one can certainly attest that most of the building patrimony was built based on earthquake knowledge, in particular for the systematic use of clamping and tie rods between walls (besides the previously mentioned use in the connections of non-thrusting roof coverings). The organization of construction systems and the realization of masonry techniques in many cases calls for the presence of tie rods put in place while the wall is raised. The construction of such tie rods is easily visible today by the mass of partial collapse dating back to the reconstruction after the earthquake in 1703, when the technique now used for over two centuries was first put into use. The clamping consists in the placement of a wooden element built inside the wall and connected at the extremities by an iron plate and nails (Figure 18) and then anchored externally to the corner by way of a small tie rod (Figure 19). It is very efficient as long as the wooden element is not placed under too much tension causing weakness nears the nails. Obviously, the necessity of balancing costs and the availability of materials called for the elaboration of variations which were not always efficient (Figure 20). More often than not, the progressive deterioration of these elements was in correspondence to connections between the wood and the iron plate, especially in abandoned or poorly maintained buildings. Generally speaking, the limited presence of out of plane displacement Fig. 18- San Demetrio: metallic tie rod with a nail connecting the rod to the wooden beam. 96 Fig. 19- L’Aquila: an elegant 17th century tie rod connects to a wooden beam placed within the masonry thickness (note the adjacent strengthening tie rod, inserted after construction on the internal side of the wall). Fig. 20- Villa Sant’Angelo: a poor example of wooden beams placed in the middle of the wall thickness without external clamping. within the vast array of damage found can be attributed to the systematic use of tie rods in building walls. Nevertheless, it was possible to encounter certain types of out of plane displacement after this earthquake. Figures 21 and 22 show cracks which caused detachment from the façade. Both were caused by poor clamping at the corners and involved of a portion of the orthogonal walls. In both cases, the portion of the isolated façade was limited to the height of the horizontal diaphragm. Figure 23 illustrates a case of the start of overturning of a wall portion relative to the two floors laid over the ground floor; here the out of plane displacement seems to have been caused by a lack of clamping with the masonry adjacent to the contiguous building and a lack of efficient connections at the level of the second floor. Also damage ascribed to localized displacement of portions of the masonry cyma were common, both in the form of fractures (Figure 24) RESEARCH - L’Aquila Earthquake Fig. 21- Castelnuovo: detachment of a wall caused by defective clamping to the lateral wall. Fig. 24- San Demetrio: localized fractures above the lintel of an opening. Fig. 22- Paganica: overturning which involved a portion of the orthogonal wall. Fig. 25- Paganica: collapse of a portion of a wall over the lintel. Fig. 23- Tempera: overturning of the top portion of an external wall. as well as the collapse of limited portions due to cracking near openings (Figure 25). In plane damage to walls is present in all of its characteristic variants. In fact the form and placement of the shearing varied according to the efficiency of the connections between the elements it was built with and the quality of the masonry pattern. Figures 26 and 27 illustrate two cases; in the first, the inclining fractures cross the external wall, traveling indifferently to the horizontal diaphragms; while in the second, the fracturing is concentrated in the masonry piers between the openings of the first floor. These situations are found wherever there was a systematic presence of clamping or for more recent buildings the presence of stringcourses. Regarding the validity of anti-seismic regulations, which had been adopted in most of these buildings, one can only say that in cases where the workmen had the technical capacity to follow the rules of good con- RESEARCH - L’Aquila Earthquake 97 the necessary clamping to the pre-existing masonry; a defect which in fact greatly limited its seismic resistance. As previously mentioned, the traditional connecting systems between converging masonry walls are the most effective: both those put into place at the time of construction (clamping at the corners, anchored wooden beams) as well as later strengthening interventions or reparations (tie rods placed in walls). The limited presence of collapse due to overturning of the façade (compared to damage caused by major in plane wall displacement) leads one to believe that these systematic connecting measures played an essential role in conservation (Figure 29). In this sense, the diffuse presence of shear fractures in masonry walls should not be interpreted as a demonstration of poor masonry quality, Fig. 26- Villa Sant’Angelo: shearing which crosses the entire external wall. Fig. 27- Sant’Eusanio Forconese: shear cracks limited to the masonry piers. Fig. 28- Castelnuovo: masonry buttress built without clamping to the pre-existing wall. struction and utilized these norms, such measures functioned to limit or modify damage mechanisms within the limits of their efficacy. Instead, Figure 28 shows the frequent case of a buttress added to a wall without 98 Fig. 29- L’Aquila: a building where an overturning mechanism initiated but was effectively contrasted by the connections at the summit thereby causing in plane resistance behavior of the walls. but as a positive consequence of the anti-seismic measures which produced a box-like behavior, impeding out of plane mechanisms. In a well-built stone wall, the formation of even deep shearing following such a violent earthquake is inevitable and allows the activation of significant dissipative capacities, limiting the risk of collapse. Over all, much of the damage observed can certainly be attributed to insufficient quality of the masonry pattern, whether in ruinous collapse or the loss of only the external façade. In general, the root of the problem is a lack of building quality: bad equipment for the façade, poor quality cement (and its excessive proportion to stone elements), absence of transverse connections between walls. Such cases are commonly caused minor damage to adjacent buildings. Figure 30 illustrates the case of a building where the entire upper floor collapsed. One can observe how the seismic activity disarranged the walls to such a point that it crumbled to the ground in rubble notwithstanding the light roof covering (and therefore not able to induce the shearing particularly prevalent in upper floors). On the contrary, it RESEARCH - L’Aquila Earthquake 2.2.5 Localized damage Always on the subject of masonry walls, localized damage was found to structural and nonstructural elements, justifiable in a situation where the force of the seism is extremely violent. In fact, even in cases where Fig. 30- Castelnuovo: total collapse of the top floor due to defective masonry quality. should be noted that the external wall of the building to the left was left whole. In Figure 31, the very common case of the collapse of only the external wall is shown. In these cases, the modality of damage declared its cause: the lack of transverse compactness of the masonry panels. Small or badly placed stone elements, lack of regularity in the pattern and clamping between the facing sections rendered the walls vulnerable to horizontal displacement and set off autonomous behavior in both walls that then very often led to collapse of this kind. The collapse of a single wall occurred more frequently where r.c. string- Fig. 32- Casentino: detachment of hewn stone elements around an opening. Fig. 33- L’Aquila: localized collapse around the borders of the openings. Fig. 31- Villa Sant’Angelo: collapse caused by the lack of transverse clamping in the masonry mesh. courses were found at the top of a building, in particular when the entire roof covering was heavy and rigid. The detachment of the wall at the level of the stringcourse is linked to the local increase of compression which originates in out of plane flexion from the condition and blocking vertical displacement (caused by the flexional rigidity of the roof covering). RESEARCH - L’Aquila Earthquake Fig. 34- Vallecupa: a chimney exposed by the seism. 99 Fig. 35- San Pio alle Camere: localized collapse of the top portion due to scarce thickness. the masonry buildings behaved well, it was natural that there was some small specific vulnerability. A frequent case observed was the constructive vulnerability of hewn stone above doorways and windows. The hewn stone elements used to border openings were rarely clamped to the masonry walls within the wall thickness which inevitably led to their detachment (Figures 32 and 33). This glaring omission to the attention given to seismic vulnerability in local anti-seismic construction deserves to be examined more closely. The problem was probably overlooked considering that such elements do not determine the stability of the building as a whole. Further damage was found in consequence to local irregularities of various types, such as continuity solutions which weaken masonry walls locally, or the presence of wide parameter walls with no structural function for the building. In the case shown in Figure 34, one can observe the collapse of the closure of a chimney along the external wall. Figure 35 shows the collapse of a portion of the top of a wall characterized by scarce thickness, since it did not bear the load of the roof and was conceived as a simple light closure. 3. REINFORCED CONCRETE BUILDINGS 3.1 L’Aquila reinforced concrete building stock ISTAT 2001 data, representing the official source for information about a b building stock in Italy, indicate in L’Aquila city a 24% of reinforced concrete structures, 68% of masonry structures and an 8% of structures whose typology is not identified (Figure 36a). Data that identify the age of construction of the buildings (Figure 36b) indicate that 55% of the whole patrimony was realized after 1945. Considering low incidence of RC structures on the total it is possible to infer that after 1945 new masonry structures were still realized and that RC structures number increased gradually over years. From distribution of storeys number (Figure 36c) it can be observed that only 5% of the buildings have more than three storeys. Assuming that all buildings with more than three storeys are RC structures, it is still possible to infer that the great majority of L’Aquila RC buildings have no more than three stories. Assuming an interstorey height that can vary between 3.0 and 3.5 meters, period approximate formulation given by the Italian Code, referred to RC frame structures, gives for three storeys buildings a fundamental period equal to 0.4 seconds. In the following section, when comparing different Italian Code spectral shapes, it will be possible to focus on period value ranges minor or equal to 0.4 seconds, thus leading to a comparison between constant acceleration parts of the spectra. 3.2 Structural and non structural damages In this section main structural and nonstructural damages to RC structures after L’Aquila earthquake are presented. Figuregraphic documentation was produced in the following few days after the 6th April 2009 mainshock. Generally speaking, damages to structural elements are not so frequent and they seldom involve the whole structural system, on the other hand damages to nonstructural elements such as internal and external infill panels involved the main part of RC structures in L’Aquila. 3.2.1 Columns and walls Main structural damages involving RC columns can be easily interpreted as failures caused by mechanisms which capacity design principles can avoid or at least limit. It is worth to observe that during an earthquake columns put up with c Fig. 36- 2001 census ISTAT data for L’Aquila town: (a) building typology, (b) age of construction, (c) storey number 100 RESEARCH - L’Aquila Earthquake high flexural and shear demand. Maximum flexural demand joined with axial force produced by gravity loads and seismic loads are located at the end of the element; in these zones (critical regions) rotational ductility demand can concentrate. Therefore, it is necessary to provide an adequate rotational capacity and to avoid buckling phenomena on compressed longitudinal reinforcements. Actual Italian seismic code provides prescriptions aimed at increasing section rotational capacity: upper limit on longitudinal reinforcement percentage, fixed the flexural resistance of the section, leads to a higher ultimate section curvature; a proper spacing between hoops and crosstie presence give, by a more efficient confinement action on concrete, an additional increase in section deformation capacity. Additionally, a proper hoop spacing avoids buckling phenomena in longitudinal reinforcement or at least fixes an acceptable upper bound limit for which this phenomena occur. On the other hand, prescriptions and structural detailing presented above are typical of modern design concepts that in Italy appeared for the first time in 1997 with explicative document to the 1996 code but were adequately ruled only in 2003 with OPCM 3274, and finally officially adopted in 2008 by DM 14/01/2008 and its subsequent explicative document. So, according to codes that were in force before 1997, it is possible to find RC columns with longitudinal reinforcement percentage that exceeds 4% limit, section dimensions not conforming to actual limitations, hoops with a not sufficiently thick space (15-20 cm) and closed with 90° hooks. Figure 37(a) presents a corner column of a RC building in L’Aquila historical centre, probably realized between 1950 and 1960, where damages occurred at the bottom end section of the element. Presence of smooth bars and small diameter of the hoops (6 mm) closed with 90° hooks can be observed, but most significantly the absence of any transversal reinforcement in the first 30.40 cm of the elements immediately adjacent to the beam-column joint region. a Fig. 37- Column with smooth bars and poor transversal reinforcement (a); damage to a column due to axial - bending interaction (b). RESEARCH - L’Aquila Earthquake Figure 37(b) reports a circular column belonging to a building in the residential zone of Pettino, realized during ’80s, which shows a typical damage due to axial force and bending moment; concrete cover was spalled due to high compression strain and longitudinal bar buckling. In this case too hoop spacing is not thick enough but probably designed in perfect accordance with code prescriptions at the age of construction. In analogy, shear demand can produce brittle failures with an outstanding dissipative capacity reduction of the column. Minimizing shear resistance mechanism to transversal reinforcement spacing only can be not exhaustive. In modern design rules shear design has to involve capacity design principles such as fixing a proper hierarchy between brittle and ductile failure mechanisms, that is shear and bending behavior of the element. In order to prevent brittle failures during post-elastic behavior, shear demand has to be evaluated based on maximum flexural demand of the element. When this criterion is applied to column, it consists in a rotational equilibrium, obtaining shear demand by the ratio between the sum of the bending moments at the end sections and the total height of the column. It is possible to prevent a brittle failure occurrence applying an amplifying coefficient to the shear demand. When shear demand is evaluated, possible local interaction with adjacent infills is considered; in fact when masonry panels do not completely fill the RC bay, evaluation of shear demand is based on the height of the column subtracting infill panel height. Adopting proper capacity models it is possible to take into account concrete degrading resistance mechanisms due to ductility cyclic demand. These prescriptions are provided by the Italian code since 2003, before OPCM came into force shear design of columns used to be made assuming shear demand from linear analyses; this procedure can easily lead to shear capacity underdesigned respect to flexural capacity; so no control of the failure mechanism can be applied and a priori the failure mechanism can be either brittle or ductile. All above considerations can be confirmed by column damages reporb a b Fig. 38- Shear failures of rectangular (a) and circular (b) columns. 101 squat column is different respect to the typical behavior of a slender element. This is why, if local interaction between the column and the concrete wall is not taken into account, a premature brittle failure due to concrete excessive compression can more often occur. Even columns belonging to staircases can show brittle failures. Most common staircase typologies, generally, are characterized by discontinuity elements in the regular RC frame scheme composed by beams and columns. In fact, on a side staircase is composed by inclined axis elements (beam or slab), on the other side squat columns are created by the intersection of inclined axis element with the column. Staircase elements considerably contribute to lateral stiffness of the whole structural system due to axial stiffness of inclined axis elements and to higher lateral stiffness of squat column. This contribution is simply estimable via linear analyses. On the other hand, staircase elements are characterized by higher shear demand that can lead to brittle failure mechanisms. Figure 40 shows a staircase composed by inclined axis beams, in particular the squat column in the corner, due to intersection with the beam, is characterized by a typical shear failure, due to an unfavorable shear demand capacity ratio. Poor transversal reinforcement in terms of spacing and hoop diameter is to be noted. Shear failures characterized reinforced concrete wall performances too. ted in Figure 38. Considering the rectangular column in Figure 38(a), whose section is probably (30x100) cm2, belonging to a building realized in 80’s, a shear failure involving top end section is evident. Transversal reinforcement has a hoop spacing approximately equal to 15-20 cm, that is completely underdesigned respect to column section dimension and consequently respect to the section inertia, leading to a premature shear failure of the element. The brittle failure mechanism is to be noted, underlined by the crushing of the concrete within the reinforcements. Third and fourth hoops from the top end of the element that are completely opened. Figure 38(b) shows shear failure of a circular column characterized by a 30 cm diameter; in this case too it is possible to detect the hoop spacing not thick enough, that leads to diagonal cracking typical of shear mechanisms and to instability of longitudinal bars in the column. In order to highlight the non secondary role played by column – infill interaction in determining shear failures in the elements, Figure 39 presents some damages to columns. In particular in Figure 39(a) it is possible to recognize the brittle failure in the column due to the local interaction with the concrete infill that partially covers the bay frame getting to 1/3 of the total height of the column. Partial infilling effectively interacting with the column reduces the effective height of the element, producing a higher shear demand that exceeds column shear capacity. This kind of phenomenon involves all of the columns that interact with the concrete partial infilling. Figure 39(b) shows an example of buildings with a partly below ground level. This basement level is characterized by walls, often realized with concrete, aimed at a retaining function of the adjacent embankment; concrete wall height is limited respect to column height to allow the realization of windows. This structural solution leads to a strict reduction of column effective height with a consequent increase in shear demand. Moreover shear span decreasing of the element can modify shear span ratio up to a modification to a squat column behavior. This situation is not of secondary importance, because shear resistant mechanism of a a Fig. 39- Shear failures of column adjacent to partial infilling panels (a), shear failures of squat column adjacent to basement level concrete walls (b). 102 Fig. 40- Shear failure in squat columns of the staircase. b Fig. 41- Failure in reinforced concrete walls. RESEARCH - L’Aquila Earthquake As an example, Figure 41 reports damages detected in two reinforced concrete walls, respectively characterized by two different shape factors; damages consist of a spread diagonal cracking. Low longitudinal and transversal reinforcement percentage can be observed, especially if compared with minimum values prescribed by actual design code. 3.2.2 Beam - column joints Beam-column joints can completely modify structural complex behavior and their failure should be necessarily avoided in a proper seismic design, considering that these element are characterized by brittle failure mechanisms. In these zones, geometrically very small, demand from beams and columns is concentrated and concrete panel with longitudinal bar is subjected to high gradients of shear and flexural demand. Beam-column joints influence structural behavior in terms of both ductility when concrete cracking and bar sliding occur and resistance when brittle failures occur. Failure mechanisms of joints are principally governed by shear and bond mechanisms. In fact force distribution which allows shear and moment transfer produces diagonal cracking and consequently joint failure due to diagonal compression in the concrete can occur, producing a reduction in strength and stiffness in the connection. Cyclic degrading of bond mechanism, on one hand, produces a reduction in bending resistance and in the ductility of the elements meeting in the joint; on the other hand an increase in lateral deformation of the level is detected. Therefore, capacity design rules essentially aimed at avoiding brittle failure mechanisms point to shear failure prevention in joints by means of design rules and proper reinforcement detailing. In fact if the joint collapses, a strict limitation results in resistance and deformation capacity of the adjacent structural elements. Generally speaking, joint design is defined by the condition of a diagonal stress induced by the elements meeting in the joint not exceeding allowable concrete compressive stress. Furthermore, in order to keep structural continuity when concrete cracking occurs, a proper transversal reinforcement along the whole element should be provided. Transversal reinforcement allows to transfer stresses even if concrete cracking phase has been overtaken, by means of a strut and tie mechanism that can develop if longitudinal, transversal reinforcement and concrete struts contribute to a truss formation. By these design prescription in the joint a ductile mechanism in beam elements can develops, avoiding a brittle failure in the joint. Joint design rules appeared in the Italian design prescriptions only in 2003, in fact in 1997 explicative document to 1996 code a transversal reinforcement in joints at least equal to the hoop spacing in the adjacent columns was simply necessary. It can be gathered that all structures realized before 1996 are characRESEARCH - L’Aquila Earthquake terized by beam-column joints without transversal reinforcement. In this kind of situation, when cracking occurs no truss mechanism can develop, leading to a strict reduction in strength capacity of the joint. Considerations presented above are confirmed by damages observed in RC structures after 6th April 2009 earthquake. Figure 42(a) shows an external beam-column joint, characterized by an extensive cracking in concrete belonging to the joint panel. The absence of transversal reinforcement in the joint, probably because of the vertical component of the seismic action, led to local buckling of the longitudinal bars that consequently brings to concrete cover spalling. It is worth to observe that the absence of a proper transversal reinforcement in the joint conducted to a loss of anchorage in beam longitudinal reinforcement. Figure 42(b) shows a typical diagonal cracking failure in concrete panel belonging to an external joint. Crack begins at the intersection between joint and upper column and ends at the intersection between joint and lower column producing the loss of monolithic connection. Hoops absence, in this situation too, leads to a buckling in the external longitudinal bar and it involves lower column not provided of transversal reinforcement in the first 30-40 cm. Other remarkable aspect in RC damage observation after L’Aquila earthquake is a peculiar loss of connection at joint-lower column interface, probably due to a not prepared cast surface that can lead to a shear friction failure. Generally, there are no code prescriptions, nor Italian or international, providing a shear friction verification at joint-column interface, because some execution details, such us preparation of the cast surface and a proper diffusion of longitudinal reinforcement along the perimeter of the column section ensure that this failure condition does not limit or influence design procedure. In fact, main resistant mechanisms in post-cracking condition are referred to (i) concrete to concrete interface shear, (ii) dowel action in column longitudinal reinforcement and (iii) clamping action produced by a local yielding in longitudinal bar that contributes to transfer main part of the shear strength. b a Fig. 42- Joint failure with evident longitudinal bar buckling (a), diagonal cracking failure in concrete joint panel (b). 103 Fig. 43- Failure mechanisms at joint – column interface surfaces. Shear friction mechanism is evidently influenced by axial force amount and roughness (friction coefficient) of the casting surface; a not proper preparation and control of the casting surface can reduce shear friction resistance. Clamping action – a friction mechanism too, integrating above contributions – is proportional to longitudinal reinforcement amount. Dowel action, not negligible in post cracking phase, is strictly connected to longitudinal reinforcement percentage but mainly, due to their peripheral position, to effectiveness of transversal reinforcement in the zone adjacent to the sliding surface. Hoops, in fact, work as a translational restraint to longitudinal bars involved in the mechanism. Figure 43(a) reports a failure mechanism due to the loss of continuity at the intersection between joint and lower column. A poor treatment of the casting surface can be easily detected and it can lead to a lower concrete to concrete friction coefficient in correspondence with this weaker surface. Reinforcement probably composed by only four longitudinal bars and the absence of hoops in the zone strictly reduce dowel action. In fact, this limitation is substantially due to a low longitudinal reinforcement percentage not properly spread on the section perimeter, joined with the spalling of the concrete cover that is the only transversal restraint to horizontal bar sliding. A strong reduction in the axial force essentially due to a non ordinary strong vertical component of L’Aquila event has further reduced shear friction capacity. Figure 43(b) shows, as well as Figure 43(a), a clear separation in concrete at joint-column interface. Absence of hoops in the joint and axial force reduction due to vertical seismic action strictly reduce, respectively, dowel action mechanism and friction mechanism at joint-column interface. 3.2.3 Infills In the previous section it was emphasized how damage limitation limit state prescriptions and verifications are essentially aimed at avoiding or reducing infill damage and most remarkably that this kind of prescription was firstly introduced in the Italian code only in 1996 and better detailed and completed in 2003 with OPCM 3274. Therefore, it is reasonable to assume that the main part of RC buildings in L’Aquila was realized without any deformability control and verification. On the other hand it should be emphasized that, even if a design procedure according to 1996 or better according to 2008 code had been employed, involving damage limitation verification, the strong PGA characterizing L’Aquila event would have equally produced a spread diffusion of damages to nonstructural elements such as external infills. As a general rule, infill failure mechanisms can be classified in: (i) horiFig. 44- Infill panel failures: diagonal cracking (a), (b) and corner crushing (c) mechanisms. b c a 104 RESEARCH - L’Aquila Earthquake zontal sliding in the central zone of the infill panel, (ii) diagonal cracking due to tensile stress in the central zone of the infill panel, (iii) corner crushing in the direct contact application zone. Figure 44 reports two building facades in which infill panels are characterized by a diagonal cracking mechanism. In the first case, see Figure 44(a), it is worth to note how cracking diffusion involves infilling adjacent to window openings and damage is concentrated at the first levels of the building; in the second case, Figure 44(b), diagonal cracking is more emphasized by plaster layer because the external layer of the infill is composed by solid clay bricks. Figure 44(c) shows a typical corner crushing mechanism. Out of plane failure of the infilling external layer gives the possibility to detect corner crushing mechanism of the internal layer; other evidence is the crack, that visibly involves the plaster but probably is deeper, localized at the top of the column adjacent to the infill panel as a consequence of column-infill local interaction. The great majority of external infill panels are composed by double layer infill panel, internal layers are generally realized with clay bricks; connections between the two layers are realized by the interposition of brick elements discretely, Figure 45(a), or lined up, Figure 45(b). Not reliable efficacy of this system should be stressed. Furthermore, in most of the observed cases, internal infilling layers are restrained at the four corners of the RC frame while external ones are constrained only by the upper and lower beam by means of a little pawl. This executive solution leads to a reduction in the interaction mechanism between RC frame and external infill panel in both plane and out of plane seismic forces. In fact, the low efficacy of the restraint applied to the external panel, coupled with ineffective connections or complete absence of connections between the two layers, produces a damage restricted to the external infill panel, which shows an out of plane failure due to seismic action in both directions as it can be detected in Figure 46. Windows or door openings represent a discontinuity in the infill panel, modifying its performance and capacity by a reduction in terms of stiffness contribution and by a modification in the failure mechanism. Figure 47 shows damages detected in L’Aquila RC buildings characterized by a different opening position in the panel or a different opening percentage respect to the total area of the bay. Both local and global interaction effect between infill and RC structure are not negligible. As it was previously emphasized, local interaction between infill panel and adjacent column can bring to (i) a reduction in the effective length of the column, an increase in shear demand and a consequent brittle failure of the column when the panel partially fills the frame bay; (ii) to a concentration of shear demand at the end of the column and to a consequent brittle failure when diagonal compression RESEARCH - L’Aquila Earthquake b a Fig. 45- External infill panel failures and discrete (a) or lined up (b) connections between layers. b a Fig. 46- External infill panel failures without connection between layers (a) and with ineffective connection (b). is applied by the panel to the RC element. As a global phenomenon, infill-structure interaction increases global stiffness of the complex system and consequently spectral acceleration demand, besides it can represent a source of irregularity in plan or in elevation when a non uniform distribution is present. 3.2.4 Criteria for regularity in plan and in elevation Regularity criteria in plan or in elevation were introduced in the Italian code in 1997 by the explicative document to the 1996 code as a qualitative definition. Only in 2003 by means of OPCM 3274 introduction a b a c Fig. 47- Infill failure mechanisms differing form opening position and percentage. 105 quantitative definition of regularity in plan and in elevation was furnished. A compact shape in plan that implies geometrical limitation in the appendixes, a uniform distribution of resistant systems in plan, slabs that can be considered as rigid respect to vertical resistant elements can ensure a regular structure in plan. Conversely, a verification in mass and stiffness distribution, verifying that storey lateral strength is not characterized by unexpected reduction, leads to a regular structure in elevation. In spite of a quantitative definition of regularity criteria, not necessarily these criteria are enough to avoid other irregularity sources not considered in the design procedure of the RC structure. It is the case of infills that by means of interaction with the structure can strictly modify stiffness and strength distribution in plan and in elevation. It is necessary to avoid non uniform distribution of infills or conversely it is necessary to explicitly take into account infill contribution in the analysis procedure. For example, Italian seismic code provides some prescriptions aimed at considering infill irregularity contribution in plan by an increase of accidental eccentricity value or in elevation by an increase of the shear demand at the storey characterized by an irregular distribution of the infills. Some peculiar cases of structural failure after L’Aquila event, mainly caused by irregularities in plan or in elevation, are reported in Figure 48. Figure 48 shows a view of the structures before the earthquake, so without any damages, on the left, and after the event where collapse is evident on the right. The first structure, Figure 48(a) and 48(b), was placed in the centre of L’Aquila city (Porta Napoli street); it was characterized by elevation irregularity due to the non continuity of the seismic resistant scheme over height, additionally, second level was characterized by an evident discontinuity in terms of infill distribution, in fact on the left wing of the building there is a sort of porch. Observing building collapse, a damage concentration at the second level is to be noted, that consequently produced complete failure of the upper levels. The two other structures proposed in Figure 48 are both placed in the residential zone of Pettino (Dante Alighieri street), close to L’Aquila, and present the same shape in plan similar to a T, so they both can be considered as irregular in plan. In addition to plan peculiarities, a different distribution of infills at the first level respect to the others, due to the presence of garages entrances, can be observed. Both buildings placed in this street showed a soft-storey mechanism at the first level that can be explained by infills irregularities in elevation and presumably by a local interaction between infills and adjacent columns, leading to a brittle failure of some columns at the first level. 4. SCHOOL BUILDINGS a b c d e f Fig. 48- Soft storey mechanisms examples in L’Aquila: Porta Napoli street (a), (b), Dante Alighieri street (Pettino) (c), (d), (e) and (f) before and after collapse occurrence. 106 One of the main objectives of the Civil Protection in the immediate post-earthquake of L’Aquila of April 6th, 2009 has been scholastic buildings’ damages assessment as well as the fast repair of the ones with non structural damages only. These activities have been developed by a joined work of Function 1 of Emergency Management and Quarter of Department of Civil Protection (DPC), Consortium ReLUIS, Seismic Risk Competence Centre of DPC and Public-Works Office of Lazio Sardegna and Abruzzo. The structural safety assessment of L’Aquila scholastic buildings started on April 8th, 2009. The in-site inspections have been coordinated by ReLUIS under the supervision of Function 1 of DPC at Reiss Romuli; the inspections have been related to both L’Aquila and its provinces scholastic buildings. The activity involved 62 scholastic buildings of L’Aquila: 53 under the administration of L’Aquila municipality (6300 students on the total of about 7000) and 9 of province (4000 students on the total of about 5000). A total of 156 structures have been investigated. The results of structural safety assessment is summarized in Figure 49. The in-site inspections on scholastic buildings in the L’Aquila provinRESEARCH - L’Aquila Earthquake and about 21% masonry structures (see Figure 51) In terms of damages the results of in-situ inspections showed that about 31% of RC framed structures were assessed as A (i.e. no significant damages), about 43% as B (i.e. no significant damages on structural members) and about 26% as E (i.e. significant damages on both structural and non-structural members). The structures with a lower level of damage (i.e. A and B) have been mainly built between ’60s and ’90s years while the structures recorded as E were mainly built between ’20s and ’70s years. The RC framed structures mainly showed damages on non-structural members (i.e. partitions and ceiling); the elementary school of Paganica is a typical example of such kind of structures (see Figure 52-53). An example of RC framed structure with significant damages on structural members is the school “Celestino V”, see Figure 54-55. The RC shear wall-type structures were assessed only as A (27%) or B (73%); no significant damages on structural members were found at all. The masonry structures, mainly built before ’60s years, were assessed as: 30% A, 24% B, and 46% E. Figure 56-57 show some significant damages on masonry members of the elementary school “S.Elia”. Fig. 49- Structural safety assessment on L’Aquila scholastic buildings. Fig. 50. Structural safety assessment on scholastic buildings of L’Aquila provinces. ces were performed in 64 different municipalities on 224 buildings for a total of 309 structures; the results of such activity is summarized in Figure 50. The scholastic buildings of L’Aquila are mainly reinforced concrete (RC) or masonry structures; in particular, about 66% are RC structures (56% RC framed structures and 10% RC shear wall-type structures), a Fig. 52- Damages on partitions at elementary school of Paganica. b c Fig. 51- Structural safety assessment results on scholastic buildings of L’Aquila: a) A; b) B; c) E. RESEARCH - L’Aquila Earthquake 107 Fig. 53- Cracks and plaster spalling on partitions of elementary school of Paganica. Fig. 56- Roof collapse of elementary school “S. Elia”. Fig. 54- Column crack at elementary school “Celestino V”. Fig. 57- Diagonal cracks on masonry panels of elementary school “S. Elia”. Fig. 55- Damages on ceiling at elementary school “Celestino V”. In the immediate post-earthquake several teams with members from ReLUIS, Seismic Risk Competence Centre of DPC and Public-Works Office of Lazio Sardegna and Abruzzo were involved in a further stage of in-situ inspections on schools in order to investigate the repair possibility before the new scholastic year official opening (foreseen in September). In some cases several destructive and non-destructive tests were performed in order to investigate on the materials mechanical properties. As a result of this second round of in-situ inspections, a cost estimate to fully repair these schools was also performed. The repair interventions were planned on schools assessed as A and B; the repair strategy and the interventions design were provided by engineers of municipality or province under the supervision of ReLUIS and PublicWorks Office. The Public-Works Office also managed the bids for works execution (see Figure 58). 108 RESEARCH - L’Aquila Earthquake Fig. 58- Table of works at elementary school of Torrione. Fig. 61. Intervention on partition to avoid the overturning. Fig. 59- Strengthening of joints on elementary school of Paganica. Fig. 62- Investigation on masonry corner of elementary school “Villa Grande” of Tornimparte. Fig. 60- Strengthening of joints on elementary school of Torrione. According to Ordinances 3789 and 3790 and commentaries the works involved not only the repair of non-structural members but also local strengthening interventions on structural members (i.e. strengthening of front and corner joints of RC structures (Figure 59-60), insertion on masonry members of chains and braces) and non structural members (interventions on partitions in order to avoid their overturning, to connect their internal and external faces, and application of zinc coated steel grids on partitions), Figure 61. The execution of repair and strengthening works has been developed together with the execution of materials non-destructive tests (rebound and sonic tests, tests on concrete cores and steels specimens, (Figure 62) as well as tests by using flat jacks on masonry structures). Finally, load tests were performed on slabs and flights. The analysis of several cases of study allowed to optimize a series of repair or local strengthening intervention on existing RC or masonry RESEARCH - L’Aquila Earthquake 109 structures; a detailed description of standard repair interventions to restore damaged buildings due to seismic actions has been reported in a document developed in collaboration between DPC and ReLUIS, “Guidelines for Repair and Local Strengthening of Structural and Non Structural Members”. The synergy between DPC, ReLUIS, Public-Works Office as well as municipality and provinces allowed scholastic buildings assessed as A to be opened with urgency in order to regularly perform the exams at the end of the scholastic year. Further, the whole stock of scholastic buildings assessed as B has been opened in the period between September 21st and October 5th. 5. THE CASE OF SAN SALVATORE HOSPITAL OF COPPITO The recent earthquake of 6th April 2009 significantly hit the city of L’Aquila and its surroundings both for the serious number of casualties and for the damage suffered by residential and important structures. Among the latter, one of the most important is surely the San Salvatore Hospital of Coppito, the crucial point of the hospital system in the area of L’Aquila, which was completely evacuated during the emergency due the damage at various floors of the buildings. A thorough analysis of the hospital facilities has shown besides the essentially non-structural damage also some aspects of the construction of the hospital complex, which might be crucial for the seismic response to future shocks and therefore open more critical damage scenarios. Other smaller hospitals located in neighbouring urban areas showed minor damage, allowing partial absorption of emergencies, thus reducing the enormous overload on the field hospital set up close to the San Salvatore Hospital. Recent valuations, in fact, have shown that more than 1500 injured received assistance during the days after the emergency, which confirms the tremendous impact on the hospital system. The hospital structure has been designed in 1966 and took about 30 years to build entirely. Such an information is particularly important if related to developments in domestic seismic regulation. In fact, the first Italian seismic law, considered a forerunner of the most modern ones, was n. 64 of 2/2/1974, issued after the 1974 Ancona earthquake. Previously, references to seismic law came from Royal Decrees (e.g. Regio Decreto Legge n. 2105 of 22/11/1937), while during the Republic era there was Act n. 1684 of 1962 that followed the Campania earthquake of 21/08/1962, and was later completed by Act. n.1224 of 5/11/1964, and by the Act n. 6090, 1969 issued after the Belice earthquake. However, such references were oriented towards defining heights, thicknesses, executive methods and quality of materials rather than calculation methods and design criteria. After the 6th April earthquake, only 3 buildings out of 15 in the San 110 a Fig. 63- Evidence of the reinforced concrete frame structure through the damaged partitions: Building 9 (a); Building 10 (b). Salvatore complex suffered considerable structural damage. This was limited to small areas and primarily was due to evident issues that will be described in detail later in this work. There was slight and relatively limited non-structural damage and significant non-structural damage in only a few buildings. In these latter inner partitions significantly helped the lateral resistance by dissipating the earthquake’s energy and suffering critical damages (Figure 63). The basement and semi-basement part of the complex, mostly made up of reinforced concrete walls, showed a stiff box response without significant damage. Finally, no evident damage was observed in the foundation structures. From the point of view of the human safety, the most widespread and relevant non-structural damage was that of exterior façade bricks, covering the entire surface of all the buildings. Such a coating, not linked to the interior walls, in many cases was partially or totally detached. No significant damage was observed on the equipment and internal mechanical devices inside. 5.1 Description of the structures of the San Salvatore Hospital In terms of typology, the San Salvatore Hospital complex consists of a series of reinforced concrete frame structures, with interior and exterior masonry walls, built from the mid ‘70s on, and put into service in the second half of the ’90s. Some of the buildings of the complex are not hospital property. The buildings differ in typology, materials and heterogeneous construction details depending on the different age of construction. A covered walkway connects the various blocks on four floors, two above ground and two underground. There are several building typologies: L-shaped of 2 or 3 storeys, tower blocks of 3 or 4 floors, in-line buildings of 2 or 3 storeys and some ground-level buildings. Most of them have one or two basement floors. The approximate date of construction and the main function of the various blocks, identified on the basis of the numbering given in Figure 64, was provided by the Technical Department of the hospital and is shown in Table 1. RESEARCH - L’Aquila Earthquake b Table 1 - Buildings of the San Salvatore Hospital complex, Coppito, L’Aquila Denomination Function Construction age Building 1 Thermal Power station 1977/78 and refectory Building 2 Analysis laboratories 1976/77 Building 3 Diagnostics and radiotherapy 1976/77 Building 9 Emergency room 1978 Building 10 Pharmacy and operatory rooms 1978/79 Building L1 Direction 1983/84 Building L2 Obstetrics and gynaecology 1983/84 Building 6 Wards 1987 Building L3 Oncology 1979/80 Building L4 Infectious Diseases 1979/80 Building L5 Neurology 1983/84 Delta 6 Wards 1987 Delta 7 Medical Delta 1985 Delta 8 Surgical Delta 1980 In all the buildings of the complex there are also several structural joints of sizes and characteristics not appropriate to shock induced movements. The resulting local pounding between adjacent bodies caused localised damage, somewhere particularly evident. Figure 66, for example, shows the damage to a structural joint ending on the top of a column, which have caused an abnormal concentration of pressure on the joint. Figure 67 shows the cracking continuing in the ceiling from the damaged joint in the wall, found in a connecting walkway (Building 2). Some local damage have been caused because of improper construction 5.2 Usability surveys and structural response Fig. 65- Damage to the coating of Building 2 (a), Building 9 (b) and Building L3 (c). The buildings of the hospital complex have been repeatedly checked because of a succession of significant after-shocks related to the so-called seismic swarm, and were grouped into categories depending on the assessed damage. All the buildings have an exposed brick wall covering, which is not enough or not at all connected with the infill panels and the reinforced concrete frame structure. These are therefore critical for human safety since they can be dangerous and might fall onto the walkways (Figure 65). Another type of frequent and potentially dangerous non-structural damage is the complete detachment of the coating of many of the ground floor tiled walls. a c b Fig. 66- Improper structural joint ending on the top of a column. Fig. 64- Site plan with different blocks (the groups of buildings identify the classification of usability as described in section 4). (Gruppo/Group; Edificio/Building) RESEARCH - L’Aquila Earthquake 111 Fig. 67- Damaged structural joint on wall, extending in ceiling. shortly, and therefore can be usable by means of simple short term countermeasures, among which: removing falling cladding, plaster and detached coatings, making safe damaged false ceilings, repairing light damage to claddings and partitions, checking all the fixings hanging from cladding and false ceilings, in order to evaluate the possible detachment risk, creating localized barriers to protect walkways, and removing unsafe portions of the outer coating. Buildings L1, L2 and L5 belong to this category, which show widespread light non-structural damage, particularly at the ground level. These three buildings will be the first to be reopened at the end of May 2009, less than two months after the main shock. Group 3: partially usable buildings Each of the Buildings 2 and 3 is composed of two different blocks separated by a structural joint, which show different levels of damage. In particular Buildings 2A and 3A, which face Building Delta 7 (Figure 69), are not usable, whereas light non-structural damage is common to the rest of Buildings 2B and 3B (Figure 69). Unlike group 1, in this group of buildings the unusable part features high structural risk, whereas the less damaged part requires modest intervention before to be used again. Fig. 68- Examples of improper transversal reinforcement and insufficient concrete cover in Building 2A and in the external connecting walkways. detailing, at least according to current seismic design criteria, such as the not always appropriate confinement of the structural elements, the insufficient concrete cover (Figure 68), the presence of columns made squat by the infill masonry walls. Fig. 69- Buildings 2A/3A and 2B/3B (Edificio/Building). Group 1: usable buildings Regarding the basement, 6 metres underground, where the thermal power station is located, Building 1 shows moderate non-structural damage, particularly in the offices at the lowest floor. The portion housing the power plant shows a moderate damage in some beams, mainly as a result of the relative movement of the Gerber half joint, and it is therefore usable. The rest of the building, however, shows greater damage in the upper storeys, even if it does not constitute a danger to the floor below, and it is therefore to be considered unusable. Group 2: buildings that can be made usable with short term countermeasures Some buildings with slight non-structural damage can be reopened 112 b a Fig. 70- Damage of the stairs of Building 2 (a) and Building Delta 8 (b). Buildings 2B and 3B can be made usable with short term countermeasures, like those described in the previous paragraph. At the last flight of the inner stairs between portions 2A and 2B, mild localized structural damage was detected, probably due to concentrated rotation of the RESEARCH - L’Aquila Earthquake Fig. 71- Structural damage (plastic hinges and shear failures) at the top of columns (ground floor of Building 2A) caused by insufficient transverse reinforcement. Fig. 72- X cracks on the external coating of Building 2A. Fig. 73-. Important damage to partitions in Building 9. RESEARCH - L’Aquila Earthquake 113 Fig. 74- Structural damage caused by the presence of belt windows, which make the columns squat in Building 10. knee beams (Figure 70). In this case limited restoration intervention can be provided, such as repairing cracks with resin or anti-shrinkage mortar, and later if necessary a seismic retrofit can be designed using fiber-reinforced materials. Blocks 2A and 3A are unusable because of the considerable non-structural damage and the structural risk caused by the failure of some columns of the covered walkway over the driveway to the Emergency Room, facing the Building Delta 7. This is the first area of significant structural damage. As shown in Figure 71, at the top of the columns it is possible to recognize clear plastic hinges, shear failures, spalling of the concrete cover with the consequent instability of the longitudinal reinforcement. All these effects are due to the scarcity or absence of transversal reinforcement, i.e. of confinement. This has led to a near state of collapse, requiring urgent propping intervention. In the same area there is widespread damage to infill panels, with the formation of X-cracks (Figure 72) typical of shear failure. Although such failures may affect only infill panels, potential shear failure to the structural elements under the damaged coating cannot be excluded, and therefore they must be checked. Group 4: buildings requiring more extensive non-structural measures A number of buildings can be made usable only after significant local demolition and reconstruction of the most damaged partitions and removal and restoration of all unsafe or detached parts. The restoration of conditions of temporary usability in this case requires more time, and therefore cannot be included among short term countermeasures. Buildings 9, L3 and L4, in this group, have suffered moderate to severe non-structural damage to many of the ground floor partitions (Figure 73) and a widespread light non-structural damage at the upper storeys. On the more damaged part, the usability restoration requires demolishing and rebuilding some infill walls, and propping a stair in Building 9. Group 5: unusable buildings The last group of buildings is classified as unusable, due to the significant structural damage or because they are close to dangerous buil114 dings, or because they feature a high percentage of severely damaged partitions compared to the volume of the building. Building 10 has severe structural damage at the ground floor, because of the shear failure of all the columns on the side in front of the church. In this part the columns have been made squat by the infill panels interrupted by the belt windows along the north-east side (Figure 74). It is clear that for most of these columns the bearing capacity is seriously compromised. The building also has widespread moderate to severe non-structural damage, particularly at the ground level. To ensure this building will not collapse, short-term countermeasures are arranged, by means of a series of cement block infill panels between the columns of the external porch and by propping the beam supported by the damaged columns. In Buildings Delta 7 and Delta 8 there is widespread structural damage more important at the lower levels. The damage to partitions is nonstructural but widespread and of moderate to severe intensity. The only light structural damage is found in one of the stairs. The two buildings are considered unusable, due to the significant extension of damage, together with the structural irregularity and the proximity of buildings with structural problems (Building Delta 8 is next to Building 10 and Building Delta 7 is adjacent to Buildings 2A and 3A). 5.3 Usability of walkways and connections in basements The basements of all the inspected buildings, where accessible, have no Fig. 75- Connecting walkways: hollow clay block collapse of the intrados of the basement at 3 metres below ground. RESEARCH - L’Aquila Earthquake significant damage. There are rare and limited examples of hollow clay block collapse in the ceiling of basements at 6 and 3 metres below ground (Figure 75). At the level of 6 metres below the ground there are unused spaces, accessible only by technical personnel, without significant damage, except for localized seepage and settlement/shrinkage cracks. At the level of 3 metres below the ground, in the underground passage connecting the buildings, the damage is predominantly non-structural and not very extensive. It mainly consists of the damage to existing joints and the formation of ‘natural’ joints after the event, with limited plaster and coatings detachments, and some hollow clay blocks collapse. In such basement levels the damage is more significant towards Building 1, where some localized modest damage is present. At the first floor level (3 metres above ground) there is damage to existing joints, formation of cracks, primarily to the completion of incomplete joints, and the subsequent detachment, sometimes only partial, of plaster, false ceilings and coatings. At the ground level the most critical situation is found since the connection walkways between the various buildings are not protected, sometimes there is just a covered porch. The risk of falling of loose parts of partially detached coating or new portions of coating falling off, even after minor shocks, makes the need to remove partially detached or already collapsed coating urgent, to protect all the paths adjacent to the buildings (when there is no covered porch) from falling objects and to close off the riskiest paths. At this level there is some structural damage: a column behind Building 9 stressed by a structural joint, and another column on the corner of Building 2 with a plastic hinge at the top. 6. INDUSTRIAL STRUCTURES 6.1 Building-like industrial structures Industrial buildings were built for many years as an assemblage of precast reinforced concrete elements. The April 2009 L’Aquila earthquake has struck, for the first time in Italy, industrial structures on a large scale. In fact, the Irpinia 1980 earthquake hit an area with few industrial sites; and similarly happened in the Umbria and Molise earthquakes, which moreover were felt within a limited area. On the other hand, the Friuli 1976 earthquake damaged industrial structures, but they were designed with no regard with respect to the seismic action; if any design rule was used, this however belonged to inadequate seismic codes. L’Aquila and its surroundings are instead undergoing a rather strong industrial development. Precast reinforced concrete buildings, RESEARCH - L’Aquila Earthquake with a column-beam structure, are the usual type in the industrial areas in Pile, Bazzano, Monticchio and Ocre (AQ). Buildings have generally one storey; two storeys are seldom observed, moreover only on a more limited area than the first storey. Beam supports on the columns may be of the saddle or bracket type. Deck beams are usually transversally aligned (with respect to the longer side of the structure plan) and they are I-shaped, with variable depth; longitudinal alignment and inversed Tshapes are less commonly observed. In the latter case, the shape is used to support the tiles. The roof is generally built with tiles -shaped; less often U-shapes are observed. Skylights are sometimes present. -tiles are also used for the intermediate deck, when there is one. External partitions are either made with bricks, or with precast reinforced concrete shells, with no stiffeners. Structural nodes are those typical of the Italian constructions: beaker footing for the foundation to column nodes, simple support for the beam to column nodes (with neoprene bearings and steel pins). Tiles are generally directly resting on the beams, with neither horizontal restraint nor neoprene bearings. Pin connections are seldom present. Tiles may be connected each other with the upper reinforced concrete layer, or simply linked via steel restrainers (partly poured within the tiles concrete, partly welded with the next tile restrainer). Partition panels are either supported by the eaves beam or by the column, via links of many types. They are also sometimes supported by the deck tiles. A typical shell-eaves beam connection is via a steel plate partially put within the concrete shell during pouring. A bolt connects the plate and a steel angle, which is restrained to the eaves beam edge. The shell to column connection is often built with a steel plate within the column and a bayonet with bushing linked to the shell, via a long bolt. This technology is used also to connect the partitions to the deck tiles; the steel angles and bolts connection is less frequent. It is worth to note that structural shell buildings are much less common than beam-column buildings. A few precast industrial buildings were under completion on April 6th, 2009, when the earthquake struck; so it was possible to verify the seismic behaviour of these structures under variable degrees of completion. 6.2 Damage and seismic performance analysis The response of the structural elements of the industrial buildings to the April the 6th 2009 earthquake was generally in accordance with their design level: no column collapsed, even though, in many cases a plastic hinge was observed, due to the high intensity of the seismic action (Figure 76). In some cases such plastic hinge was not observed at the column base, i.e. at the column-foundation joint, but even one meter above, where the longitudinal reinforcement decreases. Furthermore no 115 a Fig. 76- Plastic hinge in columns of industrial buildings: (a) FIAT garage at Pile; (b) building used for bovine-breeding at Fossa. b Fig. 78- Collapse of beams due to loss support of a building at Fossa used for bovine-breeding. ve the collapse of the beam due to support loss at the side without joint bar, caused by too large displacements, and the pounding between the beam and the column top fork (Figure 78). The phenomenon of the joint bar cover splitting can be also noted at the intermediate level of some two-storey precast buildings, where, as already written, the beam-column joint is on corbel. The same phenomenon has also characterised the collapse of some tiles. In this case, indeed, even where the joint had been fastened by a steel bar, the little thickness of the bar cover of the beam, also characterised by the lack of stirrups, collapsed, causing the tile support loss (Figure 79a). Obviously, such support loss easily happened where the tile-beam connection was not fixed and/or there was no connection between tiles; particularly unlucky situations were characterised by buildings in phase of assembly, where the floor slab, joining the tiles, was not made yet. Fig. 77- Effects of pounding between the cover tiles and the beam. a plastic hinge was observed in beams or tiles due to the increment of the vertical action. However, the damage of the precast industrial buildings should be well analysed; indeed, it was characterised by collapse of parts of the buildings, which, if the mainshock had happened during the working time instead of at 3 a.m., it would have caused victims. The static scheme of such structures is characterised by large deformability; consequently, the most of the observed damages of structural elements (made by reinforced concrete) depend on the relative displacements between the elements. Indeed, many cases of pounding between elements of the same structure were observed. Furthermore, pounding between adjacent buildings was frequent, in the case of both precast and cast in situ structures, due to the insufficiency of separation joints. In Figure 77 the pounding between the tiles and the beam of an industrial precast building placed at Bazzano is shown. Confirming the numerical studies performed in the last years, the connections represented the weak parts in terms of seismic performance of both old and new precast buildings. Some buildings have shown damages at the beam-column connection: the only observed case of precast beams collapse was due to the damage of such connection and to the following support loss. Indeed, as shown by numerical analyses, the splitting of the joint bar cover happened where the thickness was minimum. In other frames of the same structure, it is also possible to obser116 b Fig. 79- (a) Tiles collapse due to cover splitting and support loss of a FIAT garage at Pile (b). Collapse of perimeter panels due to the breaking of the angle stirrup or to the bolt head going out from the profile happened in a building used as material and machine deposit at Bazzano. However, the most important and spread damages of precast industrial buildings caused by the April 6th earthquake are those concerning the elements on the perimeter; indeed, the large damage of such elements, even though the structural typologies are different, associates precast buildings to the in situ cast ones. The top connection of the vertical panels to the side of the gutter beam, made by a profile drowned in the panel, bolt with nut and angle stirrup, in some cases gave way due to the angle stirrup breaking and/or to the bolt head going out from the profile (Figure 79b). This last phenomenon also caused the collapse of panels connected to columns by a profile drowned in the column and bayonet with bushing joined to the panel by bolt; some of these last connections, instead, collapsed due to the bayonet breaking at bushing RESEARCH - L’Aquila Earthquake Fig. 80. Local failure of the beam support. position. Some other failures where due to the going out of the whole profile from the panel where it was drowned. A better seismic response was shown by panels joined to the structure by angle stirrups and bolts. In the case of perimeter elements made by bricks, the seismic action determined their out of plane deformation, in many cases up to the expulsion of bricks and the consequent partial or total collapse of the perimeter element. Finally, among the carrying out mistakes, it is noteworthy, for precast structures, the local failure of the beam support. In Figure 80, a near collapse condition is shown, caused by the large column cover due to the fire protection provisions; indeed, due to such provisions, a volume of concrete without reinforcement works as beam support. Fig. 82- Pictures of the sili after the seism (Figure by G. Verderame, ISPRA, F.M. Mazzolani). 6.3 Non-building-like structures: the case study of the Sili Vibac at Bazzano The sili of the Vibac multinational (a chemical company which produces plastic films), located at Bazzano, close to Onna (Figure 81) represent an exceptional case of damage to steel constructions. They also represent an emblematic case of damage induced by the earthquake of April 6th. The sili are used for the storage of polypropylene pearls, and they were full when earthquake struck. Some sili collapsed, some other remained standing even though strongly deformed, both locally at some rings and diffusely (Figure 82). A more close visual inspection indicated that the collapses occurred for overturning due to the crushing of the base rings and the hopper. Moreover, along the sili height, deformations induced by buckling phenomena of the wall panels are apparent. In some cases an effect of pounding on the adjacent precast reinforced concrete constructions took place, the latter have achieved the partial failure of the infills, a Fig. 81. (a) Localization of the plant VIBAC in the Bazzano municipality (AQ). (b) Sili before the earthquake. RESEARCH - L’Aquila Earthquake b which have induced strong deformations of the shells of the sili. Such type of damages are a clear effect of the earthquake vertical component, whose importance they highlighted (Figure 82). The Vibac sili have a metallic structure. Generally for their conception sili have a very low structural weight, normally significantly lower than the weight of the contained material. Such a characteristic implies a very slender structure. It is evident that such structures are sensitive to both local and global buckling phenomena. In fact the most common failure mode is the instability of the wall panels due to the effects of the axial force in compression. Such actions are due to the friction between the silage material and the walls. The horizontal radial pressure, acting on the cylinder surface from the silage material, has a stabilizing effect against the buckling of the silos’ walls, giving rise to a tension stress field of membrane type. The distribution and intensity of the internal forces in every constituting part of the silos, the cylinder and the hopper, are strongly influenced by the material extraction behaviour, which in turn depends on the shape of the silo. The Vibac sili have an elongated shape typically used for the storage of plastic material. Therefore the predominant extraction mode is of the so called “mass” type, having the characteristic that the first material coming out is the one inserted as first in the silos, all the material mass is in movement at the leakage. In case of sili with a stocky shape, the extraction behaviour of “funnel” type prevails, it has the characteristic that a central tube forms in the material mass, which is sucked by the hopper. Such a “tube” is fed by the silage material all along the height, the part of material external to the tube rests during the leakage. In particular, in elongated sili, when completely full, along the height of the cylinder, from the higher ring bands the radial pressure grows towards 117 the base up to assume a constant value, then at the section variation, it reduces from the ring where the hopper is installed, and high stress levels arise. Obviously in case of empty or partially full silos the behaviour is different, the stabilizing effect of the radial pressure is lost in the empty part with a consequent abrupt variation of the critical stress. Pressure variations inside the silos depend also by the leakage of the material through the hopper, which causes a backwash effect and thus depressions. In order to control and regulate such an effect, sili are provided with pressure valves. Given that it is plausible that on one side the effect of the seismic vertical component provoked a sharp and important increment of the actions in compression in the sili walls, causing buckling, the contemporary seismic action in all the components accentuated the effect of possible asymmetrical distributions of pressure, due either to structural eccentricities, or to the silos filling method, or to the anisotropy of the silage material, causing a reduction of the stabilizing effect of the radial pressures themselves. Furthermore, buckling could also occur due to constructional imperfections at the joints between the coating ring bands of the silos, where joints in any case represent a discontinuity in the flow of longitudinal stress in compression, with high concentrated stress. The above mentioned considerations fully justify the collapse behaviour observed during the L’Aquila earthquake. 7. EMERGENCY MANAGEMENT FOR LIFELINES AND RAPID RESPONSE AFTER L’AQUILA EARTHQUAKE 7.1 Road Network ANAS S.p.A. is the agency that manages in the Abruzzo Region, as well as in the rest of the national territory, the state road network. The residual functionality and safety investigation of the road network were the first priorities identified by ANAS for the management of the first phase of the emergency. Physical and human resources were deployed to achieve the following goals: 1) rapid survey of the road network to ensure, at the largest possible extent, the regional mobility; 2) activation of emergency contracting procedures (“somma urgenza” agreements) to immediately begin, where possible, activities for the restoration of normal mobility conditions; 3) damage survey of the road-network components; 4) short term planning for the repair of damaged components. At the same time, physical and human resources were deployed in support of the Civil Defence for a first partial debris removal and for the excavations works necessary for the installation of relief campsites. It is worth mentioning that, further to the local resources, additional ones were used to manage the emergency. These resources were available from few ANAS’ Regional compartments differently located on the 118 a b Fig. 83- Impact of the earthquake on the road network: (a) SS80 “Gran Sasso d’Italia” road affected by rock falls, but featuring rock-proof tunnels. (b) Distribution of traffic management solutions (updated to 01/05/09) for the 61 road tracts affected by the earthquake (red = road closed; dark green = passable with limitations; yellow = alternating one way; light green = lane and velocity restictions). national territory, with an average daily commitment of 80 men and 70 vehicles. Rockfalls (Figure 83a) and landslides triggered by the earthquake and aggravated by the heavy rain that hit the area in the days following the event, were identified as the most problematic situations affecting the network mobility. However, the rock falls and landslides occurred mainly in mountainous areas around L’Aquila, while the main road network in the city was not affected by the aforementioned phenomena. In the urban area, mobility limitations were caused by debris following damaged and/or unsafe residential and monumental buildings adjacent to the roads. Immediate activities for the restoration of normal mobility conditions included: 1) removal of rocks and soil from the roads; 2) rock slope consolidations; 3) enhancement of soil slope stability. These activities were conducted employing, where possible, internal resources or activating, alternatively, emergency contracting procedures with external organisations. Securing of unsafe buildings adjacent to roads was carried out by firemen. Temporary traffic management measures were extensively implemented in order to minimize road closures; these measures included traffic flow restrictions; alternating one-way; lane and velocity restrictions (Figure 83b). The only significant damages occurred to the road network components were the structural failure of the viaduct “Corfinio” on the national roadway SS5 and the collapse of a bridge on the main road SP36 “Forconese”. No further significant damages were reported to the components of the road networks including the numerous tunnels present in the Region that performed well. The urgent need for a standardized and structured survey form to report damages and disruptions in the road networks was highlighted while performing safety investigation and damage survey operations. A rapid survey form and an ad-hoc procedure were therefore identified and formalised while the survey work was in progress. The timely information on the mobility conditions was a key component of the effective emergency management. The Civil Defence issued daily a report summarising road closures, mobility restrictions and repair RESEARCH - L’Aquila Earthquake works carried out in the road network. Using a Geographic Information System, GIS, the technical compartment of the Direction of Command and Control, Di.Coma.C represented this information in a cartographic format. Road closures and other temporary traffic management measures were overlaid to aerial Figuregraphs, technical regional maps, etc. providing maps that had a fundamental role in supporting many emergency management operations. As for the public information, emergency bulletins were regularly issued to update in real-time the end-users about the mobility situation in the Abruzzo Region. Communications and timely news were, as well, posted on the ANAS website. Once the firth phase of the emergency was managed, efforts and resources were concentrated, on one hand, to handle the modified traffic conditions in L’Aquila city due to the closure of the main road that ran through the city and, on the other hand, to respond to the new mobility requirements created by the relief camps, and by the construction of the provisional accommodation: Temporary Housing Modules M. A. P, and C.A.S.E project. 7.2 Water distribution network Gran Sasso Acqua G.S.A. SpA is the water provider for L’Aquila city and for 37 municipalities in the earthquake area. The organisation offers an integrated water service including potable water supply, sewerage and wastewater treatment. The G.S.A. has 3 major supply systems (Chiarino, Gran Sasso, Water Oria) in addition to some secondary ones. The water supplied is transported by a network consisting of approximately 900km of large diameter pipes and is stored in a huge number of tanks (about 200) that require continuous functional and hygienic monitoring and maintenance. The water is distributed from the tanks to approximately 100000 customers through a 1100 km distribution network made of quite old cast iron and steel pipes. The pressure inside the main pipeline network is quite high, reaching 30-50 atm., as well as in the distribution networks where it can reach 6-8 atm. Thanks to a remote control service and guided valves connected, through cables or wireless connection, to the main reservoirs and supply systems, it is possible to check the water flow inside the pipeline network and to manage partial or total opening/closing operations directly from the Gran Sasso Acqua headquarters. In particular, electromagnetic sensors, measuring input low pressure, and electromagnetic gauges (or “Clamp on”), measuring output differential pressures, are installed in the tanks. The remote control service allows furthermore the assessment of the water level in the tanks. The equipment connected to the remote control system revealed, on the RESEARCH - L’Aquila Earthquake morning of April 6, a significant and sudden change in the water flow for a main pipeline in Paganica. The immediate closure of the relative shutters for that pipe was operated directly from the GSA headquarters, before the technician team reached the affected site. The cause of the rupture was identified in the fault crossing the Paganica pipe. Because of that, the steel joint of the pipeline (diameter = 600cm; pressure 2530atm) slip-off, causing a violent escape of water (Figure 84a). A connection portion at the joint, however, was still grasped for a length of 6cm. In order to quickly respond to the emergency, the repair was limited to the welding of the pipes at the joint. Exception made for the aforementioned joint slip-off, no significant damage was observed to the main distribution and storage system. Following the repair of the damaged joint it was, therefore, possible to restart the provision of potable water for all municipalities administered by the G.S.A. SpA since the evening of April 6. As a lot of ruptures were expected in the minor water distribution system, in order to prevent flooding and deterioration in the buildings already damaged, the decision was made, not to restore the water distribution in L’Aquila historical centre and in the most affected villages. For these areas, the restoration of the water provision was gradually operated starting from the less affected zones and/or the zones with a strong need for reactivation; priority was given to the strategic services, secondly to the commercial and industrial activities, including the hotels to be reopened for the G8 meeting, and finally to the residential buildings classified safe, after the specific AeDES survey. The partial restoration of the water distribution was possible because of secondary networks and of a shutter system that allowed the exclusion of areas where the water supply was not urgently needed. A few days after the earthquake (19 April), due to a further slip of the fault, the welded joint of Paganica pipe broke, requiring a further repair intervention. The priorities identified in the second phase of the emergency management were, on one hand, the provision of the water service to the relief campsites and, on the other hand, the management of all the activities for restoring the water provision in L’Aquila City. To carry out the works for the water network connection in the relief campsites, the technical staff of the company (fully operative since the third day after the earthquake) was supported by the “Genio Civile” staff. On the other hand, the works for repairing damages and restoring the functionality of the water service in L’Aquila were operated, where possible, by the G.S.A. SpA technicians, or activating emergency outsourcing procedures for the most demanding operations. Relationships with external organizations have been unfortunately, nowadays, interrupted because of the financial difficulties that the company is undertaking due to the lack of income. Most commonly observed damages in the minor distribution system 119 a Fig. 84- Impact of the earthquake on the water distribution network: (a) Joint slip-off in a main water network pipeline in Paganica. (b) Repair on a cast iron pipe in a Paganica at the moment when some of the evacuated people were returning home. were the slippage/breakage of the joints and the breaking of cast iron pipes (Figure 84b). It is important to emphasize, however, that in large part of the “red zones” (damaged zones with prohibited access) the water network is still closed. Because of that, it has not yet been possible to completely estimate the extent and the spread of the damage suffered by the network1. Finally, it is worth mentioning that the drinking water purity and quality has been officially tested and certified daily since the early days after the seismic event. Because the G.S.A. official testing laboratory was severely damaged after the earthquake, this service was guaranteed via mobile laboratories of a neighboring water organization, C.A.M.. The third phase of the emergency management focused on the construction of the water distribution network and connections for the sites identified for the construction of the provisional accommodation: Temporary Housing Modules M. A. P, and C.A.S.E project. Both the design and the new construction of the reservoirs and of the distribution network for these areas were committed to external organizations and contractors. The costs for both the design and the construction of the new reservoirs and networks for the temporary accommodation were covered by the Civil Defence. The G.S.A. SpA will continue to be in charge of the management of the water provision for the temporary accommodation areas. 7.3 Wastewater treatment plant The technical visits at the wastewater treatment plants serving L’Aquila (AQ), in the resorts of Ponte Rosarolo, Pile and Arischia, and at that located in the City of Corfinio (AQ ) have shown that examined systems have similar technical characteristics, as they have the same practical functions. Each plant was equipped both with the structures necessary for the treatment of wastewater (primary clarifier tank, aeration tank, digestion tank, settling tank, thickener, sludge dewatering band press The water consumption was reduced by 30% as a result of water shut off into the ‘red zones’. Mobile water tankers were used to serve the relief camps in the first days after the quake. 1 120 b and chlorinator system) and with those for management purposes (buildings used as offices, rooms for technical equipment and laboratories). The facility in Ponte Rosarolo is located near the historical center of L’Aquila (42°20'18.10''N - 13°23'39.09''E). Structures were built the ’60s-’70s. The reinforced concrete digestion tank suffered partial collapse of a longitudinal wall (Figure 85a), several vertical cracks on a transversal wall and the separation of orthogonal walls at the edges (Figure 85b). The partial collapse of the wall also involved the steel pipe adducting wastewater that was connected to it. In buildings used as offices, local technological and laboratory equipment (RC framed structure) were also found cracks of both internal partitions and external walls. However, there were no evidences of damage to structural elements: the cracks detected on non-structural elements did not represent significant damages and did not prevent the use of building. The inspected facilities were therefore useable at the time of inspection, except the digestion tank that was useless. Due to this damage the tank has lost water and the plant were partially closed by reducing the disposal capacity of about 60%. The remaining functionality was still sufficient to face the demand, which was significantly reduced due to the large number of evacuated people (approximately 30,000), housed outside the city. a b c Fig. 85- Ponte Rosarolo Plant. Digestion Tank: (a) partial collapse of a longitudinal wall and of the pipe connected to it. (b) Detail of the detachment of the orthogonal walls at the edges. (c) Displacement of the pump in the control room. The structures of facility in Pile (42°21'3.25''N - 13°22'13.41''E), which is situated between the town and the industrial area of L’Aquila being the second plant serving the city, were realized in two different periods (’80s and 2000) with RC walls and slabs. Structural damages were not detected, only some damages to the partitions of local offices occurred. With regard to the older settling tanks, characterized by a circular cross section, a deterioration of the curbing RC beam was detected due to significant corrosion of the steel reinforcements. The inspected structures, therefore, were viable and fully functional despite the damages (of non-seismic origin), due to degradation of materials descending from a insufficient maintenance of the settling tanks. However, in the control room, a tube connected to the pump (not anchored) was damaged due to a displacement of 15 cm, Figure 85c. Finally RESEARCH - L’Aquila Earthquake it should be noted that this plant has been out of energy for three days after the earthquake, so it worked through its own backup generator. The plant located in Arischia (42°24'49.02''N - 13° 20'25.48''E) presents reinforced concrete structures with the exception of the circular tanks for leaching, consisting of circular walls of artificial masonry blocks connected with a RC curb at the top of the tank, and a gravity retaining wall. The structures date back to the ’70s with the exception of RC curb which was more recently constructed. Cracks on the walls of a distribution trap and damages to the retaining stone wall, which led to the partial obstruction of the hydraulic groove drain at the base of the tank, were observed. With regard to the circular tanks, one of the two rotating distributors was put out of service for damage to its support; the cracks found on some blocks of the structure were dated before the earthquake. Therefore, the inspected facilities were functional, although the restoration of the full functionality of the hydraulic facility required some minor rehabilitation and repair of the tank distributor. In any case, the age of the plant suggests a constant monitoring even after the remedial action. The treatment facility in Corfinio (AQ) situated not far from the center of the same town (42°7'25.74''N - 13°50'31.78''E) is a RC construction built in the ’90s. The central part of the longitudinal walls of the aeration tank, separated from lateral walls, shows a rotation very probably occurred in large part before the seismic event, as witnessed by the comparison of the positions of monitoring slides before and after the earthquake; such slides were applied two years before the event: the displacements due to the earthquake did not compromise the hydraulic seal of the joint, nor the functionality of the structure. A comprehensive analysis of the observed damages was carried out in relation to the position of each facility with respect to the epicenter of the earthquake of April 6th, 2009 (UTC 01.32 hours) and to the records provided by the National Network accelerometric (RAN) available. It can be observed that: - Ponte Rosarolo facility is located near the epicenter and close to the AQK accelerometric station, which recorded ground accelerations equal to 3.7 m/s2 equal to about 50% of the maximum value recorded for the same seismic event (station AGV - 6.6 m/s2); after the earthquake, the plant has shown damages to the tanks with rectangular walls larger than those found in circular tanks of the Pile plant, despite the geographical proximity. The structural behavior of the circular tanks was essentially better than that of the rectangular ones, mainly because of the lack of structural details ensuring effective connection between the orthogonal walls; - Arischia plant lies about 5 km from the L’Aquila accelerometric stations AQV, AQG and AQA, which recorded maximum ground acceleration values; even if distant from the epicenter (approximately 10 km), RESEARCH - L’Aquila Earthquake it has shown some structural damages; - The Corfinio plant was not damaged because distant from the epicenter (approximately 50 km): the maximum acceleration recorded by the accelerometers of Sulmona station (Sul) located near the plant, is indeed equal to 0.34 m/s2, approximately one-twentieth of the maximum recorded at AQV Station of L’Aquila. 7.4 Gas distribution network Enel Rete Gas S.p.A. is the gas provider for L’Aquila city and for other 5 municipalities in the earthquake affected area, namely Lucoli, Tornimparte, Ocre, Rocca di Cambio, Rocca di Mezzo. The gas is distributed via a 621 km pipeline network, 234 Km of that with gas flowing at average pressure (2.5-3 bar) and the remaining 387 Km with gas flowing at low pressure (0.025-0.035 bar). The medium pressure network is connected to the high pressure national one (namely SNAM network) through 3 reduction cabins while, about 300 reduction groups allow for the transformation of the gas transport pressure (2.5-3 bar) into the gas distribution pressure (0.025-0.035 bar). The gas network is mainly made of steel pipes, with an average internal diameter of intenal =125cm (external diameter external =139.7cm) and the joints are mainly welded. The first priority identified for the management of the gas network, in the first phase of the emergency immediately after the earthquake, was the timely securing of the network in order to avoid explosions, gas leaks and fires and to allow the emergency vehicles and the USAR teams to act in the safest possible way. To ensure this priority, the entire network managed by Enel Rete Gas S.p.A. in the affected area was shut off via the closure of the 3 reduction cabins. Thanks to this decision, and to the rupture of a pipeline near Onna (Figure 86a), it was possible to timely and significantly reduce the gas pressure and to avoid the occurrence of secondary effects. The subsequent closure of the 300 reduction groups ensured the full securing of the network in less than two hours after the earthquake. In the days following the event, the gas valves external to each residential building were as well closed. The pipeline damaged in Onna was replaced with a new one that was too rigidly connected to a reinforced-concrete support. It is worth highlighting that, as a result of the earthquake, the Enel Rete Gas headquarters in L’Aquila resulted unusable. Because of that the chief executive and the staff had to manage the emergency without the support of their data, software and maps. Luckily, the national society Enel Rete Gas has, at a national level, an integrated information system, including a data base and a geographical information system GIS. Making reference to the closest Enel Rete Gas headquarters in Teramo and Pescara, it was possible to reprint the maps and all 121 the documentation necessary to operate. The second phase of the emergency response was focused on the activation of the physical and human resources in support to the Civil Defence. The timely provision of gas to the strategic structures was the first priority identified and was operated via mobile reduction cabins and gas wagons. H24 shift were organized for the local technical and administrative teams, as well as for the teams coming from other areas of the national territory including the Enel Rete Gas national headquarters in Milan. In the first month after the earthquake, the daily commitment of physical and human resources resulted on average approximately equal to 70 men and 35 vehicles, including equipped trucks, gas wagons and gas-leak detectors. On the same time, activities for the reactivation of the gas provision were started. The reactivation of the shut gas network required to operate gradually restoring, first of all, the gas flow into the medium pressure network, secondly the gas flow in the low pressure network, up to each external valve pertinent to each residential building previously closed. Reactivation of the service was managed according to the following four steps: 1) seal verification; 2) nitrogen check; 3) repair of damaged pipes and/or valves; 4) reopening. In the seal verification phase, the detection of broken pipes and/or the possible joint slip-off was made, acting in the first instance, from node to node, and further segmenting the network when necessary. The material and equipment needed for the repair was immediately available from the integrated logistics system which Enel Rete Gas uses; actually, the material normally in storage in the Battipaglia interharbour to perform ordinary repairs and maintenance works, was simply diverted to L’Aquila. The adopted strategy ensured the remediation and testing of more than 90% of the gas network in three month time after the earthquake. The diagram in Figure 86b shows how, three months after the quake, it was possible to restart the gas distribution for all the end-users with a safe home, exception made for L’Aquila city. It is worth mentioning that the reconnection of the individual user supplies required, on one hand, the definition of the priorities to be followed and, on the other hand, the definition of the testing procedures to be carried out to certify the safety of the gas systems that were subjeca 122 ted to the action of the earthquake. As for the priorities, those identified by the Civil Defence were followed; namely, the service was provided first of all to the strategic buildings, secondly to the manufacturing and industrial plants, and finally to the residential buildings identified as safe after the AeDES ispection. As for the testing procedures, in accordance with the procedures used by Enel Rete Gas for routine checks, an ad hoc protocol was defined in collaboration with the Civil Defence and the Firefighter Department. It was decided to reconnect each single user following the fulfillment of four conditions: 1) safe dwelling (classified as A following the AeDES survey); 2) leak-tightness checking; 3) operative test of the equipment; 4) smoke test. It is worth mentioning that the Civil Defence fully covered the cost of the whole procedure to reconnect the individual users to the gas service and that a dedicated phone line (Line Amica Abruzzo) was specifically set up to facilitate and support the end-users in this operation. As a final note it is worth remembering that no damages were detected to the gas storage facilities. 7.5 Electric power distribution network and telecommunications It was reported that two substations serving the greater L’Aquila had damaged connections between a rigid bus and insulator, Figure 87a. That was due to shifting of the un-anchored transformers during the earthquake. Also due to sloshing of the cooling oil within the transformer, cooling oil pressure increased, and actuated the safety shut off feature to avoid costly damage. One of the transformers moved about 14 cm. In the distribution system, 30 posts were damaged causing severed links that resulted in service disruption. More than 180 pedestal type connection boxes were dislocated and severed cable connections at the termination lugs that resulted in localized power failure (Figure 87b). The Electric Power Control Center at L’Aquila sustained severe damage, both building and equipment, and it had to be moved to a temporary building in the yard of the building premise. It took three days to complete the move, while the essential part of the system was functional by 9 AM the day after the earthquake (Figure 86). Transformers in substations were not anchored. We noted that steel angles were welded on the b Fig. 86- Impact of the earthquake on the gas distribution network: (a) Onna (AQ), damaged pipeline. (b) End-user gas connections activeted on June 8, 2009 (Green = end-users that can be potentially reconnected; Bleu = end-user reconnected with respect to total that can be potentially reconnected). RESEARCH - L’Aquila Earthquake a b Fig. 87- (a) Damage to rigid connection of a transformer. (b) Typical damage to pedestal box. a b Fig. 89- One of the relief campite in L’Aquila set up by the Civil Defence. Fig. 88- (a) Steel anchors installed after the earthquake to avoid sliding of transformers. (b) Unanchored batteries’racks in substation. tracks that the transformers were supported to stop sliding, Figure 88a. This was done after the earthquake. However the steel angles seemed to be under sized. In the control house of substations, the batteries were not anchored or tied to the racks, Figure 88b. There was no batteries damage reported at these substations. Some locations were without power for three days, e.g. wastewater treatment plant. Telecommunication service performed reasonably well. It went off air for a couple of hours right after the earthquake. Cellular phones seemed to be the main means of telecommunication in this small community. Although there was no reported damage to the physical equipment and equipment building, we saw a number of temporary cellular sites deployed within the earthquake impacted areas. The increase of cell sites might have reduced the circuit overload that commonly occurs after an earthquake. Both Fire Fighters and Police used their own radio system as the primary communication tool. Cellular phones were also used to compliment the radio system. With a good backup power generation plant, their communication was not interrupted. The Fire department had three repeater stations, which were not damaged. A number of landlines were damaged or severed, as repairs were evident during REFERENCES C.F. Carocci, S. Lagomarsino, Masonry Buildings in the historic centers of the L’Aquila area, Progettazione Sismica, 2010. IUSS Press, Pavia. E. Cosenza, G. Manfredi, G.M. Verderame, Reinforced concrete buildings, Progettazione Sismica, 2010. IUSS Press, Pavia. M. Menegotto, Observations on precast concrete structures of industrial buildings and warehouses. M. Di Ludovico, G. Di Pasquale, M. Dolce, G. Manfredi, C. Moroni, A. Prota, Behavior of scholastic buildings after L’Aquila earthquake, Progettazione RESEARCH - L’Aquila Earthquake our investigation. Since tenants were not allowed back to their houses or apartments, most landlines were not used. Hence the demand on this circuit became much lighter. 7.6 Temporary housing The Italian government organizations and NGOs (Non-Government Organization) were to be commended on a great effort providing the victims with relief services and care. The military and fire brigade set up service camps to provided needed services to the victims. Some of the relief campsites provided the victims with Internet services in addition to daily necessities such as medication, food, and water. In general the victims were very satisfied with the relief service. Many residents were afraid to get back to their houses even when their houses (marked as class A or B) were not condemned, due to their fear of future earthquakes and the potential for damage to their homes. Temporary housing is scheduled to be completed by September 2009 (before winter arrives) for the victims, Figure 89. These houses will be on a base isolation system to protect residents from future earthquakes. There were more than 30,000 victims settling in more than 160 campsites. Sismica, 2010. IUSS Press, Pavia. C. Casarotti, A. Pavese, S. Peloso, Seismic Response of the San Salvatore Hospital of Coppito (L’Aquila) during the 6th April 2009 earthquake, Progettazione Sismica, 2010. IUSS Press, Pavia. B. Faggiano, I. Iervolino, G. Magliulo, G. Manfredi, I. Vanzi, Post-event analysis of industrial structures behavior during L’Aquila earthquake, Progettazione Sismica, 2010. IUSS Press, Pavia. M. Dolce, S. Giovinazzi, I. Iervolino, E. Nigro, A. Tang, Emergency Management for lifelines and rapid response after L’Aquila earthquake, Progettazione Sismica, 2010. IUSS Press, Pavia. 123 Reconstruction between temporary and definitive: the CASE project THE IDEA should actually be considered permanent, since they had a lifetime longer than 10 years (ignoring the fact that apparently between 10 and 50 years works can neither be called provisional, nor permanent). If then the provisional does not exist from a durational point of view, it would be useful to wonder whether it makes sense that it would exist looking at energy consumption, sustainable environment or pollution. It would also be useful to wonder whether buildings could be constructed with environmental characteristics and safety level similar to that required for permanent ones on a temporary basis and with cost per unit similar to provisional ones. If this should be the case, it would be logical to propose to build provisional houses with characteristics of the permanent ones. These ideas and others were discussed in the days directly following the Aquila earthquake with Guido Bertolaso for the political, administrative and economical aspects, with Mauro Dolce, Edoardo Cosenza and Gaetano Manfredi for the technical and scientific aspects. A first complete conceptual proposal, with 3D-rendering and preliminary calculations was submitted on April 16th, together with several comments. It was hypothesized to deliver the buildings for 3,000 inhabitants within 5 months, guaranteeing seismic safety by means of an hat is the time difference that distinguishes a temporary or provisionally home from a permanent or final? It is not easy to respond to this question, if you consider the seemingly enduring eternity of what in Italy is built with the objective to last for months, or for a maximum of few years. With reference to Italy, it is enough to consider what happened after the earthquakes of Belice and Irpinia (or even in Friuli), there is therefore no need to further elaborate the concept. On the other hand, we could refer to the technical code of 2008 [1], in which the nominal lifetime of a structure is defined as the number of years in which the structure – normally maintained – can be used for the purpose it was built for, it is indicated in a table and it needs to be specified in the design documents. It is interesting to note that the code only indicates a maximum for provisional works (10 years) and two minima for ordinary and important works (50 and 100 years respectively). If one sticks to these data, it should be concluded that all the provisional works that were constructed in the aftermath of the earthquakes that took place after WWII W 1 3 Fig. 1- One of the first sketches of the project illustrating the logic of the buildings constructed on isolated plates. Fig. 2- A plan sketch made by architects Ragazzi e Hoffer as to illustrate the logic of the infrastructure in a court open to pedestrians. 2 124 Fig. 3- One of the many 3D renderings used to illustrate design hypotheses. RESEARCH - L’Aquila Earthquake Gian Michele Calvi1 and Vincenzo Spaziante2 1 2 Eucentre Foundation - Centro Europeo di Formazione e Ricerca in Ingegneria Sismica, Pavia. www.eucentre.it Department of Protezione Civile, Rome. www.protezionecivile.it isolation system at the level of an urban block, and proposing elevate standards of living, technology and environment protection. The pursuit of these objectives, apparently impossible, was based on the construction of large isolated plates and the subsequent assembling of pre-fabricated three-storey living units. The need for the project to be as much as possible independent from local soil conditions and from the unknown construction technology (many different ones would have been necessary to meet the deadlines) became immediately clear. To this end it was stated the need of urgently identifying the possible building technologies compatible with the timing programme and the technical constraints, of selecting technical and commercial partners and of explo- ring the production capacity of the market. The time programme was defining in four weeks the date to open the construction sites, i.e. to start construction by mid-May, to deliver houses to 3,000 inhabitants by September. The economic analyses indicated an estimated cost of 120 million euro, VAT excluded, for 3,000 inhabitants, with a 20% uncertainty rate and without considering furniture, purchase of the terrain and photovoltaic installations. In preliminary calculations it was assumed to use friction pendulum devices [2-8], with a radius of curvature of 4m, a vibration period of 4s, a displacement capacity of about 300 mm, a friction coefficient between Fig. 4- Images used in the preliminary phase to illustrate possible technologies for the assemblage of the buildings. 3 and 5% and an equivalent viscous damping between 20 and 25%. The alternative of using rubber isolators was also taken into consideration, but appeared in this specific case to be less competitive, considering the relatively low axial forces and the large horizontal displacement demands. In the days immediately following, several aspects that would have permanently defined the project were discussed and clarified: - The reduction of each one of the isolated plates to about 20 by 60 m, suitable to sustain three-storey buildings with each floor surface of about 600 m2, with a capacity of about 80 inhabitants in 25 to 30 apartments. Plates of this dimension should allow an adequate flexibility in relation to the plane altitude conditions of the areas to use (at that RESEARCH - L’Aquila Earthquake 125 moment unknown) and the construction technologies, also unknown; - The definition of 150 as the approximate number of plates to construct and therefore of about 12,000 inhabitants to settle in; - The division of the intervention in numerous small villages, consisting of 4 to 20 plates and hence a number of inhabitants between 300 and 1600; - The definition of a serial timesheet in which a group of 30 plates should be finished about 15 days after the previous group, which implied a forecast of delivery of the apartments in 5 tranches for 2,400 inhabitants a time, with deadlines spread out between 30 September and 30 November; - The decision to manage the entire project directly, without intervention of a general contractor, setting up a non-profit technical structure that responds directly to the Civil Protection Department (DPC). It was thought that this way it would be possible to save substantial economical resources, mainly on general additional costs and to have a more accurate control on deadlines and quality of the project. THE ORGANISATION The definition of an operational, management and outsourcing structu- re, of personnel roles, activities and their interaction, time programme and milestones required several days of intensive work and was completed and formalised by May 8. The way the project is managed is very innovative with respect to the schemes that are normally adopted, and not only in Italy. In fact a single–purpose consortium was created (named ForCASE), formed by Eucentre (a non-profit foundation, centre of competence for seismic risk of the department of civil protection, founded by four public institutions and with a nature of ‘public company’ in Europe) and two construction companies, (ICOP and Damiani). The two companies agreed to operate in this context as non-profit entities and not to participate in any other reconstruction activity in Abruzzo. Their role would have been that of a technical office, and therefore to facilitate the consortium to act on behalf of the CPD as a general contractor, with the capacity to manage directly supplies purchasing, to coordinate activities on the construction site, to arrange and verify all accounting matters. Obviously, the consortium had as well the main task of carrying out all designing and construction management activities, under the responsibility and coordination of the authors of this article. Coherently with what has been briefly described, the operational organogram demonstrates five main areas of actions: two being related to design activities, Fig. 5- The personnel and work organization plan set up in the preliminary phase. 126 RESEARCH - L’Aquila Earthquake pletion of the project; - Finalisation and publication of call for bids; - Stipulation of contracts; - External checking and control; - Relations with institutions and obtainment of permissions; - Identification of the intervention construction sites, expropriations of lands and related activities. INFRASTRUCTURES AND ARCHITECTURAL DESIGN Fig. 6- A simplified version of the extremely detailed and complex time schedule that allowed daily overviews on each aspect of the project and the construction. two to management and accountancy activities and one to project coordination. In order to obtain maximum efficiency, in terms of time and costs, and to ensure quality control, three different operational modalities for contracting and execution of the work were identified: - For the activities of preparation of the construction site and infrastructure works, it was decided to mainly use local contraction companies; - For the foundation and isolation systems, it was opted to act directly as a general contractor acquiring materials and supplies, such as concrete, welded wire meshes, steel columns, isolation devices, formwork positioning, concrete casting, etc.; - For the construction of the housing structures it was decided to launch a call for bids that included final design and global construction, allowing the use of any building technologies compatible with the needs and available time, and selecting the proposals with the highest quality and the lowest cost. The economic quantification of the costs for the management of all activities was estimated based on the pure cost of the staff assigned to this temporary job (in months), on a monthly cost, in general between 3,000 and 12,000 euro (these are costs for the consortium, not net salaries), and on a sum to cover cost of accommodation and travel, that could in any case never exceed 3,000 euro per person per month. As all the activities would be executed within the non-profit framework that characterizes the Eucentre Foundation and the ForCASE consortium, the estimations were considered as a maximum not to be exceeded, while the real costs would be subjected to accountability checks. The Department of Civil Protection would directly execute, in cooperation with the consortium, all the activities related to: - Definition of Civil protection ordinances, possibly needed for the comRESEARCH - L’Aquila Earthquake The architectural project of a building unit, as briefly presented, favoured the development of different types of apartments, as a function of family compositions, which resulted in 109 different shapes after the selection of 16 contracting bids, as discussed later. Regarding the choices on infrastructure, it needs to be highlighted that a first guiding concept was that of placing the settlements in the neighbourhood of existing villages that had suffered severe damages because of the earthquake, to be able to relocate the people within their own territory, to preserve the close ties that people have with land and neighbours. This general principle was confronted with technical difficulties deriving from non-ideal geomorphic, hydrological and geotechnical circumstances of the areas, to finalise the best possible selection of the areas of intervention. Once the settlements had been defined and sized as a function of quantitative needs and land capacity, considering the dimensional and morphological characteristics of the location, the problem of existing infrastructures (roads, pipelines, sewing system, etc.) and of their improvement and integration had to be faced. Finally, the population indices could be defined, starting from figures between 100 and 150 inhabitants per hectare, for location in more rural or more densely populated areas. Such figures imply a rather sparse settlement typology, marked by large green areas. A final infrastructure index had been identified by assigning 30% of the land surface to services and facilities, such as leisure, sport, shopping centres or education and religious structures. Based on these premises the final urban design of the areas was completed, obviously combining the building units previously described (essentially consisting of three inhabited floors above a covered parking), also considering exposure to sunlight, valley and mountain views, steepness of terrain. Driveways and walking paths were kept separated to the maximum possible extent, generally locating vehicles roads on the outer skirts of each area, with access limited to parking lots and ground floors of the buildings, also used as parking. The walking paths were designed elimina127 Fig. 7- An example of the plans that were designed for the bids of housing construction, with an underground parking between the two plates. 128 RESEARCH - L’Aquila Earthquake Fig. 8- Location of the construction sites, all within the municipality of L’Aquila. Preturo Sassa Fig. 9- Examples of the urban plans for some site. Bazzano Coppito 2 Fig. 9- Examples of the urban plans for some sites. RESEARCH - L’Aquila Earthquake 129 ting all architectural barriers, connecting green areas and inhabited levels to road systems and parking lots with external elevators when needed. The final character of the new settlements tried to combine in an optimal way people needs, environmental and landscape requirements, use of existing infrastructures and construction of new ones, in an integrated vision. Later, another problem had to be faced, i.e. how to combine each one of the specific building units (at this stage 150, in 20 different locations) to each one of the 16 different typologies proposed by the companies who won the call for bids. Choices had to be made in relation to construction technology and material, external aspect, number of buildings awarded to each company, construction plan and schedule proposed by each company. Finally, considering the high environmental value of the landscape, the design and realisation of the green areas was again the subject of a public, international call for bids, where again cost, time and quality of the proposal were considered to select the winning bids. STRUCTURAL DESIGN Preliminary considerations The structural design of the buildings constitutes the fundamental element that allowed the development of the entire project and is extremely simple in its basic logic: two reinforced concrete plates, separated by columns and isolators, the lower one being in contact with soil and the upper one with the building. The plates were designed without knowing the local soil properties, nor the weight and plan distribution and structure of the buildings. Therefore for both aspects conservative assumptions were used, to be verified later. In a few cases, some potentially selected construction location had to be discarded because the soil properties appeared to be unsuitable. It should be noted that the two plates are characterized by similar flexural actions induced by gravity, if it is assumed a uniform distribution of the building load and of the soil reaction. Preliminary evaluations, based on a column span of 6 m in both directions (convenient for parking arrangements), lead to a required thickness of both plates of 500 mm. The weight of each building, with three floors of about 600 m2 each, was estimated in a maximum of 21 MN, with a consequent total maximum weight of slab, dead loads and building details of between 30 and 40 MN (or an average weight per column of about 1 MN). The first vibration period of the building can be estimated between Ts = 0.25 and Ts = 0.45 s, using the equation: Ts CsH0,75 130 in which H is the height of the building and Cs is 0.05 for wall structures, 0.075 for reinforced concrete frames, 0.085 for steel frames. It is however well known that equations of this sort tend to underestimate the real vibration period resulted from a secant stiffness to yield, that for the examined buildings could arrive at values between 0.8 and 0.9 s [9, 10]. Based on these considerations, the design period of vibration of the isolation system was selected in the range of 4 s. It was also preliminarily observed that even an extreme temperature variation of ±30 °C, leads to variations in length of about 8,5 mm on each side of the axe of symmetry, that would not induce excessive horizontal loads into the columns. Seismic action Seismic action and in particular spectral demands in acceleration and displacement are discussed in detail elsewhere in this volume [11]. Here it is however important to note that the fundamental parameter to be assessed for a proper design of the isolation system is the maximum displacement demand at a period of about 4 s. The spectra derived from the registrations of April 6th show generally displacement demand of less than 120 mm, with one exception, the AQK registration, in which spectra values are close to 250 mm. The code spectra for events with return periods of 1000 years, to be used for the design of the isolation system, have values of about 300 mm for soil type B and 400 mm for soil type E. These values can be significantly reduced in presence of energy dissipation, as a function of an appropriate equivalent damping, according to the factor: = 10 5+ where is the equivalent viscous damping value, that could be in the order of 10-15% for rubber bearings and of 20% for friction sliders. The values obtained from the reduction coefficients are between 0.6 and 0.7, with consequent estimations of displacement demands of about 250 mm for soil type E. For the non-linear analyses the code spectrum for vertical actions has also been considered, while for the building phases it was defined as a ‘construction event’ consistent with what indicated in addendum A of Eurocode 8, part 2 [13]. Such an event appeared to be consistent with registrations corresponding to a magnitude of 4.0, and was thus considered reasonable. While the demand in terms of acceleration was significant (in the order of ag = 0.10 on stiff soil), the displacement demand was negligible. Eight sets of spectrum compatible accelerograms have been used for non-linear analyses, derived from registrations made in L’Aquila (3 records), and during the events of Imperial Valley in 1979, Loma Prieta RESEARCH - L’Aquila Earthquake Fig. 10- Acceleration and displacement spectra of an event with a 1000 year return-period in L’Aquila, according to the Italian code [1], soil category B and E, damping 5%. in 1989, Northridge in 1994, Kobe in 1995 and Taiwan in 1999 (one for each of these events). Isolation system The design and the verification of the isolation system was carried out considering the possibility of adopting two different configurations, characterised by different devices, one based on the use of 12 elastomeric isolators, together with 28 multi-directional sliding pot-bearings and the other on the use of 40 isolators sliding on spherical surfaces, universally known as friction pendulum [FPS, 2]. Both choices are compatible with the project requirements, in different ways. Actually, the smaller dissipation capacity of the system with elastomeric isolators (estimated to be equivalent to 12% damping) with respect to the one with FPS isolators (estimated damping 20%,) requires a larger displacement capacity; in the order of 300 to 360 mm for the elastomeric isolators, versus 260 mm for the FPS, depending on the soil properties. Obviously other combinations may be possible, also related to the various displacement demands for isolators placed in different positions (because of the eccentricity of the loaded mass, even only accidental, the demand at the perimeter is larger than that closer to the slab central area). It was therefore allowed to bidders to propose different solutions, provided that they were respectful of design performances and input. The result of the call for bids, in which FPS systems were preferred, should not be considered as a general demonstration of superiority with respect to elastomeric devices, but rather as a consequence of the specific conditions of this project, characterised by relatively large horizontal displacement demands, low vertical forces on the devices and relatively low horizontal stiffness (as discussed, vibration periods of the order of 4 seconds were assumed). This was the reason why elastomeric isolators had to be coupled with pot bearings: the use of rubber bearings alone would have resulted in stiffness values incompatible with the requirements of the project. In the case of the FPS devices, the force corresponding to a displaced position is defined by the following equation: F = Mg + Mg d R ( ) Fig. 11- Comparison of several spectra recorded on April 6th on soil type B, code spectra for an event with a 1000 year return-period according code [1] and results of a recent research project (DPC-INGV-S5 [2]). RESEARCH - L’Aquila Earthquake In which Mg is the axial action (M is the mass and g the acceleration of gravity), R = 4 m the radius of the spherical surface, = 3% is the friction coefficient and d the displacement of the isolator. The least favourable conditions for the verification of displacement capacity of the isolation system versus the corresponding demand are likely to be those of a rigid and heavy superstructure, i.e. those of a large participating mass and deformations concentrated in the isolation system. With a configuration of this sort, the system global characteristics (40 pieces) resulted to be as follows. 131 Fig. 12- Force – displacement response of a system of 40 isolators and heavy superstructure. Fig. 13- Force – displacement response of the system considering axial force variation due to vertical acceleration and global interaction response [2, 4]. Effective stiffness, secant to the design displacement: Verification of slabs and columns The foundation and isolation plates have been subjected to numerous finite element analyses, that allowed to calculate the maximum bending and shear demand levels for several load combinations, to design the reinforcement, generally made by welded wire meshes to favour a fast positioning, and to verify the resulting action combinations with appropriate strength domains. Local verifications for loads concentration at the column ends were also performed on both slabs, considering the consequences of the substitution of a bearing as well. This operation was needed in hundreds of case during construction, when the isolators were not yet available at the time of casting the upper slabs. The columns have been designed and verified considering either the case of reinforced concrete and of steel, again to allow the use of various Keff = 14615 kN/m Corresponding period of vibration of the isolation system (note that in general heavier structures are also stiffer, therefore characterised by lower vibration periods): T = 2 M =3.29s Keff Corresponding equivalent damping: FPS = 2Mg = 0.201=20.1% Keffd Fig. 14- Examples of displacement histories for an elastrometic isolator (left) and for a FPS isolator (right), subjected to events with a 1000 year return period derived from 3 registrations in L’Aquila, compared with capacity circles of 360 mm (left) and 260 mm (right). 132 RESEARCH - L’Aquila Earthquake Fig. 15- Examples of reinforcement distribution in a section of the isolated plate. technologies and thus reducing the operation time. For the same reason steel columns were in general preferred, even if more expensive, using concrete only when no steel elements were ready to be mounted. Prescription for building design As already mentioned, the final design of the home buildings was left to the bidders, to allow the use of any building technology. However, the specifications to which the projects would have anyway to conform needed to be defined as to assure an appropriate safety level to the global structural system. The seismic demand was defined in terms of design acceleration of the building masses, calculated with reference to the maximum value of the ratio between base shear and weight of the building, obtained in the worst loading conditions, corresponding to those of a stiff building (T = 0.19 sec) with the lowest mass (1500 t). For analyses performed with accelerograms compatible with the design spectrum at a collapse limit state (SLC, return period 1000 years), the base shear always resulted less than 0.11 times the weight of the building. It was therefore prescribed to assume a design acceleration equal to 0.1 g to verify the buildings at a life safety limit state (SLV, return period 500 years). For the same conditions, the average inter storey drift resulted on the range of 0.1%, a value that certainly allows a full use of the buildings even after a high intensity event. Together with these extremely simple design data, a series of prescripRESEARCH - L’Aquila Earthquake tions on the characteristics of the buildings needed to be defined, in order to keep them within the parameters assumed for the analyses and therefore avoiding unexpected responses and jeopardizing the verification of plates, foundations and isolation system. A summary of these prescriptions follows: 1. The load resulting from the building structures shall not induce in any element of the slab – foundation system local actions larger than those resulting from a uniformly distributed live load equal to 50 kN/m2 (i.e. excluding the slab self weight). 2. The load distribution on the plates shall exclude concentrations potentially resulting in local collapses. 3. The maximum vertical action on a single bearing should be less than 2800 kN, either for the seismic load combination and for the gravity combination at the ultimate limit state, including the weight of the plate. 4. Bearings shall not be subjected to tensile forces in any load case. 5. The main period of vibration of the building (considered fixed at the base) shall not exceed 0.5 seconds. 6. The eccentricity between centre of mass of the building and centre of mass of the plate shall be less than 5% of the total length of the plate (57 m) in the longitudinal direction, and less than 10% of the length of the plate (21 m) in the transversal direction. 7. The maximum seismic mass of the building alone (i.e. without considering the weight and loads of the slab), calculated including self weight, dead load and the fraction of live load to be considered for seis133 Fig. 16- Example of bending stresses in the foundation plate, for gravity loads (1st row, moments around the two axes of symmetry in kNm/m) and for seismic loads (2nd row: maximum values, and 3rd row: minimum values). 18 Fig. 17- Example of local reinforcement of the foundation plate at column bases. Fig. 18- Example of bending moment – axial action strength domain, for a section of plate (at columns centres). Fig. 19- Example of bending action on the isolated plate during bearing substitution at different locations. 17 19 134 RESEARCH - L’Aquila Earthquake Fig. 20- Reinforcement in a foundation plate with concrete columns and steel columns with isolators on a casted plate. mic verification shall be less than 2100 t. 8. The buildings shall be designed in accordance with the technical code of 14/01/2008. It is accepted to represent the horizontal load equivalent to the seismic action by means of a static force vector, to be applied to the building floors, according to equations given in the code, assuming a design acceleration Sd (T1) of 0.1 g. CONSTRUCTION OF THE PLATES As previously discussed, for the production of the plates, the ForCASE consortium has directly taken the role of general contractor, with calls for bids for excavations, supply of concrete (initially about 200,000 m3, with peaks in delivery of more than 5,000 m3 per day, self compacting and aerated), supply of welded wire meshes (initially about 260,000 kN, in general with diameter 14 mm at 100 mm), supply of steel columns (initially 180,000 ton, diameter 800 mm), supply of isolators (initially 6,000 pieces, including assistance to positioning) and supply of casting forms (initially for about 336,000 m2) and on-site assistance for reinforcement positioning and pouring of concrete. All quantities were later significantly increased, since the number of buildings passed from 150 to 184. The prices per unit obtained through bidding have been the following: Contractors for the production of the plates with initial price and offers RESEARCH - L’Aquila Earthquake 135 Fig. 21- Rendering and floor plans of some buildings, proposed by the bidders. 136 RESEARCH - L’Aquila Earthquake Contractors, structure material, number of buildings offered and price per building Structure Walter e di • Self-compacting concrete • Welded wire mesh • Steel columns • Isolators • Forms and on-site assistance 82,55 0,49 2,09 1,427 91,7 €/m3 €/kg €/kg €/piece €/m2 CONSTRUCTION OF THE BUILDINGS A public call for bids was launched for the construction of the buildings; including final design. The 150 buildings to be built were grouped in 30 lots, each one of 5 buildings, allowing a bidder to present a proposal for a maximum of 10 lots. Depending on the final ranking of the offers, it might have been possible to have from a minimum of 3 contractors (in case the first 3 would each propose 10 lots) to a maximum number of 30 contractors (in case each one would have proposed 1 lot). The basic price for any lot of 5 buildings (about 160 covered parking spots, 3,000 m2 of outside pavement and 9,000 m2 internal living area) was fixed at 11 million euro. The evaluation of the proposals was essentially based on the proposed improvement of the minimum performance characteristics foreseen by RESEARCH - L’Aquila Earthquake the existing norms (that already represent a high standard). The maximum time allowed for completing each building from the availability of the upper plate was fixed at 80 days, a proposed reduction was also considered in the evaluation, together with a reduction of the proposed price. Following the presentation of the 58 proposals and an accurate review, 16 contractors were selected, with a total average amount per lot of about 10,500,000 euro, which means an offered price reduction of about 5%. On a total of 150 buildings, timber structures were proposed for 75 (50%), concrete structures for 45 (30%) and steel structures for 30 (20%). INFRASTRUCTURES, FURNITURE, ELEVATORS, MECHANICAL AND ELECTRICAL INSTALLATIONS, GREEN AREAS To complete the project it was necessary to prepare and launch other 5 groups of bids, in order to satisfy various needs: - The upgrading and integration of the external infrastructure (networks of any type) with the difficult problem of interacting with the 137 Fig. 22- Same complete buildings. construction sites. Twenty bids were released, one for each area of intervention, inviting companies located in Abruzzo and preferably in the province of L’Aquila. Five companies randomly sorted out were invited to bid for each site. - The furniture and supplies necessary to immediately use the apartments. In this case a public competition was set up, on four lots of about 1,000 apartments each. The foreseen time to assemble the furniture on site was 6 days from the moment an apartment would be finished. 18 companies presented an offer, with the following four resulting winners: Deltongo Industrie spa, Mobilificio Florida srl, RTI Europea spa – P.M. International Furnishings srl – Martex spa and Estel Office spa. The average price reduction offered was about 34%, which corresponds to an average cost for the interior furnishing of an apartment of 9,500 euro. It has to be underlined that the specifics of the bid requested the highest possible standards also for the electrical and mechanical equipment included in the offer, such as dish washer, washing machine, tv set, etc. - 309 elevators to connect the various floors of the buildings and 129 elevators to connect the buildings to the parking ground floor. This need derived from the specific choice of completely eliminating all potential architectonical barriers case, in excess of what compulsory for legal requirement. A call for bids was released for three lots of 146 elevators each; 12 companies participated in the competition. Marrocco elevators srl, ATI S.A.S. srl – Grivan Group srl, Schindler spa resulted winners with an average reduction of price of about 16%. - The opportunity of producing electric energy on site, collocating photovoltaic panels on the roofs. An estimate of about 45,000 m2 of roof surface was considered adequately exposed to sunshine and consequently another bid was released for the design, construction, mana138 gement and maintenance of a photovoltaic system, capable of producing about 4,500 kW. The call for bid assumed that there should have been no cost to the administration, and was based on technical merit and on one fundamental economical parameter, i.e. a yearly fee to be paid, as a percentage of the public incentives provided to favour the use of alternative, renewable energy sources. The winner and therefore contractor was Enerpoint spa, Ener Point Energy Srl and Troiani & Ciarocchi Srl., who offered to refund 9,01% of the incentives. - Finally, two last calls for bids were launched to complete the green areas, simply grouping the eastern and western construction sites. The offers should obviously include land preparation, grass, bushes and trees, walking and cycling paths, but also irrigation and drainage systems, external furniture, sport and leisure fields. 19 companies participated in the bid and contractors were selected on cost and on evaluation of landscape beauty, environmental sustainability and maintenance and management characteristics of the offers. The selected contractors were 3A Progetti S.p.a, which lowered the estimated price of 39% and the Sestante Consortium, that managed to offer a 35,16% reduction. WORK MANAGEMENT, QUALITY CONTROL, SAFETY MEASURES The extremely limited time available for the completion of the project required an extreme level of control and programming, with a continuous flow of information between engineering work management and construction companies and daily reports and checks. A coordination and management system was therefore set up, focusing on the definition of priorities and of the main activities consequently RESEARCH - L’Aquila Earthquake Fig. 23- Work in progress and completed works. RESEARCH - L’Aquila Earthquake 139 required and on the identification of potentially critical elements and work phases that could threaten the fulfilment of the programmed time schedule. As previously discussed, the work activities and their management and control were organised in five sectors, corresponding to production of the plates, buildings (including interior design and furniture), mechanical and electrical installations, infrastructures roads and green areas. For each technical sector a technical coordination structure was defined with a responsible for programming, coordination with the construction companies and management of works. The general timeline of the works was accordingly subdivided into the same five sectors. Daily updates on the work progress and comparison with the time planning guaranteed that each sector was closely monitored in terms of work progress, as well providing all technical personnel with an overview of the general picture, fundamental to manage the coordination between different sectors. The graphical visualization of the daily progress of the works resulted to be particularly useful for a rapid interpretation of the complexity of the data that needed to be managed. An idea of the large quantities of materials and labour that needed to be managed, can be obtained by considering the example of the foundation and isolation system, that on a daily basis needed an average concrete Fig. 24- Example of a global daily overview form. Fig. 25- Example of a production summary overview daily form (25 October, general overview on the left, production and delivery of plates on the right). 140 RESEARCH - L’Aquila Earthquake Fig. 26- Example of a daily report on the general development of the project works (19 October). Fig. 27- Example of a daily report on the general developments of the works in a specific area (19 October). RESEARCH - L’Aquila Earthquake 141 supply of the order of 5,000 m3, welded meshes and reinforcing bars for about 10,000 kN, about 200 steel columns (with a diameter of 800 mm), to be provided in general in 20 different construction sites. The efficiency of the team that was set up to program and coordinate the activities, allowed such a proper and precise forecasting of the work progress that all construction sites proceeded always on time and actually all works were completed ahead of time, despite of the difficulties inherent in the number of workers (more than 8,000 in some phases) and in the complex interaction between different work activities. An example of the time schedule programmed for the construction of the two slabs systems, with foundation and isolation, can be summarised in Fig. 23. Finally, the great efficiency of the team in charge of controlling all aspects of safety in the work process should be noted. The extremely detailed and continuous checks allowed the completion of hundreds of millions of euro worth of work in just a few months without any notable accident and with the appreciation of all external controlling institutions, from those aimed to assure workers health to the unions. THE COSTS The total cost of the project is split in the table below, considering the different category of work and giving the average cost per building, per apartment and per square metre of living space. The total cost of 655 million euro refers to a total of 164 buildings, while 150 were foreseen at the starting of the project and 184 were actually built at the end. Applying a criterion of linear proportion it can be inferred that the original 150 buildings would have cost 599 million euro, which is in line with the 700 million that were initially estimated, since the sums indicated do not include the cost for land expropriation and V.A.T. The cost of the double slab foundation system is compensated to significant extent by the value of the covered parking spots, each one of them have the size of a large garage box (6 by 3 metre). The number boxes exceed that of the apartments. It is thus reasonable to assume that the real cost of the foundation system is actually a fraction of that indicated in about 30,000 € per apartment. If a fraction of 30% would be assigned to the foundation itself, the cost per square metre of the living space should result to be less than 1,400 €, including foundations: a reasonable value, especially considering the compressed time of construction, that was made possible by a continuous work over the 24 hours, with three turns of 8 hours each, day and night and considering as well the very high quality of the buildings for aspects related to energy consumption, environment and detailing quality. Parametric costs of the whole intervention, based on 164,29 equivalent buildings, v.a.t. not included 142 RESEARCH - L’Aquila Earthquake It is interesting to note that the seismic isolation cost only about 1,5% of the total, or rather just a bit over 2% when only the building cost is considered. The modest cost of general and technical activities has to be noted, made possible by the way the project was managed, extensively discussed in the previous sections. The real share of the technical costs of the ForCASE consortium (design, management, security, etc) has been around 8 million euro, i.e. not much more than 1% of the total cost. The costs of the furniture includes everything, from TV sets to bed sheets. THE FUTURE At the moment this article is being completed (September) the last 20 buildings are being constructed, with a significantly lower cost because they are built in already inhabited areas. The decision of the Civil Protection Department to build additional houses was motivated by upgraded in the population census. It is foreseen that these buildings will be delivered within February 2010, with the possibility of notable anticipation if the meteorological circumstances should be favourable. The delivery of the houses started Tuesday 29 September with about 500 apartments and will continue at a pace of approximately 300 apartments a week. The property of the buildings will be eventually assigned to the city of L’Aquila who will be responsible for the management and maintenance based on pre-defined procedures, specified in detail in the project documents. Political and economical choices, with relation to the progress in the repair, strengthening and reconstruction of the buildings damaged in the historical centre and in the city outskirt, will drive the decision on rent costs and use of the new villages. The users of the houses are being carefully selected jointly by the city of L’Aquila and the DPC, taking into account the preferences expressed by the homeless people, parameters connected to the family situation (number of components, age, economical capacity, etc.) and the localisation of the original place of living. A prerequisite to be considered is that a family previous home should have been classified in the category ‘non easily to be repaired’ (type E and F in the classification of damage). Forecast of the number of apartments and beds available in function of the foreseen completion period (forecast of September 22nd, including the twenty buildings that had just been added, of which forecasts are cautious) RESEARCH - L’Aquila Earthquake 143 The houses will anyway become part of the city’s heritage and in the future it will be therefore possible to reuse them to host vulnerable categories of population (such as the elderly people) or to host students, a need particularly relevant in L’Aquila, where a significant fraction of the 25,000 students come from other regions. In the near future the availability of student housing at a controlled price could become a relevant peculiarity of the university, modifying its attraction capacity in a positive way. Those who have contributed to the success of the C.A.S.E. project: bani, Marco Vecchietti, Paolo Verri, Stefano Vitalini (site responsible for plates), Roberta Viviani Department of Civil Protection Giacomo Aiello (legal responsible),Emilia Aloise, Giovanna Andreozzi, Enrico Ardito, Vincenzo Ardito, Arianna Bertelli, Mariano Bonvegna, Angelo Borrelli (administration responsible), Fabrizio Bramerini, Cristina Capriotti, Maria Teresa Cartolari, Mario Cera, Claudia Ciccone, Pietro Colicchio, Alessandra Conti, Marco Conti, Maria Laura Conti, Chiara D’angelo, Antonella De Felice, Giulio De Marco, Giovanni Di Achille, Giovanni Di Mambro, Mauro Dolce (technical responsible), Riccardo Fabiani, Maria Cristina Ferroni, Salvatore Fiengo, Claudia Fiore, Mariasilvia Gianneramo, Beatrice Guerra, Gerarda Iannarone, Federica La Chioma, Luisa Marinaro, Lucia Palermo, Francesca Paneforte, Ada Paolucci, Roberto Pesolillo, Giancarlo Piccione, Patrizia Picuti, Immacolata Postiglione, Giuseppina Sementilli, Vincenzo Spaziante (general coordinator), Tiziana Tarduini, Vergilio Tidei, Fabiola Toni, Angelo Vici. CASE Consortium Fabio Aldrovandi, Francesco Ambrosi, Francesco Amici, Maurizio Ardingo (responsible for construction safety measures), Luciano Baglione, Giovanni Bastianini, Paolo Battegazzore, Giuliano Bellini, Maria Teresa Dolores Bertelegni, Federica Bianchi, Saverio Bisoni, Gaia Boggioni, Filippo Bonali, Barbara Borzi, Maria Benedetta Bossi, Matteo Bottari, Vittorio Bozzetto, Roberto Brandimarte, Piero Burba, Maurizio Calderari, Andrea Caligari, Maura Castellani, Gian Michele Calvi (project leader, designer and construction director), Salvatore Caroli, Christian Caroli, Paolo Caroli, Francesco Ceribelli, Antonio Coccia, Andrea Colcuc, Oliviero Comand, Massimiliano Cordeschi, Filippo Dacarro, Michele D’Adamo, Alberto Damiani (responsible for building construction), Pietro Damiani, Edi Danielis, Simonetta Di Nicola, Maurizio De Santis, Pasquale Di Marcantonio, Dante Di Marco, Stefano D’Ottavio, Ettore Fagà, Mario Fanutti, Carlo Florio, Pierluigi Fontana, Fabrizio Frau, Renato Fuchs (organisation coordinator), Nicola Gallina, Marco Gasperi, Fabio Germagnoli, Federico Gianoli, Daniele Gimnetti, Sergio Giordano, Stefano Grasso, Carlo Lai, Massimo Lardera (responsible for infrastructure), Ignazio Locci, Giuseppe Lombardi, Mauro Maganetti, Giovanni Magenes, Claudio Maggi, Carlo Magni, Fabrizio Magni, Michele Magnotti, Gabriele Mantini, Antonio Marcotullio, Paola Marotta, Sara Martini, Emanuele Meago, Paola Migliazza, Enrico Misale, Marta Molinari, Federico Monutti, Matteo Moratti (site responsible for structures), Vincenzo Pane, Vincenzo Paolillo, Alessandro Papale, Carmine Pascale, Pierluigi Pascale, Moreno Pavan, Fausto Pedetta Peccia, Gianfranco Peressutti, Edoardo Peronace, Michele Pescina, Paolo Petrucco (site responsible for plates and infrastructure), Piero Petrucco, Nereo Pettenà, Dario Pietra, Roberto Pitolini, Federica Polidoro, Alessandro Pollini, Stefano Pozzi, Salvatore Provenzano, Bruno Quadrio, Nadia Rizzardi, Enzo Rizzi, Fabio Roiatti, Cristiana Ruggeri (responsible for mechanical and electrical installations), Gaetano Ruggeri, Mario Rusconi, Daniele Sambrizzi, Valentina Scenna, Matteo Schena, Michele Schiabel, Paolo Scienza, Fabiola Sciore, Roberto Scotti, Domenico Sgrò, Martino Signorile, Danilo Marco Siviero, Luigi Spadaro, Davide Tagliaferri, Piergiuseppe Tamburri, Alessandro Tosello, Stefan Trenkwalder, Roberto Turino (site responsible for buildings), Diego Ur144 Checker team, administrative aspects Giovanna Andreozzi, Maria Laura Conti, Alessandra Conti, Michele D’adamo, Giovanni Di Mambro, Salvatore Fiengo, Giorgio Grossi, Emilia Aloise, Mariano Bonvenga, Carlo Bordini, Cristina Capriotti, Maria Teresa Cartolari, Carluccio Codeghini, Fabio Compagnoni, Dario Compagnoni, Massimo Criscuolo, Antonella De Felice, Giuseppe Fasiol, Maria Cristina Ferroni, Arturo Furlan, Achille Gentile, Alessandro Greco, Gerarda Iannarone, Giuseppe Ianniello, Giovanni Infante, Ettore Iorio, Paolo Marchesi, Luca Pagani, Lucia Palermo, Roberto Pesolillo, Salvatore Provenzano, Rosario Romano, Gianni Strazzullo, Fabiola Toni, Daniela Ursino, Michele Villani Checker team, structures Edoardo Cosenza, Gaetano Manfredi, Claudio Moroni, Paolo Pinto (President), Paolo Zanon (assistenti: Massimo Acanfora, Claudio D’Ambra, Antimo Fiorillo) Companies and organisations Excavations: CO.GE.FER. s.p.a.; Midal s.r.l.; P.R.S. Produzione e Servizi s.r.l. Concrete: Colabeton s.p.a.; Società Meridionale Inerti SMI s.r.l. Steel reinforcement: La Veneta Reti s.p.a. Steel columns: A.T.I. Edimo Metallo s.p.a. /Taddei s.p.a.; Cordioli & C. s.p.a.; Formwork and assistance: Consorzio Edile C.M. Gruppo Bison; Sacaim s.p.a.; Zoppoli & Pulcher s.p.a. Isolators: Alga s.p.a.; FIP Industriale s.p.a. Buildings: A.T.I. Consorzio Stabile CONSTA s.c.p.a./Sicap s.p.a.; A.T.I. Donati s.p.a./Tirrena Lavori s.r.l./Dema Costruzioni s.r.l./Q5 s.r.l.; A.T.I. Eschilo Uno s.r.l./COGEIM s.p.a./Alfa Costruzioni 2008 s.r.l.; A.T.I. Ille prefabbricati s.p.a./Belwood s.r.l.; A.T.I. Impresa Costruzioni Giuseppe Maltauro s.p.a./Taddei s.p.a.; A.T.I. Iter Gestione e Appalti s.p.a./Sled s.p.a./Vitale Costruzioni s.p.a.; A.T.I. COGE Costruzioni Generali s.p.a. /Consorzio Esi; Consorzio Etruria s.c.a.r.l.; Consorzio Stabile Arcale; Cosbau s.p.a.; D’Agostino Angelo Antonio Costruzioni Generali s.r.l.; Impresa di Costruzioni Ing. Raffaello Pellegrini s.r.l.; Meraviglia s.p.a.; Orceana Costruzioni s.p.a.; R.T.I. Ing. Armido Frezza s.r.l./Walter Frezza Costruzioni s.r.l./ Archilegno s.r.l.; Wood Beton s.p.a. Furniture: Del Tongo Industrie s.p.a.; Estel Office s.p.a.; Mobilificio Florida s.r.l.; R.T.I. Europeo s.p.a./ PM.International Furnishing s.r.l. Infrastructure: CO.M.AB. Appalti Pubblici e Privati s.n.c.; Codimar s.r.l..; Codisab s.r.l.; Conglomerati Bituminosi s.r.l.; Facciolini s.r.l.; G.C.G. s.r.l.; I Platani s.r.l.; Impresa Edile Di Cola Michele; Ing. Armido Frezza s.r.l.; Molisana Inerti Conglomerati s.r.l.; Produzione e Servizi s.r.l.; Ridolfi Idio e Figli s.r.l.; San Giovanni Inerti di Pietro Mascitti s.r.l.; Valentini Costruzioni s.a.s.; Elevators: Marrocco elevators s.r.l., ATI S.A.S. s.r.l./Grivan Group s.r.l., Schindler s.p.a.; Photovoltaic panels: R.T.I. Ener Point s.p.a./Ener Point Energy s.r.l./Troiani & Ciarrocchi s.r.l.; Green areas: R.T.I. 3a Progetti/Gsa s.r.l./O.Ci.Ma. s.r.l./Bellomia-Sebastianini-Euroengineering s.r.l., Consorzio Sestante. Demolition: CODISAB SRL, A.S.M. s.p.a.; Connections to external pipeline networks: ENEL Rete Gas, ENEL Energia, GranSasso Acqua.1 RESEARCH - L’Aquila Earthquake REFERENCES 1. NTC (2008) - Norme Tecniche per le Costruzioni, D.M. 14/01/2008, Gazzetta Ufficiale 04/02/2008, Italia. 2. Zayas V., Low S. (1990) - A Simple Pendulum Technique for Achieving Seismic Isolation, Earthquake Spectra, Vol. 6, No. 2. 3. Almazan J.L., De la Llera J.C. (2002) - Analytical model of structures with frictional pendulum isolators, Earthquake engineering and structural dynamics, Vol. 31, 305-332. 4. Calvi G.M., Ceresa P., Casarotti C., Bolognini D., Auricchio F. (2004) - Effects of axial force variation on the seismic response of bridges isolated with friction pendulum systems, Journal of Earthquake Engineering, Vol. 8, SI1, 187-224. 5. Christopoulos C., Filiatrault A. (2006) - Principles of Passive Supplemental Damping and Seismic Isolation, IUSS Press, Pavia. 6. Priestley M.J.N., Calvi G.M. (2002) - Strategies for repair and seismic upgrading of Bolu Viaduct 1, Turkey, Journal of Earthquake Engineering, Vol. 6, SI1, 157-184. 7. Tsai C.S. (1997) - Finite element formulations for friction Pendulum seismic iso- lation bearings, International Jour. for Num. Methods in Engineering, Vol. 40, 29-49. 8. Wang Y., Chung L.L., Liao W.H. (1998) - Seismic response analysis of bridges isolated with friction pendulum bearings, Earthquake engineering and structural dynamics, 27, 1069-1093. 9. Priestley M.J.N., Calvi G.M., Kowalsky M.J. (2007) - Displacement based design of structures, IUSS Press, Pavia. 10. Crowley, H. and Pinho R. (2004) - Period-height relationship ofr existing European reinforced concrete buildings, Journal of Earthquake Engineering, Vol. 8 (SP1), 93-120. 11. Crowley H., Stucchi M., Meletti C., Calvi G.M., Pacor F. (2009) - Uno sguardo agli spettri delle NTC08 in relazione al terremoto de L’Aquila, capitolo 1.7 in questo volume. 12. AA.VV. (2007) - Definizione dell’input sismico sulla base degli spostamenti, progetto S5 INGVDPC, http://progettos5.stru.polimi.it. 13. Comité Européen de Normalisation, Eurocode 8 part 2 (2006) - prEN1998-2, CEN, Brussels. Here and in the next pages, some pictures of the completed buildings areas. RESEARCH - L’Aquila Earthquake 145 146 RESEARCH - L’Aquila Earthquake RESEARCH - L’Aquila Earthquake 147 148 RESEARCH - L’Aquila Earthquake RESEARCH - L’Aquila Earthquake 149 150 RESEARCH - L’Aquila Earthquake RESEARCH - L’Aquila Earthquake 151 CONSTRUCTION Italian High-Speed Network A special focus on concrete structures he new Italian high-speed Network, due to the needs of increasing the capacity of the actual railway operating lines, nearly doubling the actual number of trains running daily, and decreasing travel time, has involved in the last fifteen years, large engineering resources, construction skills and strict planning, managing organization, railway engineers supervision, apart from the necessary economical huge investments. The main characteristics of the new lines and the strategic choices from the infrastructural and structural points of view are presented in the next chapter. The new lines are designed according to the national code for the design and construction of railways bridges [1], and to the most advanced technological standards in order to achieve the safest conditions of service, speed and interoperability with operating railways and with the European highspeed lines of railway transportation of passengers and freight. More than 90 % of bridges and viaducts of the new high-speed lines are realised with simply supported spans of prestressed concrete (PC) decks, so attention will be paid on their typical structural solutions. Simply supported composite steel and concrete spans, few continuous bridges and some special structures (arch bridges and the cable-stayed bridge over Po River [2]) compose the remaining part. Main concepts of durability of concrete structures required in the design of railway bridges are then focused. Construction processes are then described, taking examples from the latest viaducts with PC decks. Finally, main concepts in the design of continuous PC bridges are outlined. T Fig. 1- Italian New High-speed Network: lines under design, construction and the operating line Roma-Firenze, built in the 70’s-80’s for a design speed of 250 km/h [3]. 154 Strategic choices Traffic analysis carried out on existing Italian railway network at the end of the 1980 remarked the following needs: quadrupling the main passenger transport routes, upgrading and increasing freight transport, reducing time of travel for passengers trains, integrating Italian network with European network. So, the first infrastructural choice was the realization of a new mixed passenger/freight high-speed network with a close integration with existing lines and with interchange centres (interports, ports, airports). The close integration with the existing conventional network will produce an increase of freight transport capacity on the “historical” lines, clearing the existing network from the long distance passengers traffic, and an increase of freight traffic using new lines during specific time bands (usually at night). The choice of a mixed traffic meant low ruling gradients (less than 12 ‰) and heavy design loads (SW0/SW2) adopted in the new Italian standard for railway bridges [1]. For this reason, the standard was rewritten in 1995, then revised in 1997.The old standards had been written 50 years before and were related only to conventional lines.The Italian standard for railway bridges [1] has introduced LM71 (passengers traffic as showed in leaflets UIC 702 and 776-1), SW/0 and SW/2 (heavy traffic) models of loads according to ENV 1991-3: Actions on structures, Part 3:Traffic loads on bridges (Ed. 1996). These new standards are in perfect agreement with the European Technical Standards for Interoperability of the trains in the European High-speed Network. One of the main prescriptions asks for a structural design respectful to all prescriptions for seismic areas (at least III category – the minimum considered in the 1996 Italian seismic code), even in no-seismic areas, apart from Sardinia. A proper standard was written and recently revised for the design of railway bridges to be built in seismic area [4]. It deserves to be pointed out that many no-seismic areas became recently seismic, in the latest proposals of codes, giving interesting confirmation to the conservative railways code approach. According to general seismic design principles, the adoption of special rules and technical details is requested to guarantee a minimum ductility of the structure, and it has direct consequences on the care for the details of reinforcement design of piers and foundations. Two main characteristics of the applied national code [1] are the concepts of train-track-structure dynamic interaction and train-rail-structure static interaction. The dynamic interaction analysis is evaluated to check the safety of the train and the comfort of the passengers, with an analysis of the following parameters: all decks for high-speed railway must respect the limit value of 2.5 as maximum dynamic amplification of static deflection (“impact factor” j real=j dyn /d stat) and the value of the vertical acceleration at deck midspan, induced by real trains running at different speed (from 10 km/h up to 1.2 maximum speed of the line), must be lower than 3.5 m/s2. For standard simply supported beam or continuous bridges with total length shorter than 130 m, a simplified analysis can be adopted according CONSTRUCTION - Civil engineering Works to Annex A of [1], with a preliminary check of flexural - frequencies of vibration modes: the simply supported prestressed concrete decks always respect the limit values specified in [1], being first flexural mode frequency between 4 and 8 Hz. For non-conventional structures, as arch bridges, cable-stayed bridges, etc., a “Runnability” analysis is required.The analysis has to consider all dynamic characteristics of the system: railway structures, suspension system of the vehicles, rail fasten system etc., track and wheel irregularities. The static interaction analysis studies the effects on rail and bridge structure due to variation of thermal conditions in the structures, to the longitudinal forces associated to braking and traction, and to the longitudinal displacements due to vertical loads. For simply supported prestressed concrete decks, which respect a maximum length of 65 m and small variations of the longitudinal stiffness of piers and foundations, a simplified method can be adopted as indicated in Annex B of [1]. In any other case, it is necessary to analyse advanced Finite Element models to evaluate these effects. The analysis has to check rail stress limits with maximum value of compressive stress 60 MPa and maximum value of tensile stress 70 MPa, the relative displacement between deck bridge and the rail, and the forces acting on the bearings. Also reliability under service conditions is required: comfort limit state has to be verified for a maximum midspan deflection with the load of one LM71 load model, increased with dynamic factor. This deflection must not exceed l/2400 for design length of the span l<30m, l/2800 for 30m<l<60m and l/3000 for l >60m. Maximum deformability of structures under train load is checked to keep the contact rail-wheel safe and stable: deck torsion, rotation at supports and horizontal deflection have to be evaluated. The limits of deformation of the structures are similar to those pointed out in the same Eurocode, and are widely respected by common simply supported spans. Special attention has been put in the concepts of durability of structures for railway bridges, introduced in [1]. As the subject deserves wide illustration and details, a full paragraph has been devoted to the scope. As high-speed network is designed for the use of long welded rail, the structural system for the viaducts must avoid rail expansion devices. In all highspeed network, only along the Milano-Bologna line, for the crossing over Po River, composed by two continuous bridges and the cable stayed bridge [2], two joints in the rails have been necessary to keep the expansion length within allowable limits. Other rules and prescriptions for design and construction are taken into consideration in [1] and are illustrated in the following paragraphs. All these are finalised to have low costs of maintenance of the infrastructure, to minimise the irregularities of the track and to reach a high performance level in the field of the durability and reliability of the system. Simply supported prestressed concrete bridges Simply supported spans of prestressed concrete deck realised more than 90% of the new lines. It is undoubtedly a traditional choice of Italian Railway Company (Ferrovie dello Stato – FS) for ordinary viaducts: to better fit CONSTRUCTION - Civil engineering Works with long welded rail, to avoid rail expansion devices, to ease maintenance operations and minimize maintenance costs. Besides, this solution is usually preferred in those cases when bridges have to be designed in areas with compressible soils or in river channels. Figures and statistics of this paper are based on more than 600 km long high-speed lines. Attention will be paid to double-track decks, with a distance between tracks of 5.0 m, designed for a train-speed of 300 km/h, and for both heavy and passengers traffic load models [1], with rails on prestressed concrete sleepers on ballast.They count nearly 2300 spans of simply supported prestressed concrete bridges, and they are composed of nearly 6400 precast beams or monolithic decks. In order to reach this frame of prestressed concrete decks, analysis will concern the structural characteristics such as use of pre-casting, tensioning systems, bearings, expansion joints, all durability issues as multi-layer protection systems, monitoring, methods of construction and costs. Deck The pre-stressed concrete elements are realised with both pre-tensioning and post-tensioning systems.The post-tensioning systems are always designed with bonded internal cables, even if Italian standard for railway bridges [1], generally speaking and under severe controls, allows also external post-tensioning. According to [1], post-tensioning cables composed by bars should be preferred for viaducts along railways with electric traction of direct current, and both solutions with cables composed by strands or bars can be used in structures for railways with electric traction of alternating current as the high-speed network. In [1], special attention for durability and limiting or avoiding cracking of concrete is introduced: undoubtedly most limiting verifications deal with limitation of maximum compressive stresses and, especially, strong limitation of tensile stresses during construction and final conditions. In particular, no longitudinal tensile stress in PC structures is admitted, with maximum design loads and both Allowable Stress or Limit States methods of verification. Besides, cracking of concrete must be verified towards no decompression limit state for verification under track equipment, where inspection is not possible. The experience of existing railway lines with concrete structures with possible beginning of corrosion of the reinforcement and spalling of the concrete, which leads to easier access to the pre-stressing tendons for aggressive agents, has been translated into design prescriptions.The required concrete cover to reinforcement, tendons and pre-tensioned strands has been increased, compared to Italian standard for design of structures. Minimum concrete cover thickness is required to be 3 cm for PC decks, increased to 3.5 cm under track equipment, at least one external diameter of duct in case of post-tensioning, and 3 strand diameters in case of pre-tensioning. Mix design of concrete for PC deck has to respect a 0.45 water to concrete ratio, a S4÷S5 concrete consistency class of at least 45 MPa characteristic cubic strength. A quality assurance system and testing before and during every casting operation reveals the quality of mix design, which is recognised as an important factor for life and durability of PC structures. Bearings and expansion joints Under simply supported railway bridges, only one kind of bearing is generally present: spherical bearings with polished stainless steel and PTFE plate. 155 Italian High-Speed Network With this kind of bearing, rotations can occur till ±0.0167 rad in all directions, in order to place the bearing without inserting packings. In order to avoid parasite forces arising with only one train on a double line bridge deck, a new kind of fixed bearings has been studied: it has a special device which controls horizontal stiffness. The cover of expansion joints are realised with dielectrical elastomeric cushion joints, composed by neoprene reinforced with vulcanized steel plates.They allow fast bearings changing with a maximum differential lifting of 50 mm between decks, operated by hydraulic jacks between deck and pier cap (all simply supported or continuous decks have to pass this design verification) without any operation under rails. Actually, the use of mechanical devices instead of resins avoids disease to daily train in case this operation becomes necessary. On pier caps and abutments of every bridge span, reinforced concrete or steel devices (“stroke end device”) are required in order to avoid deck slipping out of pier cap and falling, because of accidental breaking of fixed bearings e.g. in case of devastating earthquakes.There are pillows of reinforced neoprene where decks may hurt against these provisions and their maintenance or changing operations has to be assured by proper design. Italian standard for railway bridge bearings and cover of expansion joints requires these devices underpass preliminary homologation tests led by F.S. technicians, through prototypes testing, in order to assure quality of every single component and of the final assembled products. Piers and foundation Piers have usually circular or rectangular, full or empty, cross-sections, while foundations are usually realised with plinths with large diameter reinforced concrete piles. In case of piers in riverbed, even if empty structural sections are adopted, low class of concrete is always poured inside till the river maximum level, in order to avoid unexpected water inside. As previously mentioned, in order to increase structural safety, all bridges are designed considering at least low seismic condition: it focuses the designers' attention especially on reinforcement details, very important for piers and piles. Good number of stirrups and loops for longitudinal bars and concrete confinement, use of hooks for good stirrup behaviour, limitation of maximum compression stress in pier concrete, no junction or superposition of longitudinal bars in the length of 3 m from foundation, etc. are consequences of above-mentioned prescriptions. The minimum reinforcement areas for both piles and piers is fixed to the 0.6 % area of concrete section, and spirals are admitted as stirrups in reinforced concrete piles only if welded to longitudinal bars in every intersection. Type a Weight of one precast box: 455 ton (33.1 m) 19% of total length of viaducts 915 ton one deck weight (34.5 m) 343.196 ton is total weight Type b Weight of single precast V beam: 88 ton 40.5% of total length of viaducts 650 ton one deck weight (25 m) 698.476 ton is total weight Fig. 2- Two box girders deck (a) and four precast V beams and cast in situ slab (b). beams with post-tensioning cables. In Roma-Napoli line it was also realised with two V-beams and cast in situ slab. Transversal beams are usually prestressed with straight cables of strands or bars. The number of transversal beams is prescribed in [1]: for a deck with two or more girders, at least two prestressed concrete transversal beams have to be designed out from supports and more in case of decks longer than 25 m. Strands getting out from the heads of the box girder are cut, isolated and protected with the use of dielectric resin. Decks' deformability is largely verified for comfort limit state: maximum deflection at midspan for Type “a” is less than l/5600. Type “b” is composed by four precast V-beams and cast in situ slab: actual maximum length is 33.6 m. Beams are steam cured, pre-tensioned with longitudinal steel strands and Typical cross sections The most common cross-sections of prestressed concrete decks are showed in Fig. 2, 6 and 11; in the following, a brief description of main features is presented for each typical cross-section. Type “a” is a box girders deck, spanning till 34.5 m, generally composed by two precast box girders, prestressed with longitudinal steel strands and connected with small second step casting in the slab and with transversal 156 Fig. 3- Prestressed concrete V beam (type b) in stocking area, Torino-Milano line. CONSTRUCTION - Civil engineering Works transversally connected with cables in transversal concrete beams; it is the most common deck: it has been chosen for 40.5 % of total length of simply supported prestressed concrete deck. The maximum deflection at midspan is largely verified: for type “b” spanning 25 m (22.3 % of length of all prestressed concrete decks) it is less than l/6000. Because of the prescription of complete absence of tensile stress during construction and life of the bridge, and of the large amount of pre-tensioning strands in V-beams, the technique of strand passivation for few metres along beam ends, over supports, has been introduced for a portion of strands, in order to reduce even minimal cracking on heads of the beam. From an aesthetic point of view, shortest spans of box girders (both V-beam or cellular deck) can be put at a disadvantage, because in [1] a free height of at least 1.6-1.8 m inside box girder is prescribed to be left to ease inspection, leading to relevant height of the deck even for short span bridge. Anyway, these spans can be agreeably inserted in case of viaducts with short piers. Type “c” is a single box girder deck, realised in two different ways and Fig. 5- The first precast 25m long single box girder (Torino-Milano), during launching operations. sversal beams or second step castings of concrete in head anchorages of tendons in the required transversal beams, which always become visible with time. Anyway, in some case of grillage deck, when perspective had to be improved, concrete noise barriers have been usefully adopted, covering second step casting or empty spaces on pier-cap between decks for inspection. Type “e” is composed by four precast I beams and cast in situ slab. Beams are longitudinal post-tensioned with cables composed by strands with straight and parabolic profiles. Some are tensioned in precasting plant, then, after completing the bottom slab and tensioning of transversal cables, the second part of longitudinal cables is tensioned over the piers and slab is casted. Longest span of type “e” is also the longest span for simply supported prestressed concrete decks: 46.2 m. Type “e” has the advantage to manage precasting and launching of one beam at time instead of full deck, so requiring simpler technology, but, at the same time, the operation of assembling formworks and casting connection of lower slab and transversal beams, and the huge transversal posttensioning (no. 47 4-strands cables for 46.2 m long deck) may put it to a disadvantage. Type “f” is the original Modena viaduct: the first case of lower way U deck for high-speed lines; the double track is realized by two independent decks, piers and common foundation. It has two single track decks spanning 31.5 m, and a total width of 18.4 m; each deck is pre-stressed with 20 longitudinal post-tensioning tendons of 12 strands. 566 km of corrugated plastic Type c Weight of single precast deck: 567 ton (25 m) Weight of cast in situ box deck: 1043 ton (43.2 m) 11% of total length of viaducts 173.856 ton is total weight Fig. 4- Box girder (type a) on carriers towards launching operations, Milano-Bologna line. lengths: 25 m long precast box girder with longitudinal pre-tensioned steel strands on Torino-Milano line (3.78 km long Santhià and 1 km long Carisio viaducts) and cast in situ post-tensioned deck spanning 43.2 m (2.8 km long Padulicella viaduct) on Roma-Napoli line. Type “d” is adopted in 5.1 km long Piacenza viaduct: 150 precast spans with two cells and curved transversal profiles. It is a single monolithic box girder of 970 ton, with a maximum length of 33.1 m. Piacenza viaduct has been provided with 119 km of corrugated plastic ducts and it represents the first application of electrically isolated disposals for the anchorages of 12 and 19 strands for longitudinal post-tensioning cables. Compared to the grillage decks, the monolithic decks have the aesthetic advantage of clean prospects and even deck sides, without tranCONSTRUCTION - Civil engineering Works Type d Weight of single precast deck: 970 ton 7.2% of total length of viaducts 145.500 ton is total weight Fig. 6- Box girder with single cell (c) and Box girder with two cells (d). 157 Italian High-Speed Network Fig. 7- Piacenza viaduct precast deck, 33.1 m, in stocking area. Fig. 8- Perspective of curved profiles of Piacenza viaduct. Fig. 9- Four precast I beams in stocking area, from Roma-Napoli high-speed line. Fig. 10- Four precast I beams launched over pier caps, from Milano-Bologna high-speed line. Type e Weight of single precast I beam: 270 ton (46.2 m) Weight of four I beams deck: 1.400 ton (46.2 m) 7.6% of total length of viaducts 137.274 ton is total weight Type f Weight of single precast deck: 689 ton 15% of total length of viaducts 446.472 ton is total weight Fig. 11- Four precast I beams and cast in situ slab (e) and Lower way U deck (f). Fig. 12- The first one of 750 Modena precast decks in stocking area, Milano-Bologna line. Fig. 13- Beam head of Modena precast deck in stocking area, Milano-Bologna line. ducts is used. In Milano-Bologna line this structural solution for prestressed concrete deck is used for 10.7 km long double track viaducts. It is also used in Junctions, for another 3.33 km of single-track, for a total number of 767 precast spans. In particular, Modena viaduct is the longest viaduct of all high-speed lines, with its length of 7.1 km. The structural solution of lower way deck has been usefully adopted to minimize structural height plus noise barrier, because the noise barriers became a part of the structure. Modena system of viaducts is one of the few cases, where aesthetics and environment impact have so strongly led the process of design and the solutions for structural and construction needs, in order to have quite original deck, unique in its kind. Durability 158 Through periodical inspection of old railway lines and particularly of the Roma-Firenze railway line, an analysis of the most common defects on bridge deck have been made in order to work out new guidelines of design and construction of the high-speed lines. Inadequate access for inspection, leaking of waterproofing system of the expansion joints between decks, insufficient cover, not efficient bearings towards maintenance operations as lifting of decks in order to change bearings, or reduced space to insert hydraulic jacks on pier-caps, etc. have been found as most frequent defects. These circumstances led to the introduction of new or more detailed prescriptions in the Italian standard for railway bridges [1], in order to guarantee better behaviour of structures with time, care for durability of concrete structures, tensioning cables, system of waterproofing, devices for good drainage and anything else whose purpose is to ensure the overall longterm integrity of bridge structure. But, first of all, great care is put to inspection ways to check the conditions of the structures and medium-life elements. Access for inspection All bridges are designed assuring access for inspection, testing, maintenance and possible replacement of medium life elements. It must be always possible to walk over bridge decks because a width of min. 50 cm on both sides is left for maintenance people. Inside cellular deck or closed box girders, as previously mentioned, a minimum height of 1.6-1.8 m must be always guaranteed; fixed stairs from deck to pier cap must be provided every 3 spans or 100 m and from piers to the ground every 500 m, for viaducts longer than 1000 m. Over pier cap it must be always possible to pass from one deck to the following and stairs or landings are fixed to ease the movements of maintenance people. Finally, it must be also possible to inspect bearings and stroke end devices or to operate in case of replacement of bearings or neoprene pillows, so a free height of 40 cm is left between lower side deck and top of pier-cap. Drainage It is a key issue about durability; deck slabs are provided with provisions for good drainage and great attention is put to design, testing and layout of all devices. Drainage of expansion joints is assured by a flashing tray of elastomeric material stuck with resins to slabs’ ends, in order to avoid leaking over piers and to drain water out of deck sides. Over bridge deck, in order to protect from atmospheric agents, a thick layer of waterproofing is extended, also beneath the footways. In case of sensible prestressing system, pre-stressing strands or post-tensioning cable system just beneath deck slab or critical drainage system (types “a”, “c”, “d” and “f”), a sprayed polyurethane waterproofing of 3 to 5 mm is extended. Checks are been carried out on site for adhesion and thickness by F.S. technicians. This surface treatment has proven to be very long life cycle performant. In post-tensioned concrete structures, deck anchorages are to be avoided on deck slab; anyway, for all anchorages, design has to avoid leakage to get access to anchorages, providing protection against leaking expansion joints, as water drips. Post-tensioning tendonsThe grouting of the sheaths of prestressed concrete bridges is always done with vacuum technique with a depression of 0.2 bar during injection. It is standard for prestressed concrete deck with post-tensioning tendons because grouting has been recognised as a key CONSTRUCTION - Civil engineering Works operation to ensure durability of prestressing. Usually, it is difficult to ensure complete filling of the ducts: pathology teaches us that the prestressing tendons are more vulnerable in the case of post-tensioning than in the case of pre-tensioning. Vacuum injection should avoid having air bubbles near high points of tendon profile and in case of simply supported structures high points coincide always with anchorage locations. Besides, all end caps are filled with grout and surrounded by concrete held in place by reinforcement, with noshrinking concrete and the same compressive strength as deck concrete. Latest tendencies about durability of anchorages are High Density Polyethylene ducts with plastic end cap left in concrete and the use of electrical isolated tendons as a further protection of the tendon and mean for monitoring: in Milano-Bologna and Torino-Milano railway lines, a large scale application of plastic ducts and electrical isolated tendons has been undertaken. Italferr has taken the Technical Report from fib (fib 2000) and Swiss guidelines on electric isolated tendons (2001) as standards, asking for mechanical and chemical tests, field measurements to be undergone; a System Approval testing has to be conducted on site on every first application of a prestressing system. Deck equipment Every bridge deck is furnished of railings on both sides, anchorages of noise barriers for their future assembly, electric traction poles, stairs to pier cap and from piers to the ground. Great attention has been put to deck equipment: every steel finishing is installed with linkages electrically isolated from deck reinforcement and connected to a dissipative end in the earth for safety reasons. Stainless steel is preferred for the most sensible connections. Electrical isolation of structures Every bridge deck is electrically isolated through isolated bearings and expansion joints, from piers and the other decks, besides, in order to prevent and protect bridge reinforcement against strain currents, few disposal for every deck are disposed in an accessible area in order to measure strain current and isolation grade after traffic activation. This is probably a minor problem on high-speed line decks, but felt deeply in every normal bridge deck and in the Junctions of high-speed line. Whenever problems of potential differences should arise, structures will be electrically connected to earth or a cathodic protection should be eventually adopted. In case of post-tensioned structures, all anchorages are electrically connected (when no electrical isolated tendons is adopted) and the terminal is drawn out of the structure in order to provide eventually in the future the same provisions as for deck reinforcement, otherwise, in case of pre-tensioned decks, the head faces of the beam are protected with synthetic dielectrical resins. Monitoring and Maintenance In order to improve deck’s behaviour knowledge and control it with time under the influence of external agents (environmental actions, traffic loads, seismic events or exceptional hydrogeological events), a complex monitoring system integrated with the highspeed line has been designed. At least one section (deck, pier, foundation, piles) per viaduct and, in case of long viaducts, one section every 1000 m is instrumented: it means a large CONSTRUCTION - Civil engineering Works number of strain-gages, inclinometers, thermocouples, instrumented bearings, load cells, foundation settlement meters, piezometers etc. Seldom accelerometers are provided in order to evaluate dynamic response of the structures also in case of seismic actions. Maintenance program of high-speed lines is essentially based on maintenance actions followings inspection visits: in the code 44/c of Italian railways about lines maintenance [5], frequencies, ways of inspection and following check schedules are prescribed. These check schedules have the double aim to check the safety of structures towards train traffic, and to keep memory of time evolution of the behaviour of structures. According to [5] every year a program of action has to be adopted to eliminate anomalies encountered in structures or to face critical situations. Construction process As all bridge designers know, construction process may deeply influence design choices, also in case of pre-cast prestressed concrete beams, which compose the majority of our new bridges and viaducts: the construction scheduling, the technologies of lifting, transporting and lowering over the piers are investigated. To improve the overall quality of the infrastructure design and production, a quality control system is implemented during both the design phase and the construction phase. In the following, main construction features of each structural solution are described in the text and representative construction phases are showed in the pictures. Precast beams and cast in situ slab When talking about construction features we must divide our decks in few major families: one of these is the precast V or I beams with cast in situ slab.The short spans of four V-beams deck of type “b” (Fig. 14-15) and the shortest I-beams of deck of type "e", of an average load of 100 tons each, are the only ones which can be casted and pre-tensioned in pre-casting plant, moved on ordinary roads and led on site, where each beam is lifted to its final position. Then predalles or formworks are assembled, reinforcement is laid and the concrete slab is casted over the piers. As it is not necessary to pass over completed decks, ordinary roads can be used and there’s no obliged sequence of spans’ layout, this method of construction has the important property of flexibility; besides, relatively simple technology is necessary for its realization. Cast in situ box girder In the only case of single box girder Padulicella viaduct (Fig. 16), the deck is casted and pretensioned over the piers on selflaunching formworks and special casting equipment is used. To accelerate the production, the reinforcement cage had to be pre-assembled, transported and lowered in the formwork before casting. Two box girdersTwo precast box girders, each weighting about 450 tons, are precast and prestressed with pre-tensioned strands, then lifted over the viaduct where they are transported by two small carriers on tyres, towards launching operations (Fig.17). Deck is completed over piers, with second step casting in central slab and in transversal beams, then transversal strands cables are tensioned and grouted. The case of two precast box girders is half way between the pre159 Italian High-Speed Network Fig. 14- Precast V beam lifted up from stocking area. Fig. 16- Reinforcement cage transported in the formwork over the piers, Padulicella viaduct, Roma-Napoli. Fig. 15- Precast V beam towards final position over the piers. cast beams and the full-span pre-casting. Actually launching operations similar to those of full span pre-casting are necessary, but second step casting and transversal prestessing in transversal beams are needed. As the full span precast decks of the following chapter, these box girders are realized in a plant near the viaduct: all these plants are dismantled at the end of the works. Full span precasting In those cases when much more spans had to be built in short time, full span pre-casting has been preferred (Figs. 18-21). According to this process of construction, decks are totally pre-casted; no post-tensioned transversal beam is needed to complete the deck over piers. Afterwards, one by one they are moved towards launching operations. A «carrier» and a «support beam» always compose the launching system. The carrier slowly moves on tyres or steel wheels, lifts a stored beam, and transports it along the viaduct, moving on the placed girders. The device for transport forms an integral part of the device for the launching of the girders: the carrier drives then into a second steel girder called support beam, suspends the beam over its final position. The support beam is drawn back and the beam is lowered. With four or six bearings, hydraulic jacks or load cells are used in order to check weight load distribution, and then the beam is lowered on its final bearings. 160 Fig. 17. Launching operations of a box girder of S. Rocco al Porto 2 viaduct, on Milano-Bologna line. Fig. 18- Modena precast deck lifted and transported on tyres from stocking area, Milano-Bologna line. The use of pre-assembled reinforcement cages, independent casting lines and several formworks, different phases of tensioning operations and the use of storage areas for cables’ injection can speed up the process. On the other hand, if for any reason one deck has to be stopped in the stocking area, the process may stop for days. So this method doesn’t have the flexibility pointed out before for beams and slab decks. CONSTRUCTION - Civil engineering Works Fig. 22- Concrete, Reinforcement and Strands loads of different typologies of deck versus span length, (figures based on highspeed lines: Roma-Napoli; Bologna-Firenze; Milano-Bologna; Torino-Milano). Fig. 19- Piacenza precast transported on steel wheels from stocking area towards launching, Milano-Bologna line. Fig. 20- Modena precast lower way U deck during launching operations, on Milano-Bologna line. and reinforcement and prestressing steel amounts for each span, apart from few exceptions. Talking about deck load, first exception to be mentioned is Modena deck: as a single way deck it results heavy solution for a double line, but, at the same time, the simple “U” profile, easy to manage from a design point of view, doesn't cause similar examples of exception for the load of reinforcement and prestressing steel. Decks composed by beams can never minimize the use of steel because of their transversal connections, while single box girders seem, even if based on few examples, to behave more efficiently. Anyway, many other factors are to be considered in the choice of the best structural and technological solution for a new railway bridge deck: they may depend on construction method, workmanship factors, number of spans to be built and required time scheduling of construction, as previously mentioned. Another factor for evaluating the solution for a bridge deck is, of course, its aesthetic impact: even if mentioned at the end of the analysis, in some case it has strictly led the design choices. Generally speaking, the span length over deck height ratio can be considered one of the simplest measure to evaluate the grade of slenderness: in case of simply supported PC decks, it ranges between 9 and 12; even for short spans, the prescription of minimum free height inside cellular decks causes small ratio. Anyway considering that the average piers’ height is not more than 7÷8 m, usually long spans are not used with very short piers because of aesthetic reasons too. Monolithic decks are to be preferred to precast beams decks because transversal beams are always impacting on the sides' prospects. Finally, a good example of agreeable bridge aesthetics in the field of simply Fig. 21- Santhià precast single box deck during launching operations, Torino Milano line. Peak cycle is variable: Modena viaduct has a casting and launching speed of two precast girders per day. Others, as Piacenza viaduct, have the design of the spans and of the casting yard centred on a target peak cycle of two double-track decks per week. Comparison between a-f typologies Last data about PC simply supported spans are in Figg. 22 and 23 where the most important figures about double-track decks of the new high-speed lines are presented. There’s good uniformity between different typologies dealing with deck load CONSTRUCTION - Civil engineering Works Fig. 23- Span length distribution (e) among the a-f typologies (figures based on high-speed lines: Roma-Napoli; BolognaFirenze; Milano-Bologna; Torino-Milano). 161 Italian High-Speed Network supported spans was obtained changing the structural solution: the Savena arch bridge on Bologna-Firenze high-speed line, designed to overpass Savena River. It is composed by reinforced concrete arch, steel hangers connected by spherical hinges to the 2930 ton prestressed concrete deck, with both transversal and longitudinal post-tensioning cables. It has the lowest height under rails (1.60 m) for a span length of 62.5 m. Continuous prestressed concrete bridges In few cases, for riverbed or embankment crossings, highway or railway over-flyings, multi-span continuous PC bridges have been designed.The most common choice for a single long span in a sequence of shorter simply supported spans is the composite steel and concrete deck, from about 40 m to more than 70 m, but they result often strongly impacting with longer PC viaducts perspective, consisting generally of a single exception, with different structural height, colour and side profile. In other case, the need to harmonize approach viaduct spans length to a bigger structure as arch bridges or cable-stayed bridge has led to multi-span PC viaduct with spans of 60÷70 m. According to ref. [1], all previously mentioned design and durability prescriptions have to be applied to continuous bridge: access for inspection of every pier cap is more stringent and difficult to obtain, leading often to complex systems of stairs and landings around central supports. Besides, every deck has to be verified for lifting in case of bearings' replacement and it may result structurally demanding, while, from a technological point of view, it can require a specific design to give disposals for 20% additional prestressing in each span longer than 40 m. PC continuous beams are often casted in phases, it is quite rare to have a single casting operation for two or three spans and in [1] precast segmental construction is forbidden. For cast in situ segmental PC bridge, a minimum reinforcement area through every joint of 3.0% area of concrete cross section of deck is prescribed and minimum compressive stress of 1.0 MPa (rare load combination, also during construction stages) is expected from design. In the following, because of lack of space, only two examples of continuous Fig. 24- First balanced cantilever of Left Embankment viaduct, approaching cable-stayed bridge over Po River. 162 PC bridges are mentioned. The first example is composed by the river embankments approach viaducts to the cable stayed bridge over Po River [2]: five spans on the left side for a total length of 260 m (Fig. 24) and three spans on the right side for a total length of 130 m.The decks are three cells box girders, built by balanced cantilevers from central piers: a couple of segments at one time is casted in situ and post tensioning cables are tensioned. Then the remaining gaps of 1.0 m long are concreted and post-tensioning cables are laid in the spans to join together, two by two, the cantilevers. For the Italian State Railways, this is the second example of this kind of structure and method of construction (the first one being built for the RomeFirenze line). The second example refers to the Modena continuous bridges to overpass two rivers, a highway and a railway Junction in the Modena System of Viaducts, for a total number of nine single-track continuous beams. All nine bridges have span lengths of 40-56-40 m, the same outer crosssection of the lower way U decks of Modena simply supported spans (type f), with higher webs on central piers.They are built in three segments casted in situ e prestressed with 40 mm bars, coupled at the end of each segment. Two methods of construction were experimented for the same structural solution, because of the different environmental conditions: for two of these beams, the segments were casted on a formwork, scaffolding from the ground with two temporary bars for each joint, in order to help the partial structure during construction conditions.The other seven obtained the same effect with a formwork hanging from steel box beams (over Panaro River) or truss beams (over Secchia River and on Brennero highway, see Fig. 25) and the end support of the beam applies nearly the same reaction of the temporary bars. Conclusions This paper has described the strategic choices and the most relevant structural and infrastructural features for the design and construction of the new Italian high-speed railway network. Most topics concerning simply supported prestressed concrete decks for new high-speed lines have Fig. 25- Continuous PC beam of Modena viaduct over Brennero highway, Milano-Bologna line. CONSTRUCTION - Civil engineering Works been analysed, while some information on continuous PC beam have been introduced at the end. Deck with precast beams and cast in situ slab is the most common choice due to its flexibility (type “b” is actually the most used structure for bridge decks) but full span pre-casting is the most important future trend. The mentioned principles of design, the so-called multi-layer protection system, the method of construction, which deeply influences design choices, and the tendency to experiment models and tests before every first realization, have been recognised as strategic factors for good results in design, construction and management of railway infrastructures. References [3] [1] [4] [2] Italian standard for railway bridges: Istruzione F.S. n. I/SC/PSOM/2298 del 2.6.1995 “Sovraccarichi per il calcolo dei ponti ferroviari - Istruzioni per la progettazione, l’esecuzione e il collaudo”, Final review 1997. Petrangeli, M. P.,Traini, G., Evangelista, L., Della Vedova, M.The cablestayed bridge over Po River: design and construction. Proc. of the 2nd International fib Congress, 5/8 June 2006, Napoli. CONSTRUCTION - Civil engineering Works [5] Figures, deadlines and picture in §1.Introduction are drawn from www.tav.it, revision April 2004. Italian standard for railway bridges in seismic areas: Istruzione FS 44/b “Istruzioni tecniche per manufatti sotto binario da vostruire in zona sismica”, Final Review 14/11/1996. Italian standard for railway line maintenance: Istruzione FS 44/c “Visite di controllo ai ponti, alle gallerie ed alle altre opere d’arte del corpo stradale: frequenza modalità e relative verbalizzazioni”, Final Review 16/02/1994. 163 HS railway cable-stayed bridge over the Po river Italian High-Speed Network Project HS railway cable-stayed bridge over the Po river Location Bologna Milano High Speed Line near Piacenza Client T.A.V. S.p.A. Concessionaire for the design and construction of the Italian HS system for RFI Design Prof. Ing. Mario Paolo Petrangeli Structural engineer Prof. Ing. Mario Paolo Petrangeli Architects Prof. Ing. Mario Paolo Petrangeli Management Contractor CEPAV UNO- Syndicate formed by ENI per l’Alta Velocità General Contractor A.S.G. Scarl – Syndicate formed by Aquater, Snamprogetti, Grandi Lavori Fincosit 164 Winner A.I.C.A.P. Award 2009 for Structural Concrete Works - Category “Civil Engineering” The new railway linking Bologna to Milan is part of the High Speed Lines Italian network. It crosses the Po near Piacenza in a section where the river is usually about 350 m wide, up to 1 km between the main embankments. The bridge will be 1200 m long, 400 m to cross the ordinary riverbed, an obliquity of 22° resulting between the tracks and the river. Two approach viaducts, respectively 6 and 4 km long, complete this work, the most important of the whole line. Four main spans of 96 m were proposed in the preliminary design to satisfy the navigation requirement, and two solutions, both with prestressed concrete decks, were selected after a first study, but the competent Authority for the Environment insisted in eliminating the central pier, a 192 m main span resulting for that. It is one of the longest prestressed concrete railway span in the world operated at a speed up to 300 km/h. Three types of structure are present in the crossing in addition to the standard 14 km long approach viaducts placed outside the upper banks: the cable stayed bridge, 12 simply supported decks on the right bank and two continuous p.c. box girders necessary to overpass the main embankments. The decks are subdivided in such a way that two joints in the rails are necessary to keep the expansion length within the allowable limits. This is the only exception along the jointless HS Railway Italian Network. The relevant part of the crossing has a 192 m central span and two 104 m long side spans. The deck is a p.c. continuous box girder with the fixed point at one tower, sliding bearings at the second tower and at the transition piers. Expansion lengths of 296 and 104 m derived from this arrangement of the bearings, joints in the rails so being required.The height of the cross section is constant and equal to 4,5 m (L/42,7) along the central span; it varies and decreases to 3,70 m in the side spans, in order to fit with the other decks. The towers are 60 m high from the footing, 51 m from the deck. The top of the towers, where the stays are anchored, is a steel-concrete composite structure. The stays are made of 55 to 91 zinc-coated, singularly greased and sheathed 0,6” super strands. The total amount of steel for the stays is 410 tons, corresponding to about 66 Kg per square meter of deck. The foundation of each tower has the footing (shaped to reduce the drag force) supported by 28 piles, 2m diameter and 65 m long. Derailment of railway vehicles. Two accidental design situations have been considered with respect to the stays: - collapse of two consecutive stays along one side due to the derailment of a vehicle: the bridge must remain in service with one design train over the track nearest to the injured side and one passenger train ( 40 KN/m ) over the other, the thermal effects being excluded; - the consecutive stays collapsed are three: only the effects due to one design train is taken into account. Dynamic analysis.Three different trains (ETR 500,TGV, ICE) have been considered for the dynamic analysis considering the dynamic behaviour of the vehicle as well as the irregularities of the track. Combined response of structure and track. The effects resulting from variable actions have been taken into account according to prEN 1991-2 and for two limit stiffness of the foundations. Seismic analysis have been carried out in the elastic range according to the Italian Railway Specifications and EC 8. Because of the low seismicity, seismic actions did not influence the design of the bridge but in a few sections in the upper part of the towers, while they were relevant for the bearings and the joints. All the decks have been built by cantilever method with cast in situ segments, but the 13 simply supported spans. CONSTRUCTION - Civil engineering Works • 1- General view of the whole bridge. A number of physical tests have been executed to assess the theoretical assumption, the most outstanding being: (i) test on a half scale model reproducing a segment of the deck with a stay anchorage, carried on in the yard; (ii) fatigue test on a full scale model of the steel box embedded in the upper part of the tower to anchor the stays and (iii) fatigue tests on three stays (composed by 55, 73 and 91 0,6” strands) complete of anchorage. Both fatigue tests were carried on in the EC Joint Research Centre of ISPRA. Due to the importance of the bridge, a large number of sensors have been permanently placed on it. The monitored quantities are: loads on the piles, stress and temperature in the most representative sections of the deck and the towers as well, forces transmitted by a number of stays and bearings, geometrical data like the angular rotation of towers and the deflection of the decks and, finally, the scour near the piers in the riverbed. Both sonar and magnetic devices have been installed to detect scour. All the data will be collected inside the cable-stayed deck and from there automatically transmitted to a remote office located in Bologna that will manage the monitoring system of the bridges of the line. 1 CONSTRUCTION - Civil engineering Works 165 Italian High-Speed Network 4 3 2 5 166 CONSTRUCTION - Civil engineering Works Completion of the towers and access viaducts. 3-4 Construction of the deck •by 2-segments. 5- Pouring the crown segment. 6- Tower elevations. 6 CONSTRUCTION - Civil engineering Works 167 “Piacenza” viaduct Italian High-Speed Network Project Piacenza viaduct Location Piacenza, Italy Client Ferrovie dello Stato S.p.A. Concessionaire T.A.V. S.p.A. Higher supervision Italferr S.p.A. Design Dott. Ing. Villa General Contractor Cepav uno 168 In the Milan-Bologna stretch of the high-speed/high load railway line the Piacenza Viaduct runs a total length of 5103 m. The structure breaks down into two stretches, Piacenza1 and Piacenza2, their lengths 2522 m and 2581 m respectively. The first stretch features a two-light caisson deck and a steel-concrete mixed-structure span 50 m long. The second stretch, like the first, also comprises a two-light caisson deck plus two mixed-structure spans of lengths 38 and 40 meters. The prestressed-concrete spans consist of monolithic precast two-light caissons with post-tensioned prestressing cables. The caissons weigh 975 tons each and are 33 meters long. The section depths/thicknesses are 45 cm for the webs, 37 cm for the deck slab and 30 cm for the bottom slab with increased depth at 60 cm from the ends. The prestressing cables are 24 post-tensioned cables, electrically insulated by the use of insulated head ends and HDPE sheaths. Of them, fifteen 19-strand cables are placed in the three webs, with parabolic trajectories, while the other nine cables, 12-strand, are placed in the bottom slab on a straight-line trajectory. The strands used are class fptk 860 MPa, having a rated section of 139 mm2. Maximum pier height is 12 meters. The foundations, deep, are built on piles. The caissons were worked up in the plant, in the following phases: creation and placement of the slack reinforcings and of the forms, a concrete pour carried out with the aid of truck mixers and of two truck-mixer pumps positioned nearby the head ends, threading and tensioning of the cables and, finally, hauling the caisson to the launch area. This last phase was carried out by a special launch car weighing 900 tons. CONSTRUCTION - Civil engineering Works the launch caisson. 2- Hauling the caisson. 3- Launching the cais•son.1-4-Preparing Mounting the side wings. 5- Viaduct cross section. 6- Construction phases: a) pour of the bottom slab; b) pour of the septums; c) pour of the top slab; d) folding back the internal forms for their removal. 7- Cross section through the two-light caisson. 8- Longitudinal section through the two-light caisson, showing prestressing cables. 1 2 3 5 b a 6 d c 4 7 8 CONSTRUCTION - Civil engineering Works 169 “Modena” system viaducts Italian High-Speed Network Project Modena viaducts Location Modena, Italy Client Ferrovie dello Stato S.p.A. (State Railway System Inc.) Concessionaire T.A.V. S.p.A. Higher Supervision Italferr S.p.A. Design Prof. G. Macchi (Final design), Ing. Sangalli (Construction design) General Contractor Cepav uno 170 The Modena Viaducts system belongs to the high-speed/high-load Milan-Bologna line and has a total length of 25,182 meters, of which 23,958 m built with precast segments and 1224 m with in situ-poured continuous beams. The Table gives the names and the principal characteristics of the viaducts belonging to the “Modena” System. All these viaducts have in common a type of deck known as the Omega, featuring a U beam bearing the track on its flange for each track.This particular cross-section conformation has the advantage of mitigating noise emissions by partially enclosing the train within the structure through the bearing walls, which also act as noise barriers. What is special about these viaducts is the particular precasting process used, which enabled installation, during full production (between 2003 and 2004) of more than one segment per day with a peak of 52 segments launched in July 2004. Besides the 767 plant-precast (isostatic) segments, the structures call for an additional nine statically-indeterminate continuous-beam stretches of length 136 m, with spans of 40-56-40 m (statically indeterminate), for a total of 27 spans. In the statically-indeterminate stretches too the cross section is still the Omega type, with projections in the zones where the bending moment is negative. The statically-indeterminate members are poured in forms hanging from overlying ribs. The typical viaduct span in the isostatic stretches is a precast prestressed-concrete member having an open cross profile.The precasting, for a single-track, is 9 m wide and 3.5 m deep, weighing a total 690 tons of which 33 tons are steel (slack reinforcing and prestressing). The outside surface of the deck features longitudinal channels and four r.c. support elements solidly joined to it, the internal surface is smooth and encloses the trackway.The decks were all built using an Rck 45 MPa concrete. The (circular section) piers are 3.5 m in diameter with heights from 5.45 m to 12.20 m.Their sections display three typologies: hollow with a 50 cm wall-depth, hollow but filled, and full-section. In the statically-indeterminate stretches the central piers are 4.50 m in diameter with full circular sections.The piers are built of Rck 35 MPa concrete. The foundations were built in two ways: on 1500 mm diameter piles of lengths between 35 and 50 m, and on diaphragm septums, 120 cm thick and 36 m long.The footings have dimensions of 9.5 m x 16.7 m x 2.2 m and were built of Rck 30 concrete. CONSTRUCTION - Civil engineering Works Longitudinal section through deck. 2- Cross section through isostatic portion. •3-41-Sections through statically-indeterminate portions showing enlargements nearby the areas of negative moment. 5- Precast segment for the isostatic span. 6- Launch of the isostatic segment. 7- Statically-indeterminate portion. 1 2 5 Statically indeterminate beams Isostatic beams, no. Viaduct name 3 Total lenght (m) Brennero - Odd track Brennero - Even track Modena Interconnection - Odd track Modena Interconnection - Even track Modena - Odd track Modena - Even track Panaro - Odd track Panaro - Even track Secchia TOTAL 6 4 7 CONSTRUCTION - Civil engineering Works 171 “Savena” Viaduct Italian High-Speed Network Project Savena Viaduct Location Bologna – High-Speed Florence-Bologna Railway Line Client T.A.V. S.p.A. Design Studio Sintecna – Prof. Ing. Giuseppe Mancini Contractor IMPREGILO S.p.A. The Savena viaduct is the crossing of the river of the same name by the Florence-Bologna HighSpeed Railway Line on a single double-track deck.This structure’s main characteristic lies in the deck’s structural depth (below the ballast), which is just 80 cm for a 63.5 m span. To achieve this slenderness design opted for a through-arch in which the deck is the structural system’s tendon. The deck plate is thus so shaped as to create in its central zone the basin containing the ballast, below which the structural depth is 80 cm. Laterally the depth was suitably increased so as to correctly house the prestressing-cable heads. The deck is suspended laterally and two alignments per side of hangers, connected to two r.c. arches, inclined toward the interior of the bridge and connected in their turn by three r.c. crosspieces. In order to meet the design performance requisites, consisting in total prestressing in service, at the deck edges in the main directions two-way prestressing had to be applied to the plate. Its effects were evaluated using a finite-elements mathematical model consisting of shell elements. The hangers are connected to the deck through pre-tensioned prestressing bars and anchored in the soffit.The bridge’s construction was carried out in the following phases: • the three-phase deck pour on the embankment behind the abutment and the deck’s progressive crosswise prestressing on the ground; then the creation of the longitudinal prestressing; • construction of two provisional piers in the river; • a forestarling 22 m long is mounted; • thrust of the deck up to the next abutment; • the mounting of centerings and forms for the in situ pour of the arches; • mounting and adjustment of the hangers, with the deck being detached from the provisional piers; • demolition of the provisional piers and their foundations. 1 172 CONSTRUCTION - Civil engineering Works • 1-2- Deck plan, and cross section through viaduct. 2 CONSTRUCTION - Civil engineering Works 173 Italian High-Speed Network 174 3 6 7 • 3- Construction of the provisional riverbed piers. 4-5 Detail of the arch-plate join and the reinforcing. 6- Installation of the arch reinforcings. 7- Forestarling for the construction of the deck. 8- Anchorage of the hanger on the deck. 9- Bridge side view. CONSTRUCTION - Civil engineering Works 4 5 8 5 99 CONSTRUCTION - Civil engineering Works 175 “Caivano” variation structures Italian High-Speed Network For the construction of the Rome-Naples High-Speed line through the municipality of Caivano, the railway had to be inserted with the least possible environmental impact on the territory. This led the customer, RFI-TAV, to work out “structures” that would be an addition to the territory. The variation, which runs some six kilometers between stations 200 km and 206 km of the Rome-Naples High-Speed Line substantially comprises three principal structures: - the conical-capital viaduct; - the multiple-arch viaduct; - the two cut-and-cover tunnels Caivano 1 and 2. THE CONICAL-CAPITAL VIADUCT Project Rome-Naples High-Speed Line Location Caivano, Naples, Italy Client R.F.I. S.p.A. (Italian Railway System Inc.) - T.A.V. S.p.A. (High-Speed Train Inc.) Design Prof. Remo Calzona CE Contractor Società Italiana per Condotte d’Acqua S.p.A. Year of completion March 2006 THE MULTIPLE-ARCH VIADUCT Project Rome-Naples High-Speed Line The conical-capital viaduct The structure is 203 m long and serves to overpass three interfering lines having centerlines strongly skew to the railway line: the Turano-Biferno aqueduct, the Secondigliano sewer line and the SS87-bis highway. The positioning of the vertical elements follows directrices parallel to the centerlines of the interferences, the deck is created by an orthoanisotropic plate, woven crosswise to these directrices so as to minimize the bearing structure’s span. Deck characteristics and constraint scheme: two-span frame with an orthoanisotropic plate fixed-jointed to the columns. Soil conditions, water table: soils of volcanic origin featuring a first 8-10-meter stratum of fairly well compacted pyroclastites, an underlying stratum six meters thick of tuff having lithoid characteristics and a successive stratum of more deeply densified pyroclastites.The water table lies at an average four meters below site level. Degree of seismicity: the area is classified as a second-category seismic zone, so that its degree of seismicity, S, is 9. Foundations typology: deep piles 1200 mm in diameter. Construction procedures: the pier foundations and standing structure were in situ poured. For the deck, resort was had to precasting long-span predalles; the precast beams were prestressed, and an in situ completion pour was made for the slab. Location Caivano, Naples, Italy Client R.F.I. S.p.A.(Italian Railway System Inc.) - T.A.V. S.p.A. (High-speed Train Inc.) Design Prof. Remo Calzona CE Contractor Società Italiana per Condotte d’Acqua S.p.A. Year of completion March 2006 THE CUT-AND-COVER TUNNELS CAIVANO 1 AND 2 Project Rome-Naples High-Speed Line Location Caivano, Naples, Italy Client R.F.I. S.p.A.(Italian Railway System Inc.) - T.A.V. S.p.A. (High-speed Train Inc.) Design Prof. Remo Calzona CE Contractor Società Italiana per Condotte d’Acqua S.p.A. Year of completion 2007 176 The multiple-arch viaduct The viaduct comprises a sequence of 74 parabolic-profile arches having a 33.00 m chord, arranged in two parallel files spaced 8.40 m apart. The arch height varies between 0.80 m at the crown, including the depth of the slab, to 4.00 m at the springer. Its depth is instead a constant 1.00 m. The upper slab, 13.60 m wide, has a depth varying between 0.60 m at midspan to 0.50 m at the ends. Overall viaduct length is 2400 m. Deck characteristics – constraint scheme: reinforced-concrete arch. Soil characteristics, water table level: soils of volcanic origin, the first stratum of pyroclastites of medium density varies in depth, being greater at the start of the viaduct and lessening towards its end. Right below it is a tuff bench six meters deep and then the pyroclastites are taken up again, more deeply densified.The water table lies at an average four meters below site level. Degree of seismicity: the area is classified as a seismic zone of second category, so that the degree of seismicity, S, is 9. Foundation typology: deep piles an average of 35 m long and diameter 1500 mm. Construction procedure: to build the standing structure a form was used created especially for the purpose. It enables building in a first phase both arches and, after their curing, the slab in a single pour. The cut-and-cover tunnels Caivano 1 and 2 In order to underpass the two interfering roadways, motorway A1 and the Nola-Villa Literno superhighway, two gigantic monoliths were designed, weighing 12,000 and 8,000 tons respecCONSTRUCTION - Civil engineering Works tively, which were translated underneath the two aforesaid interferences. Completing the job are the cut-and-cover rain tunnels, which at the mouths prevent the entrance of rainwaters. Soil characteristics and water table: soils of volcanic origin. The first stratum of medium-dense pyroclastites varies between 67 meters of depth; the next 5 m down sees a tuff stratum of good mechanical characteristics, and deeper down yet are again dense pyroclastites. The water table lies at four meters below site level. Degree of seismicity: the area is classified as a second-degree seismic zone, so that its seismicity, S, is 9. Construction procedures: the monoliths, 115 m and 70 m long, were poured in situ in special forms and then translated using a thrust system that enabled the translation of the greater of the two caissons in just six days. CONSTRUCTION - Civil engineering Works 177 Tunnels in the Florence-Bologna stretch of High-Speed Line Italian High-Speed Network Project Tunnels in the Florence-Bologna stretch of High-Speed Line The design and construction of the tunnels were carried out under the A.DE.CO-RS (Analysis of Controlled Strains in the Rocks and Soils) design methodology. This approach was used to make up the base-contract project and then the construction design. This tunnel design and construction methodology avoids the limitations of traditional approaches, by supplying the possibility of industrializing the tunnel advances even when traditional driving methods are applied, in complex geomechanical contexts and with covers running from a few meters to six hundred.The tunnels drive through sundry Apennine geological formations, consisting mainly of marls, sandstones, scaly clays and limestones. In driving the running tunnels the following methodologies were adopted: • “Traditional” driving by the use of traditional machines (jumbos, excavators, jackhammers, power shovels), except for the Ginori service tunnel, the only stretch in which wholly mechanized driving was carried out (by a shielded TBM). Overall some 17 million cubic meters of material were excavated. • Full-section driving after consolidation of the core-face (where necessary), especially under difficult stress-strain conditions. • Limitation of soil decompression by means of pre-confinement operations on the core-face or confinement of the cavity (sub-horizontal jet-grouting, fibreglass plastic structural elements in the core or around the cavity, shotcrete and steel ribs, radial bolts, etc.).The operations were defined depending on the strain behaviour of the advancing core-face, evaluated during design phase, described according to the following three behaviour categories: A= stable front, B= short-term stable front, C= unstable front. Corresponding to each category is a tunnel section type for the driving and advance.The percentage distribution of the tunnel section types applied is as follows: type-A sections (35%), type-B sections (53%), type-C sections (12%). • Final concrete and reinforced-concrete lining.The final linings (roof, sidewalls and inverted-arch) were in situ-cast concrete of class C25/30 in depths of 60-100 cm. On the whole seven million cubic meters of concrete were applied. Duration of the construction phase: 13.5 years (from July 1996 to December 2009) with advance rate of one to five meters per day and up to 2000 meters per month on thirty faces at the same time. Location Florence-Bologna stretch Client R.F.I. S.p.A. (Italian Railway System Inc.) Garantee T.A.V. S.p.A. (High Speed Train Inc.) Higher Surveillance Italferr S.p.A. Design MAIRE Engineering Rocksoil S.p.A. General Contractor FIAT S.p.A. Year of completion 2009 Main features Total length of the High-Speed Florence-Bologna railway stretch: 78.5 km Underground works: - 9 double-track driven tunnels having multi-centered sections with a driven area of 140 m2 and a net area of 82 m2, their lengths running from 693 m to 18.2 km; - 13 access windows for a total length of 9.3 km; - one service tunnel 10.65 km long; - 2 single-track interconnection tunnels (total length 2.2 km); - 3 cut-and-cover double-track tunnels 2.8 km long; - one large underground chamber for switching space, one underground interconnection chamber. 1 178 CONSTRUCTION - Civil engineering Works 1- Pianoro Nord area: Savena bridge and the portal of the Pianoro Tunnel. 2•Northern portal of the Monte Bibele tunnel. 3- Firenzuola chamber. 4- From the northern Morticine portal to the southern Borgo Rinzelli portal. 5- Southern portal of the Sadurano tunnel. 6- Southern portal of the Raticosa tunnel. 2 4 3 6 5 CONSTRUCTION - Civil engineering Works 179 New stations for Italian High-Speed Network Italian High-Speed Network In all cities the construction of a new railway station is a special event, if only in that unlike an airport or other man-made transportation facilities, it constitutes a “port within the heart” of the city itself. In Italy station construction has marked the stages in the modernization of the country; the stations of the main Italian cities were the starting point of the “journey” and as such were often constructed as authentic monuments. The new stations that are emerging due to the advent of high-speed rail transportation are being located in the cities according to different criteria than in the past, often being designed to reunite parts of the city separated by the railway lines and to contribute to their redevelopment and enhancement. Some of the world’s leading contemporary architects have been commissioned to design stations that are full of life, light and sound -in a word, stations with a definite soul, and one that they are able to project: no longer an anonymous “non-place”, a desolate point of transit and metaphor for lone travel, the new stations are “the place”, and, similar to how a town square encourages aggregation, dialogue and leisure, they embody the very concept of urban community life. Railway stations will be home to bookstores, cafes and shops and become venues for music, art and culture so that they come to be looked on by the public as places in which social relations are played out. On the horizon are the new HS stations of Naples Afragola designed by Zaha Hadid, Rome Tiburtina designed by ABDR-Paolo Desideri; Florence Belfiore designed by Norman Foster; Bologna designed by Ricardo Bofill; Reggio Emilia designed by Santiago Calatrava and Turin Porta Susa designed by Arep Group. Meanwhile, plans and works are in progress for the redevelopment of the historic mainline stations to adapt them to new management and operational requirements and enhance the cultural heritage they represent. 180 CONSTRUCTION - Civil engineering Works HS Bologna Station – the map. 2- Structural sketch of the new Bo•logna1- TheHS new Station (drawing by P. Bellotti). 3- The transversal section. 4- The new HS Bologna Station work site. 1. BOLOGNA HS STATION Project Bologna High-Speed train station 2 Location Bologna Client R.F.I. S.p.A. (Italian Railway System Inc.) Design and structural engineer ITALFERR S.p.A. Management Contractor Italferr S.p.A. Architects Ricardo Bofill Contractor Astaldi S.p.A. The Bologna HS Station extends under a section of the track array of the existing central station into a large underground chamber approximately 640 m long, 42 m wide and 23 m deep. The new underground station will be split into three levels.The HS tracks will be laid on the bottom level, passenger services and 1 commercial activities will be located on the middle level, while the upper level will be reserved for vehicular traffic to the station and as parking space.The middle level will also be used as an exhibition area for the numerous archaeological finds (including a road, a furnace and burial chambers) found during excavation. The HS Station was designed by the Catalan architect Ricardo Bofill who adopted innovative solutions of high architectural value. The supporting structures of the excavation, for example, are designed as “facing arches” that transfer earth thrust to “spurs” placed at 12 m intervals: this results in large bulkhead sections free of structural obstacles both horizontally (12 m of clear space) and vertically (24 m of clear space). This innovative solution exploits the facing arches as architectural elements to project daylight onto the tracks creating a vertical illumination effect similar to that found in Gothic architecture and also allows the insertion of vertical communicating elements between levels. An international design competition for the completion of the central station and the redevelopment of the urban area in which it is located has been recently awarded to the Japanese architect Isozaki. 3 Main features Plan dimensions: 640m x 42m Overall height: 23m (underground) Pile perimetral bulkheads: 20,000 m2 Bulkheads, rider arches and spurs = 37,000 m2 Foundation concrete: 57,000 m3 Foundation reinforcing steel: 10,000 t Concrete in standing structure: 100,000 m3 Reinforcing steel in standing structure: 15,000 t Structural steel: 31,000 t Floor-structure area: 80,000 m2 4 CONSTRUCTION - Civil engineering Works 181 •tion.1- Overall view. 2- Detail the steel-glass canopy. 3-4- Internal view. 5- Cross sec- Italian High-Speed Network Main features Plan dimensions: 450m x 52m Overall height: 26.5m Bulkheads: 40,000 m2 Foundation concrete: 95,600 m3 Reinforcing steel in foundation: 22,800 t Standing-structure concrete: 75,000 m3 Standing-structure reinforcing steel: 23,700 t Structural steel (tons): 8,000 t Floor-structure area: 35,000 m2 2. FLORENCE HS STATION Project Florence High-Speed railway station Location Former Macelli/Belfiore area of Florence, Italy Client R.F.I. S.p.A. (Italian Railway System Inc.) Design ATI Foster and Arup Structural engineer Definitive design: Arup Final design: Nodavia Architects Foster & Partners 1 Management Contractor Italferr S.p.A. General Contractor Nodavia, Ati Coopsette-Ergon engineer The new Florence HS station will be built in a nineteenth-century district of the city, that of the former Macelli (slaughterhouses) area, and is part of a wider-ranging project for the recuperation of abandoned industrial sites in various parts of the city. The new station will not replace but form an interchange node with the existing Santa Maria Novella station. The two stations will be linked by a new tramway that will extend to Peretola airport and by shuttle trains between the Circondaria regional train station and Santa Maria Novella station. Like the great stations of the past, the new HS station will feature large, mainly glass-covered volumes. While construction technology and trains have radically changed since the nineteenth century, large spatial dimensions and quality remain indispensable requirements for modern stations.The project was developed by the architect Norman Foster.The station will be built on two underground levels in a vast chamber 454 m long and 52 m wide, and the rails of the high-speed line will be located at a depth of 25 m from ground level. From a structural point of view the station is characterised by 1.6 m thick vertical support panel bulkheads reinforced by perpendicular spine walls and strutted in such a way as to allow ample clearance for the passage of light. 182 2 3 4 5 CONSTRUCTION - Civil engineering Works • 1-2- Overall view. 3- Detail. 3. ROMA TIBURTINA HS STATION Project The new Rome Tiburtina High-Speed train station – 1st functioning job segment Location Rome, Italy Client R.F.I. S.p.A. (Italian Railway System Inc.) Design ABDR Architetti Associati – Paolo Desideri arch. (Chief of job coordination) Structural Engineer Ezio Maria Gruttadauria CE Architects Studio Tecnico ABDR architetti associati Contract Management Italferr S.p.A. 1 Contractor ATI Coopsette / MECoop 2 Main features Overall height: 36 m of which 26 m above ground. Bulkheads: 29,150 m2 Piles: 62,190 m Foundation concrete: 42,450 m3 Reinforcing steel in foundation: 14,425 t Standing structure concrete: 24,675 m3 Standing structure reinforcing steel: 7,415 t Structural steel: 11,750 t of which 1,475 t for the roof space-lattice structure Floor-structure area: 54,000 m2 3 CONSTRUCTION - Civil engineering Works 183 1- General view. 2- Transversal section of the first part of the station. 3-4-5-6-7•8- The work site. Italian High-Speed Network 4.TURIN PORTA SUSA HS STATION The underground station The station was built in two phases under two integrated projects, developed in different periods. The first project is tied to the construction of the Turin through line for putting underground the tracks running through the city and for quadrupling them; this to be done with the construction of the Porta Susa station underground. This station, essentially an underground chamber conceived as an underground station, is in an advanced stage of construction and is partially operating since 2009. In what follows the principal characteristics of both projects are set forth. 1 Project The Turin Porta Susa High-Speed train station Location Turin Porta Susa, Italy Client R.F.I. S.p.A. (Italian Railway System Inc.) Design ITALFERR S.p.A. (Definitive), Ing. Campa (Final) Structural engineer ITALFERR S.p.A. (Definitive), Ing. Campa (Final) Architects ITALFERR S.p.A. (Definitive), Ing. Campa (Final) Management Contractor ITALFERR S.p.A. 2 Contractor A.T.I. – Astaldi S.p.A. (Mandatary Group Leader) – Vianini Lavori S.p.A. (assignor) - Impresa di Costruzioni Rosso geom. Francesco & Figli S.p.A. (assignor) – Di Vincenzo Dino & C. S.p.A. (assignor).– Turner & Townsend Group Limited (assignor) Main features Plan dimensions: 465 m x 45 m Overall height: 12 m Bulkheads: 2,500 m2 Foundation concrete: 20,000 m3 Reinforcing steel in foundation: 2,4 kt Concrete in standing structure: 23,500 t Reinforcing steel in standing structure: 3,4 kt 184 3 4 5 6 CONSTRUCTION - Civil engineering Works • 9- The new station. 10- The structure completed. 11- Detail. 12- Overall view. The new station building The second project for completion foresee a station building integrated into the new city plan. The station also acts as an exchange node with the underground MRT system. Project The Turin Porta Susa High-Speed railway station Location Turin Porta Susa, Italy 7 8 Client R.F.I. S.p.A. (Italian Railway System Inc.) Design/Structural engineer/Architects Joint venture of designers: AREP J.M. Duthilleul, E. Tricaud (Group leader), arch. Silvio D’Ascia, prof. arch. Agostino Magnaghi Contract Management R.F.I. S.p.A. Contractor Joint venture of companies: Guerrino Pivato S.p.A. (Group leader), BIT S.p.A. Main features Plan dimensions: 385 m x 33,60 m Overall height: • portion below street level: 10.19 m • portion above street level: varying from 3 to 12 m Floors above ground: 1 Floors below ground: 3 Gross pavement area: 39,800 m2 Underground parking area: 8,700 m2 9 11 12 10 CONSTRUCTION - Civil engineering Works 185 Italian High-Speed Network 5. REGGIO EMILIA HS STATION Project Reggio Emilia High-Speed railway station Location Reggio Emilia, Italy Client The Emilia-Romagna Region and T.A.V. S.p.A. Design Santiago Calatrava Structural Engineer Impresa Cimolai S.p.A. is making use of the following designers: SETECO (steel) – SGAI (concrete) Architects Impresa Cimolai S.p.A. – RPA (architecture) with the supervision of architect Calatrava for the artistic aspect Contract Management Italferr S.p.A. Contractor Impresa Cimolai S.p.A. Main features Plan area: 483 m x 50 m Overall height: 20 m average, since the roof has a sine-wave profile and h varies. Foundation concrete: 16,734 m3 Foundation reinforcing steel: 1,700 t Standing structure concrete: 2,250 m3 Standing structure reinforcing steel: 430 t Structural steel: 9,140 t (portals, arches and beams) Floor structure area: 7,728 m2 (loading platforms) and 200 m2 (ground-floor business stalls) 186 CONSTRUCTION - Civil engineering Works 6. AFRAGOLA HS STATION Project Naples – Afragola High-speed railway station Location Afragola district - Naples, Italy Client R.F.I. S.p.A. (Italian Railway System Inc.) Design Definitive design - Zaha Hadid arch. Final Design: SAIR – GEIE (European Architecture, Town-planning and Engineering Group) Structural Engineer Definitive design - Zaha Hadid arch. Final design - SAIR – GEIE (European Architecture, Town-planning and Engineering Group) Architects Zaha Hadid arch. Contract Management Italferr S.p.A. Contractor ATI DEC S.p.A. Main features Plan dimensions (project area, including parking): 450 m x 350 m Overall height: 26.45 m Bulkheads: not present Foundation concrete: 38,000 m3 Foundation reinforcing steel: 4,000 t Standing structure concrete: 45,000 m3 Standing structure reinforcing steel: 5,200 t Structural steel: 4,200 t Floor structure area: 23,000 m2 CONSTRUCTION - Civil engineering Works 187 “Colletta” cable-stayed bridge Project The Colletta cable-stayed bridge Location Sangone creek, Giaveno (Turin), Italy Client The District of Turin Design A.T.I. [GEODATA SpA, Mario Petrangeli & Associati Srl (Prof. ing. Mario Paolo Petrangeli, ing. L. Fieno, ing. L. Pinchiaroglio)] General contractor A.T.I. (SISEA, COGEIS, FIP Industriale) Stays (supply and work) TESIT SpA Photographs Mario Petrangeli & Associati Srl 188 After the floods of October 2000 that caused enormous damage, the province of Turin appropriated funds for setting the riverbeds to rights and for reconstructing damaged infrastructures, among which the bridge over Sangone creek. The impossibility of changing the existing highway route, owing to the numerous constructions lined along it, compelled design to conserve the old bridge’s position in both line and grade, and this was a heavy constraint on the design of the new one. In making up the design, the alternatives evaluated had to eliminate the intermediate supports (their presence would mean the construction of deep-lying foundation structures) and increase bridge length by twenty metres, while meeting the hydraulics clearances required and providing a wide range of choices of construction methods and an architectural value suited to the site’s environmental value. At the end the choice fell on a cable-stayed bridge eighty meters long. The deck cross section, a total 15.10 m wide, is the classical one for small-span stayed bridges: there are two main girders, of rectangular section 2.0 m x 1.20 m, in situ-poured and lightly prestressed, on whose centerlines are anchored the stays, with their heads placed in special places.The two longitudinal beams bear the secondary crosswise weave, created with adherent-strand prestressed precastings placed at 2.50 m spacings.The pylon, a total 36 m high from its springer, consists of two blade uprights inclined by ten degrees to the vertical and connected by an upper prestressed crosspiece, placed immediately below the stay anchorages. The pylon bears eight pairs of stays that sustain the eighty-meter span and is itself anchored to the ground by another four pairs of stays that are anchored on the mooring block. The pylon base is a caisson foundation structure, such as to directly transfer the stresses below the creek bed directly onto the bedrock. CONSTRUCTION - Civil engineering Works in which is seen too a bridge built for provisional traffic flows. 2- The brid•ge,1-frontPlan,view. 1 2 CONSTRUCTION - Civil engineering Works 189 Pour of the deck slab. 4- The completed pylon structure, awaiting removal of •the3-scaffoldings. 5- The stays system in its end configuration: in view are the two mooring blocks anchoring the stays, since the single-span bridge scheme is dissymmetric. 6- Cross sections through the deck: typical (left) and nearby the pylon (right). 3 5 4 6 190 CONSTRUCTION - Civil engineering Works CONSTRUCTION - Civil engineering Works 191 Rio S’Adde viaduct Project Road viaduct Location Rio S’Adde – SS 129, Macomer, Sardegna, Italy Client ANAS spa Agency letting contractor Province of Nuoro General design Ing. Gian Paolo Gamberini Structural design Ing. Pietro Paolo Mossone Chief of supervision of construction Ing. Gian Paolo Gamberini General contractor CONSCOOP, Forlì – Coop. Edile “Edile di Orgosolo s.c.r.l.” (awarded contractor) 192 The structure, enabled the elimination of several kilometres of tortuous road that made connections with the city of Macomer, in the heart of Sardinia, inconvenient. This was effected by a viaduct that crosses a valley 180 m broad. The nature of the place, imposed on design choices aimed at maximizing the oeuvre’s harmony with its context.The structure comprises a singlelight box deck of variable section set on two slender piers, each composed of two septums set close together. The deck breaks down into three spans of lengths 45, 90 and 45 metres. The deck depth runsbetween 2.30 and 4.50 metres, while the depth of the box soffit slab varies between 0.22 and 1.00 m.The thickness of the side walls is 0.50 m and the extrados slab is 0.22 m deep. The crosswise width is 13.00 m at the upper slab and 6.50 m at the lower. The piers each comprise two septums having a section of dimensions 1.00 m x 7.50 m and heights of 21.70 m and 25 m respectively. The two septums are connected together at the base by crosswise septums 0.50 m thick. Deck construction proceeded by symmetric balanced advance cantilevered from the piers with pours of successive segments; these were then prestressed in pairs by the application of post-tensioned cables. The deck was built of 43 segments. The two approach spans comprise ten segments each, and the centre span comprises two facing halves, each of which breaks down into ten segments; there are also the crown segment and the two pier-head segments. Each segment is 4.20 m long except for the centre span crown segment, which is 1.00 m long.The deck is prestressed with post-tensioned cables.The pierhead segments were poured on centerings, to create the base platform for the launch cars. From these segments construction went ahead symmetrically with two isostatic tees being built, joined by the crown segment. CONSTRUCTION - Civil engineering Works Deck cross section at the pier. 2- Cross section through deck at midspan. 3•The1-procedure for constructing the deck cantilevered from the pier. 4- The septums composing the pier structure. 1 2 3 4 CONSTRUCTION - Civil engineering Works 193 • 5- Bridge grade profile. 194 CONSTRUCTION - Civil engineering Works 5 CONSTRUCTION - Civil engineering Works 195 Bridge over Vajont creek Project Road bridge Location San Martino, Erto (Pordenone), Italy Client Erto and Casso Municipality Structural design Ing. Paolo Giovenale, ing. S. Rossi, Roma Geothecnical works design Prof. F. Colleselli, Padova Chief of supervision of construction Ing. P. Sommavilla, Belluno Safety coordinator Ing. A. Tenani, Belluno Impresa costruttrice Monti S.p.A., Auronzo di Cadore (BL) The bridge over Vajont creek, which stands five kilometres in an air line from the dam, was literally swept away by the wave, running uphill, generated by the slide of 260 million cubic meters of material that detached from Mount Toc on October 9th 1963. Some three years ago the Erto and Casso city administrations decided to start up reconstruction work of the bridge and to improve the existing city road on the left bank of the creek.The solution approved was a prestressed-concrete box-girder bridge built cantileverwise by successive segments starting from the right bank of the creek. In its definitive configuration the bridge is a total 87.25 m long and 7.50 m wide. The net span of the bridge between its bearings is 74.50 m.The rest of the deck corresponds to a stretch built on the right bank, that acts as counterweight, and anchorage for the stay cables.The route in plan is in tangent, and its grade profile lies at 731 m above sea level.The roadway section has a 4.50 m wide carriageway and a bicycle and foot path 1.50 m wide. The deck consists of a prestressed-concrete single-light box whose depth varies from 6.94 m at the bearings on the right bank, to 3.25 m in midspan. The width of the box is a constant 3.00 m. The upper slab is 7.00 m wide. The depth of the extrados slab is a constant 0.25 m in the center, between the (vertical) webs. It descends to 0.20 m in the cantilevered parts. The soffit slab depth varies from 0.25 m in span to 0.70 m at the starting section of the first segment. The webs are 0.30 m thick. The statics scheme of the structural system as a whole is thus a fixed-jointed or simply-supported beam. The deck comprises a total of fourteen in situ-poured segments.The abutment segment, 14.00 m long and weighing 930 tons, was poured in a specially built form bearing on the ground. The last segment, 2.75 m long and weighing 55 tons, was poured directly on a form mounted on the left-bank abutment. 1 196 CONSTRUCTION - Civil engineering Works 1- Longitudinal section through the bridge. 2-3 Phases in the cantilevered con•struction of the deck by successive segments. 4- The last segment connecting with the tunnel. 3 2 4 2 CONSTRUCTION - Civil engineering Works 197 • 5- The bridge in plan. 6-7 Testing and load testing. 6 7 198 CONSTRUCTION - Civil engineering Works 5 CONSTRUCTION - Civil engineering Works 199 “Cesare Cantù” cable-stayed bridge Project Cable-stayed bridge, crossing the Adda river Location Between Calolziocorte (LC) and Olginate (LC), Italy Client Province of Lecco Design Eng. Angelo Valsecchi (Department of Transportation, Province of Lecco) Structural engineering Prof. Carmelo Gentile, PhD, Eng. Roberto Gentile Management Contractor Department of Transportation, Province of Lecco General contractor Vitali S.p.A., Cisano Bergamasco (BG) Year of completion 2009 200 The “Cesare Cantù” cable-stayed bridge is a roadway bridge, crossing the Adda river between the municipalities of Olginate and Calolziocorte (about 60 km north-east of Milan).The bridge, opened to traffic on February 13th 2009, is the seventh crossing of Adda river in the Province of Lecco and represents an important commercial link between the opposite banks of the river in a very intensely industrialized area; the conceptual and executive design of the new bridge were completed in 1999 and 2003, respectively. The bridge consists of two H-shaped concrete towers, double-plane cables and a pre-stressed concrete girder deck; the bridge girder is formed by a central span of 110.0 m and two lateral spans of 55.0 m, for a total length of 220.0 m. The deck, made in C40/50 pre-stressed concrete, was cast in place and post-tensioned. The deck is 11.50 m wide and consists of 2 two-cell box girders, 1.50 m high, connected by a central slab and by a series of 24 transverse cross-beams, providing the lower anchorage of the stay cables. The equally spaced cross-beams are 8.00 m apart and their width exceeds of 1.25 m per side the width of the deck. The deck was designed to have a depth of 1.5 m, corresponding to about 1/150 of the total length, so that a good transparency of the bridge girder was attained from aesthetic stand point. The deck is suspended from 48 stay cables, arranged in two planes in a semi-fan, held at the top of the two main reinforced concrete portal towers in special welded steel tower-head assemblies.The cast-in-place concrete towers (C32/40) are about 38.0 m high and consist of two concrete piers, a lower concrete wall connecting the piers and supporting the deck, upper steel devices providing the anchorage for the stay cables and a transverse steel truss connecting the upper part of the piers. The bridge stays use 19 and 31 16 mm diameter strands of steel cable; each strand comprises seven 5 mm wires and is protected by a high-density polyethylene sheath. The construction of the deck was carried out by using an unusual technique. First, a series of large diameter steel pipes were placed on the bed of Adda river in order to allow the water flow corresponding to the maximum expected flood level. Subsequently a stabilized embankment was constructed over the steel pipes and the river bed, so that the embankment was used to continuously support the formworks for the casting of the concrete deck. It should be noticed that the above construction technique, usually adopted for very small spans, turned out to be cost effective; in addition, the stability of the embankment and the effectiveness of the water pipes were successfully checked by the severe flood occurred in Italy during Spring 2008. It is further noticed that, according with the seismic classification introduced in 2003, the seismic hazard at the bridge site was described by the ground design acceleration ag=0.05g and the importance factor was assumed as gI=1.3. The seismic design of the bridge was carried out in order to ensure: (a) elastic behaviour in the vertical and transverse directions; (b) nonlinear dissipative behaviour (by using base isolation hysteretic devices) in the longitudinal direction. It is worth mentioning that the reception tests of bridge included not only the procedures that are mandatory in the Italian Code (i.e. extensive characterization of the materials and severe load tests) but, according to the international practice, also dynamic tests (involving deck, towers and stay cables) during the construction phases and before the bridge opening. CONSTRUCTION - Civil engineering Works The cable-stayed bridge on the opening day (February 13 , 2009). 2- Eleva•tion,1-plan and deck cross-sections of the bridge (dimensions in m). rd 1 2 CONSTRUCTION - Civil engineering Works 201 3-4-5- Construction phases of the bridge. 6- Aerial view of the “Cesare Cantù” •cable-stayed bridge. 7- View of the bridge central span during the reception load tests. 8- Details of the transverse cross-beams providing the lower anchorage of the stay cables. 3 4 5 202 6 CONSTRUCTION - Civil engineering Works 7 8 CONSTRUCTION - Civil engineering Works 203 Bridge between La Maddalena and Caprera Islands La Maddalena Caprera Project Bridge between La Maddalena e Caprera Islands Location La Maddalena Island (Italy) Client Italian Government Design Prof. Ing. Gian Michele Calvi Structural detailing Prof. Ing. Gian Michele Calvi, Lombardi Reico srl (Ing. Giorgio Pedrazzi, Ing. Carlo Beltrami), Ing. Matteo Moratti Architect Prof. Ing. Gian Michele Calvi Contract Management Ing. Valter Frascaroli, Ing. Matteo Moratti General contractor A.T.I. Dott. Mario Ticca S.r.l. – Sassari, S.C.I.R. S.p.A. – Cagliari, Novaco S.r.l. – Sassari Year of completion 2009 204 The bridge replaces a temporary Bailey bridge connecting the islands of La Maddalena and Caprera.The design bridge length is 52 meters, with three spans symmetrically arranged (two lateral spans 13.5 m long and a central one of 25 meters). The rise of the arch is about 5 m. The bridge is composed by double cantilever truss elements, conceived to conceptually allow the rotation of each side on its foundation to open the central span.The variable thickness of the arches that form each cantilever element is such that the vertical dead loads reaction is centred in each foundation. The steel truss elements connecting the upper and lower arches have circular hollow sections (D=150 mm).The lower central span arch and the upper deck merge at the centre in a flexural hinge transmitting shear forces. Axial forces and bending moments reactions are provided at each one of the central arch foundations, by three bearings with tensile reaction capacity.Tension and compression axial force restraints are provided at each abutment. The use of high performance concrete allowed to reduce the structural thickness and to use post-tensioning tendons in the upper deck, to equilibrate part of the tensile forces developed in the upper chord of the spatial trusses. The whole bridge has been protected with white polymeric resin, to provide durability and at the same time to improve the aesthetics of the bridge. All design choices are essentially governed by environmental constraints: 1. the geometry of the fixed points derived from the historical heritage, as well as the idea of an arch bridge and of a conceptually rotating structure; 2. the central span height was the best compromise between deck slope and boat clearance space (5 m (h) by 8 m (w)); 3. the arch shape and the reduced element thickness minimizes the environmental impact; 4. the horizontal reactions at the abutments and foundation had to be limited because of the soil characteristics; 5. an improved structural durability was dictated by the marine environment; 6. the on-site work duration had to be kept at a minimum to minimize the interference with the local traffic; 7. two longitudinal concrete ribs (20 x 50(h) cm) have the double purpose of protecting the pedestrian traffic without inserting heavy guard rail elements, and of contributing to the upper chord structural capacity; 8. the external light parapet complete the sailing boat reminiscence of the whole structure, with only white resin and stainless steel used as finishing materials. CONSTRUCTION - Civil engineering Works 1- Historical bridge in the same location (destroyed). 2- Details of the parapets •of the pedestrian walkway. 1 2 CONSTRUCTION - Civil engineering Works 205 6 3 4 5 206 CONSTRUCTION - Civil engineering Works 3- Construction of the piles cap. 4- Detail of the active-anchorage zone of the •longitudinal tendons. 5- Temporary support and scaffolding of the central arch. 6Joint at midspan: fixed ends of the tendons on both sides. CONSTRUCTION - Civil engineering Works 207 “Don Bosco” bridge at Arenaccia. Architecture, white as light Project Don Bosco bridge at Arenaccia Location Naples, Italy Client City of Naples – RUP Giuseppe Pulli arch. Design and yard management Prof. Antonio De Luca CE Assistants Giuseppe Mautone CE, Alfredo Sasso CE, geom. Corrado Esposito Architectural consulting Prof. Fernanda De Maio arch., Gianluca Marangi arch. Artistic consulting Mariangela Levita Structures consulting Prof. Attilio De Martino CE Geotechics and foundations Prof. Carlo Viggiani CE General proof testing Prof. Roberto Ramasco CE General contractor Joint venture of 3 parties: Fico Costruzioni srl, Amato Trivellazioni srl, Fico Giuseppe Concrete supplier IMECAL s.r.l. Mosaic supplier TREND GROUP S.p.A. Year of completion 2009 The Via Arenaccia is one of the Naples street system’s main arteries, a role it has maintained as the centuries passed. In 1999 the City of Naples decided to replace the old bridge with a new structure that would re-establish, in its entirety, the city’s old connection – as borne witness to by 18th century maps – with its northern districts. The project is highly complex and has many critical features, arising from the bridge’s position in relation to other existing buildings, in an old urban area that is today densely populated. A few of its interactions with existing infrastructures may be mentioned: two 1000 mm pipes under pressure, two sewer trunks six meters wide, 24,000 telephone cables, many electrical cables of medium and high voltage, and gas lines. The very slender deck (its depth at midspan is 50 cm) has the shape of a strongly depressed skew vault.The net span between the bridge abutments, measured on the skew, is 26.90 m, with a width of 19,85 m. The slenderness coefficient, L2/f, is 1450, a very high value for a concrete arch, putting it at the top of the list of constructions of this type internationally. The heavy thrust exerted by the arch deck is taken by the very sturdy caisson-form abutments, which constitute two control rooms needed to create the hydraulic bypass. Special care was taken with durability, by choosing the best material that could be used for the purpose: self-compacting concrete, and by seeing to its physical and mechanical protection through the use of a cladding, long-lasting and easily maintained. The concrete protection was thus converted into a design and architectural point of departure to best fit the infrastructure into its urban context. The choice was to wrap all surfaces: piers, abutments, vault, shelf girders, etc. with glass-mosaic tesseras forming a design, its purpose also to give the structure uniformity and continuity. Bridges built in urban areas too often feature elements lacking order, disconnected and various: beams, crosspieces, bolts, welds, aprons, sails, little shelves, shelf girders, railings, guardrails, meshes. These elements often form a disorderly universe that allows no possibility of cleanness of form in creating an insertion into the urban fabric. The infrastructure thus becomes, too often, synonymous with poor architectural quality. Concrete, with its vocation for the continuous structure, lends itself to eliminating the diversity of elements: piers, main and secondary girders, crosspieces, shearbracings etc. The mosaic thus offered the possibility of creating a uniform whole. The decision to clad the bridge with mosaic tesseras gave the new infrastructure complex a very obvious character, making it readable from the road crossing it even at long distances. Design had, in this case, set up, after consulting the painter Mariangela Levita, an abstract design of great size in tones of black, grey and golden-yellow on a white background, the idea to transform the passageway into a true promenade amid art and architecture.The design on the down-slope abutment bends then towards the new stairway both to mark the thickness of the abutments (six meters deep) and to suggest the continuation of the walk towards the city’s upper level. The protection of the concrete surfaces, with a view to the durability and sustainability of a public work, formed the point of departure for an artistic operation and for the best fit of the infrastructure into its urban context, where the bridge becomes something that does not arrogantly state its presence but that rather seeks to fit its various parts in, discreetly.The mosaic is like a mantle in Christo’s installations, which enwraps all parts of the bridge to give it conformity and continuity. The whole (mosaic, railings and light poles) as white as light. Project co-financed by the European Union FERS European Fund for Regional Development P.O.R. Campania 2000-2006 Measure no. 5.1 208 CONSTRUCTION - Civil engineering Works project design. 2- Cladding of the upslope abutment. 3- View of the down•slope1- Theabutment. 1 2 3 CONSTRUCTION - Civil engineering Works 209 of the bridge with the stairway connecting Via Arenaccia and Via Don Bo•sco.4-5-6ViewBridge longitudinal section and plan. 4 5 6 210 CONSTRUCTION - Civil engineering Works Photo: Luciano Romano CONSTRUCTION - Civil engineering Works 211 Viaduct for State Road (SS)23 Project Road viaduct Location Pinerolo – traffic circle grafting SS23 to SS589 Client Agenzia Olimpica Torino 2006 Design Studio SINTECNA – Prof. Giuseppe Mancini CE Contractor Torino Scavi Manzone S.p.A. – General construction Year of completion 2006 212 The viaduct is part of the upgrading operation on the regional highway Laghi di Avigliana, the former State Road 589.This secondary extraurban artery (class C in the CNR standards) is being converted into a principal extraurban highway (class B), in the stretch in the City of Pinerolo from station 27+800 km to station 30+250 km, by improving its exchange systems with the main communication ways (principally State Road no. 23). At the intersection between SS 589 and SS 23 the construction of a traffic circle was envisaged, having three lanes and an internal radius of 91.00 m, to distribute the traffic into the various directions. Called for too is the construction of an overpass, SS 23 flying over the new traffic circle, thus freeing the bypass traffic from all the other flows. At the crossing with Corso Torino there was a grade intersection. Since the object was to free the state highway's route of the urban fabric, the construction of a high-speed road in cut was proposed, so as to underpass the crossing.This will be placed above site level and will be a two-lane traffic circle having an internal radius of 31.00 m. It will comprise two simply-supported viaducts in curve. Both viaducts display a section involving a ribbed prestressed-concrete plate of maximum depth 1.30 m. Its outside profile is rounded to make it fit better into the landscape.This solution, which today receives everybody's thorough approval for its safety and durability, offers the following advantages: • it has a significant structural mass that, even with reduced spans, makes it insensitive to the dynamic effects induced by the transit of vehicles; • it can harmoniously take on any form in plan; • it has a high guarantee of durability, because of its massive structure devoid of thin elements, because of the reduced extent of its exposed surface as compared with more traditional solutions (beams plus slabs), and because of the adoption of HDPE sheaths for the prestressing cables, wholly impenetrable by the chlorides of antifreeze salts, which will certainly be used for a considerable period of the year; • it provides the possibility of forming the section at design’s pleasure, and thus of facilitating its fit into the surrounding environment. Proposed for the case in question is a crosswise profile having sizeable curved fairings and a central zone of lower width, which gives the impression of high slendemess to an observer standing on the ground around it, even if his point of observation is but a short distance from the structures; • there is the possibility of pursuing the structural shape with the finish works (parapets, barriers, protections for the underlying crossings), so shaped as to harmonize the structure-finishings complex. The SS 23 viaduct on the traffic circle grafting it onto SS 589 has six spans.The two side spans at the end are 28 m long, and the four central spans are 33 m long.The structure is continuous-beam with intermediate bearings. Considering its height (not far above ground) and the reduced interference with the road system during construction phase, its construction was envisaged as in “standard shoring”, that is with formwork and strutting bearing on the ground, through a slab to distribute the forces.The construction methods call for a complex centering involving six successive phases, each of which involving the tensioning of the prestressing cables envisaged for the construction phases. Finally, when the pours have been completed, a further prestressing will be introduced into the final statics scheme through the use of a second series of cables, having two different types of trajectories.The piers have a structural geometry with a profile faired into the deck’s and a very limited longitudinal dimension (one meter) so as to not form a barrier effect for the observer glancing’at the panorama from below. On the outside of the viaduct a service sidewalk is envisaged with a parapet whose function is also that of noise barrier. It is composed of metal uprights and coloured polycarbonate panelling having a curved profile so as to fair into the deck section. In order to facilitate inspection and maintenance of the works inspection spaces are provided for the prestressing head ends.There is also the possibility of replacing the deck bearings without limiting traffic. CONSTRUCTION - Civil engineering Works 1- Cross section through viaduct at pier centreline. 2- Cross sections through deck •in span and at abutment centerline: reinforcings. 1 2 CONSTRUCTION - Civil engineering Works 213 View of the structure. 4- General plan. 5- Form for the pour of the deck. 6- De•tail,3-showing slack reinforcing and prestressing cables. 7- Centering to support the formwork. 3 4 6 5 214 CONSTRUCTION - Civil engineering Works 7 CONSTRUCTION - Civil engineering Works 215 “Roccaprebalza” viaduct Project A15 Roccaprebalza road viaduct (North carriageway) Location Cisa Motorway A15: upgrading of the motorway route at the Vigne viaduct Customer Autocamionale della Cisa S.p.A. Design Studio SINTECNA - Prof. Giuseppe Mancini CE Contractor L.A.S. S.c.a.r.1. Year of completion 2006 216 The viaduct displays a continuous-beam scheme having a single-light caisson section of variable depth, built cantilevered from the piers with span lengths of 120 m. Only in the end stretch where it is expected that landslips might take place was a statically-determinate span built, its length 45 m. On the pier shared with the continuous deck it utilized special adjustable keepers that permit the pier to freely move without generating stress states in the decks. Design opted for a mixed steel-concrete solution with steel webs and r.c. slabs that make possible segments of considerable length, although only relatively light pieces need be handled (the webs), the whole being completed with in-situ-poured top and bottom slabs. The hollow piers appear as shafts, running from 15 m to 87 m tall, of square cross section whose dimension varies with shaft height. The minimum width lies at around 25 m from the taller pier tops, so that the piers taller than 30 m display a trumpet profile that contributes to fining the structure, while at the same time ensuring for the taller shafts an optimum sizing against instabilities. The section of least dimensions displays plan dimensions of 6x6 m. For the pier and abutment foundations circular caissons filled with concrete were used, their diameters varying from 9 m to 14 m.This solution was dictated by the nature of the soils (fractured and scaly oxylites), by the considerable forces unloaded by the viaduct and by the need to counter landslips in the viaduct's end area.The viaduct in question is the first structure in Italy in which the caisson deck, built of wed segments cantileverwise from the pier, is of mixed structure, with the use of both outside prestressing and bonded-cable prestressing.This choice enabled construction of the 9-meter-long segments owing to the fact that the elements to be handled consisted of the steel webs only (and were thus of relatively low weight), a building-construction crane anchored to the pier being used. Once the webs were positioned they were connected together with a system of provisional guys and struts that made it possible to obtain the section form desired, the distortions necessary in the stretch in tangent being imposed as well to create the screw-like behaviour of the section tied to the changing crosswise slopes. Once the webs were blocked in definitive position the lower slab was poured, using precast predalles as throwaway forms. In the final phase the upper slab was poured, using a metal form sliding within the caisson, precast pilaster strips being used to anchor the upper prestressing cables. Once the tees were connected the outside continuity cables were threaded, being deflected by means of two full diaphragms placed at the quarter-spans, and finally they were tensioned to one-half design value. Thus the construction rises could be reduced. Only when the entire deck had been built and solidized, was the tensioning of all the outside cables completed, starting from the Parma side and ending on the La Spezia side. CONSTRUCTION - Civil engineering Works • 1- Cross section through deck in span (a) and at pier centerline (b). a b 1 CONSTRUCTION - Civil engineering Works 217 Cantilevered construction from the piers of the mixed steel-concrete struc•ture2-3-4. deck. 5- Detail of the connector reinforcings for the precast pilaster strips. 3 2 5 4 218 CONSTRUCTION - Civil engineering Works CONSTRUCTION - Civil engineering Works 219 “Sandro Pertini” bridge upgrade Project Sandro Pertini road bridge Location Macerata, Italy Client County of Macerata Design Prof. Gian Michele Calvi CE, Matteo Moratti CE Structural detailing Prof. Gian Michele Calvi CE, Matteo Moratti CE Architects Prof. Gian Michele Calvi CE, Matteo Moratti CE Contract management Studio Calvi s.r.l., Pavia, Italy General contractor A.T.I. Rosi Giancarlo Costruzioni Srl, G.S. Costruzioni Generali Srl, Cagnini Costruzioni Srl, Costruzioni Edili Sirolesi Srl, Dell’Orso Perforazioni Srl 220 In June 2005 the masonry bridge spanning the Potenza river near the town of Macerata (92 metres long with five 18 m spans) was closed to the vehicular and pedestrian traffic because of evidence of structural damage, apparently due to significant foundation settlement. The importance of the bridge (average traffic 24,000 vehicle/day) required a rapid intervention, that should have also addressed the problem of seismic safety (with an expected peak ground acceleration of about 0.25 g for a 10% probability of exceedence in 50 years). The architectural and historical relevance did not allow signigicant changes in the aesthetics of the bridge.The proposed solution was to built a new concrete bridge inside the old masonry one, only emerging with the new deck, wider than the original one to adequate the geometry to the present prescription for vehicular and pedestrian traffic. The final design and the work program were developed in ten days. Works were completed in 40 days. The conceptual design was very simple: 1. two piles (D=1,2 m, length 30 m) were drilled into the three existing piers and at the abutments; 2. all material above the arch structures was removed; 3. five transverse cross beams were casted above each pile couple; 4. thirteen high damping rubber bearings were installed, 2 on each abutment and 3 on each pier; 5. a deck composed of precast extruded beams was placed on temporary supports; 6. top slab and six diaphragm beams were casted in situ; 7. the temporary supports were removed; 8. the structure was completed with a waterproof membrane, protection, finishing, asphalt, parapets, joints, deck drainage, lighting systems, and traffic signals. CONSTRUCTION - Civil engineering Works • 1- Longitudinal section. 2- Deck plan. 1 2 CONSTRUCTION - Civil engineering Works 221 3 4 5 LEGEND 1 - Drilling 2 - Water bed 3 - Original concrete foundation 4 - Siffening foundation with micropiles for masonry piers 8 5 - Sands, silty sands and sandy silts 6 - Gravel, gravel with sands 7 - Argillaceous silts 8 - Sands with gravel 9 - Siltstone clays with thin sandy layers 6 7 222 9 CONSTRUCTION - Civil engineering Works Emptying of the bridge, with the heads of the piles already driven. 4- The emp•tied3-bridge. 5- Longitudinal section through the project site’s geology. 6- Longitudinal section. 7- Cross section. 8- Laying the aseismic isolations. 9- Laying the precast beams. CONSTRUCTION - Civil engineering Works 223 Cable-stayed footbridge over the Frodolfo river Project Cable-stayed footbridge over the Frodolfo river Location Bormio, (Italy) Client Bormio Municipality Structural detailing Prof. Gian Michele Calvi CE, Dario Compagnoni CE, Matteo Moratti CE Architect Prof. Gian Michele Calvi CE Contract Management Studio Calvi s.r.l., Pavia, Italy General contractor G.A.L. costruzioni, Bormio, Italy 224 The bridge has a single span of about 66 m passing over an important road and a river, is curved in plan and in elevation, the deck has a variable thickness of about 300 mm and is sustained by a single pylon, hinged at the base.The main structure has been mounted in four days, without any temporary support, using six identical prefabricated deck sections, each one being 12 m long, and a 35 m monolithic steel pylon to which the deck sections are anchored, by means of four cables each. The total construction cost has been approximately 500,000 €. The bridge is technologically highly innovative, light, beautifully inserted in the environment and very cost effective. The design choices were essentially guided by the environmental constraints: • no intermediate support was really possible, and only on the west side topography and building locations permitted a relatively easy construction of foundations; on the same side, an underground parking under construction provided some appropriate anchoring mass; • the beauty of the valley and the presence of an ancient stone bridge required a light structure, with minimum interference with the surroundings; • the construction time on site needed to be reduced to a minimum, to mitigate as much as possible traffic interruption on the main road. It was decided to design an asymmetric steel pylon, rotated both vertically (about 7 degrees) and horizontally, in order to optimize the force distribution. The pylon is made of a monolithic 35 m steel pipe (812 mm external diameter) with a second external co-axial pipe (850-1100 mm variable diameter) welded to the internal one by six radial steel wings). The pylon is hinged at the base and its position is essentially governed by the actual loading, with a variable inclination. Eleven tendons (52 mm maximum diameter) restrain the pylon at the ground. The deck is formed by five precast high performance concrete elements supported on 10 couples of thinner cables. Each segment has the same length (12 m) and the same radius of curvature both in plan (about 300 m) and in elevation (about 1200 m). The in–plane curved shape of the deck is effectively reacting to horizontal loads by arching action, whilst vertically the deck is free to rotate around a horizontal axis on the west side and is connected to the east abutments with a double-hinged 6 m long truss that allows vertical free movements and rotations of the deck. Pylon foundation, abutments and anchor mass for the fixed cables were constructed on site, taking advantage of the contemporary construction of an underground parking lot.The pylon was transported overnight in a single piece and mounted with two cranes; within the subsequent three days it was possible to position and anchor the five deck sections, prefabricated elsewhere. During construction, a temporary connection between the deck sections was provided by steel self centring couplers, later on included in concrete injections that made the deck fully continuous. The results of the complex nonlinear time-history simulations carried out during the design phase were later confirmed by in-situ dynamic testing, with induced vertical displacements of ± 180 mm. CONSTRUCTION - Civil engineering Works CONSTRUCTION - Civil engineering Works 225 Post-tensioned concrete plinth at pylon base. 2- Temporary self centring cou•plers1- (clockwise: plan view; section B-B; detail of the steel pin; section A-A RC transversal beam cast on site). 3- Main section of the deck (hatched zone indicates RC, dimensions in mm). 4- Main geometry of the footbridge frontal view from South. 5Horizontal hinged bearings at the West abutment. 6- Deformed shapes under live loads of the f. e. model (from left to right: South-East view; East view; plan view). 1 2 3 226 CONSTRUCTION - Civil engineering Works 6 5 4 CONSTRUCTION - Civil engineering Works 227 Bridge over Mazzocco creek Project SS16 Adriatica - Bypass of the settlements of Montesilvano and Marina di Città Sant’Angelo – job segment 1 – Road bridge over Mazzocco creek Location Pescara, Abruzzo, Italy Client ANAS S.p.A. Design Prof. M. P. Petrangeli CE, E. Cipolloni CE Management Contractor ANAS S.p.A. General contractor A&I Della Morte (Naples) - Impresa Martella, Pescara, Italy Year of completion 2008 228 The new stretch of the SS16 (State Road) bypass between Pescara and Montesilvano features, besides an 1800 m long tunnel, a new bridge over the Mazzocco creek, described here. Both the contracting agency and the local authorities considered the arch bridge to be a sine qua non for the project underway, even though the creek could have been crossed with a traditional prestressed-concrete-beam bridge, built by successive segments. Another item that could not be ignored was that the projected works had to be compatible with the future doubling envisaged, which would upgrade this section to the characteristics of already-existing SS16 alternate, thus obviating future demolitions. The construction procedures were so worked out as to not need centerings, which would have had to stay in place for a long time since they would be in the creek bed and there was no guarantee for the whole period of construction that the centering’s ground supports would not settle differentially, owing to the presence on a creek bank, revealed by soil studies, of waste material originating from the driving of an old tunnel. Mazzocco creek was crossed on a four-span bridge a total of 140 m long. The 70 m arch span founds on circular-section caissons 15m in diameter, of maximum depth 25 m. Pier 1 and the abutments found instead on 1200 piles up to 30 m in length, which had to assure, besides the required bearing capacity, a minimum strain so as not to induce drops in the arch thrust owing to interaction with the not especially good foundation soil. The piers, of lengths up to 14 m, are two-column frames, since deck width varies between 17.2 and 26.23 m. The decks were built with 4 precast concrete U-beams 1.6 m deep, prestressed with bonded strands, their length between 24 and 24.7 m. The first span was built instead with 18 double T beams 1 m deep. The 4 V beams, between piers 2 and 3, bear on the crosspiece connecting the five members constituting the arch. Each member, its double T section varying continuously from the base to the minimum section at the crown which is 1.20 m deep, comprises three precastings jointed in place. The central element of the three is prestressed with two post-tensioned cables of ten 0.6” super-strands, anchored on the two ends of the precasting. The connection of the members among themselves and to the foundation footing is effected by prestressing bars. The precastings were built on site to limit handling. For their launching and mounting two provisional struts 15 m tall were set up, each built with five Innocenti steel-pipe towers connected together and shearbraced, bearing on two provisional footings founded on 800 piles. In the first phase all 5+5 low elements were launched, bearing by means of supports on the caisson footings and on struts. After launching by means of a 300 ton crane of the central elements, the stitches were effected and the provisional struts unloaded, this being carried out progressively by means of the lowering of a series of large screws and sand-filled boxes placed below the provisional bearings of the precastings, the structure’s strain behaviour being constantly monitored to check on the correspondence of the shifts with theoretical. Thus was completed the launching of the deck beams and the subsequent pour of the slabs. CONSTRUCTION - Civil engineering Works • 1- Bridge plan. 1 CONSTRUCTION - Civil engineering Works 229 for the arch central precasting being struck. 3- Lower arch precasting •being2- Forms mounted. 4- Handling the precastings. 5- Detail of the provisional support for the precasting on the footing. 6- Longitudinal section. 7- Central precasting launch phase. 8- Detail of the precastings’ upper connections. 6 2 5 3 4 230 CONSTRUCTION - Civil engineering Works 7 8 CONSTRUCTION - Civil engineering Works 231 Bridge over the Sacco river Project Road bridge over the Sacco river Location Municipality of Sgurgola, Rome, Italy Client Consorzio Pegaso S.C.AR.L. Roma I.T.S. S.p.A. State Railway System – High Speed lines Design PROGEEST S.r.l., Prof. Arch. HC E. Siviero CE, Prof. R. Di Marco CE Structural engineering Enzo Siviero, Roberto Di Marco Architects Enzo Siviero Management Contractor Consorzio IRICAVUNO General contractor Consorzio IRICAVUNO Consorzio PEGASO S.C.AR.L. 232 The bridge over the Sacco river is one of a series of operations called for by the new highways system setup, itself made necessary by the construction of the new high-speed railway line between Rome and Naples. The solution adopted is an arch bridge built using high-performance curved precast-concrete elements. They are positioned on provisional supports and locked in place by completion pours.To balance the thrust, at the abutments the arch ends are connected by diagonal struts to the deck, which thus takes on the role of chain and is under tension. The moment arising from the eccentricity of this force relative to the arch thrust is balanced by the action of active tendons placed at the deck ends, so that the forces transmitted by the structure to the soil are practically vertical. To eliminate continuous forms, which significantly affect the structure’s overall cost, in the construction of the arches precast curved elements were used, of high-performance concrete, placed in position by the use of provisional supports between the spans and later solidized by in situ pours. In order to cut construction time, a solution was adopted for the deck construction involving precast beams completed by an in situ pour. To balance the thrust of the arches, which could be incompatible with the soil’s mechanical and strain characteristics, their ends at the abutments are connected by diagonal struts to the deck. It thus takes on the statics role of a chain and is thrown into tension. The moment given rise to through the eccentricity of this force relative to the arch thrust is balanced by a counter couple due to the action of active tendons anchored to the deck ends and by the corresponding reactions of the piles below the abutments, so that the forces transferred to ground are prevalently vertical. The structure has a total length of 132 meters and comprises two arches, 56 m in span with a 5.6 m camber, which sustain the deck connected to them at the crown and at the abutments. The structure’s “permeability” reduces its environmental impact and interference with the flow of water, increasing the flowrate and lowering the crosswise hydraulic thrust. Each arch is created by the assembly of 20 x 5 precast arch segments of high-performance concrete, having a 70 cm x 50 cm section.They are set side by side to create a structure 10 m wide, then solidized together by the pour of a concrete slab of 25 cm minimum depth. Since the bridge centerline is skew to the river’s flowline, the precast arch segments are mounted having a mutual longitudinal slide so as to follow this geometry. In each arch’s central zone the deck slab is directly connected to the arches by ribs of variable depth held up by the arches. At the abutments and the pier the support consists of precast inverted-T-section beams . The total width of the deck is 13.10 m. It is sized for a road having two 4.75-meter lanes and two sidewalks raised up and protected by guardrails. The abutment and pier foundations are built on large-diameter piles (150 cm), their length varying from 16 m at one of the abutments to 33 m at the central pier. CONSTRUCTION - Civil engineering Works • 1- Bridge side view. 1 CONSTRUCTION - Civil engineering Works 233 234 CONSTRUCTION - Civil engineering Works CONSTRUCTION - Civil engineering Works 235 Bridge over the Santa Caterina channel The design solution and the arrangement in plan ensure simplicity and lightness to the whole, in perfect harmony with the surrounding landscape and fitting with the environment. In plan, the highway bridge has a deck in the form of a parallelogram, whose major side is 64 m long, while the width is 12 m. As regards durability and resistance to weathering the choice of materials assures the structure the capacity to last if properly maintained. The structure’s symbolic significance too may be considered quite as durable. Costs are in proportion to function, to structure safety, to the advantages that the new structure produces, to the construction phases and schedules necessary to finish it, and to the positive judgement on the view of the whole at the end. The bridge has a basic characteristic: its centerline is skew to the river’s flowline. This design choice gives the structure a special characteristic, creating a very interesting foreshortening in perspective and a play of light and shadow. Its centerline forms a 36° angle with the river’s flowline, this being perceptible from some points of view but absolutely invisible from others. The result is, at times, a forced perspective that tends to lengthen the image laterally. In the same way, the deck and arch dimensions and the imposingness of the whole structure are legible only when compared with the human dimension, bearing witness to a careful search for proportion. Despite the strong dimensions the eye is not especially impressed by the beam depths, whether before or after the successive pours. Its juxtaposition with the existing bridge is natural: after having undergone restoration the older structure will be used as a foot bridge, while continuing to be a memory of the past of this part of the territory. Structurally speaking the bridge comprises the following principal reinforced-concrete elements: - a central parallelogram-plan arch 1.00 m deep, thrown across a 39-meter chord; - a horizontal parallelogram deck 1.00 m deep and a width perpendicular to the sides of 7.00 m; - along the lateral edges two wings are cantilevered, each 2.50 m wide, thus bringing total deck width to 12.00 m; - two diagonal lateral plates, 1.00 m thick, connect the central-arch springers with the end edges of the deck plate; - two support walls in the riverbed, created by continuous bulkheads 1.00 m thick, having a plan length of 12.5 m, thrust down to a depth of 22.00 m below the arch springer; - two support walls at the banks, built from continuous bulkheads 1.00m thick, having a length in plan of 12.50 m, thrust down to a depth of 18.00 m below the springer of the horizontal upper deck. Project Road bridge over the Santa Caterina Location Sant’Urbano, Padua, Italy Client Municipality of Sant’Urbano, Province of Padua Design PROGEEST S.r.l., Prof. HC E. Siviero arch. CE Structural engineering Enzo Siviero, Luigi Rebonato Architects Enzo Siviero Management Contractor Municipality of Sant’Urbano General contractor Impresa Locatelli, Impresa Thiene 1 236 CONSTRUCTION - Civil engineering Works • 1- Longitudinal section: slab reinforcings. 2- Cross section through deck. 2 CONSTRUCTION - Civil engineering Works 237 3 5 4 238 CONSTRUCTION - Civil engineering Works 3- Longitudinal section: foundations. 4- Plan of the highway route in which the •bridge is fit. 5- Longitudinal section: reinforcings of the arches and of the diagonal slabs. CONSTRUCTION - Civil engineering Works 239 Bridge over the Cimadolmo branch Project Road bridge over the Cimadolmo branch Location Cimadolmo, Treviso, Italy Client Province of Treviso Design PROGEEST S.r.l., Prof. Arch. HC E. Siviero CE Structural engineering Enzo Siviero, Luigi Rebonato, Federico Zago Architects Alessandro Stocco Management Contractor Province of Treviso – Lucio Bottan arch. General contractor F.lli PACCAGNAN S.p.A., Ponzano Veneto (Treviso) Year of completion 2009 240 As part of the general project for upgrading the roadway system to which S.P. 92 belongs, the Treviso Provincial Administration indicated its intention to widen the structures so as to enable them to take the carriageway common to type V CNR roads (extraurban C2 according to the new operating standards for highway construction, Ministerial Decree of 11 May 2001). This involved upgrading the carriageway to a total width of 9.50 m and inserting service sidewalks on both sides. During this phase the construction of just the deck holding the vehicle way is envisaged, while the sidewalks will have to await new financing. The considerable use of precasting technology for the slab enabled shortening the construction-yard phase, greatly reducing the inconveniences caused to traffic. The system designed envisaged the construction of six typological slabs combined in four types of segments to define the bridge plan for a total length of 420 m, broken down into 20 m spans. The deck comprises three principal full-web beams 1000 mm deep, spaced 3500 mm apart, connected to the 26 cm deep r.c. slab by Nelson-type rungs. The slab is constituted of precast plates having a 2 m module, broken down into two parts to cover the entire carriageway width. The plate depth coincides in the central portion with the slab’s finished depth, while in some areas (lateral relative to the plates) and in the zone where it is supported on the steel beams, the slab is lowered to permit an in situ pour of concrete, in order to bring about static continuity both longitudinally and crosswise, as well as with the steel beams below.The plates are so positioned as to supply the crosswise slope of the roadway plane, making the depth of the asphalt pavement constant over the entire roadway surface, and consistent with the behaviour of the centerline in plan. Envisaged are trestlework diaphragms (crosspieces) distributed at 4.00 m spacings and connected by diagonal shearbraces placed at the level of the lower flat arch in such fashion as to form a structure of considerable torsional stiffness, able to distribute the eccentric loads almost uniformly over the three principal deck beams. The total deck width is 10.70 m, of which 9.50 m are carriageway, while 60 cm for each side of the cross section are used to hold the guardrail and its cladding. On each pier and on the abutments elastofip-type bearings are called for, made up of a coupling of neoprene, steel and confined teflon, so as to create unidirectional bearings for the central beams, and multidirectional ones for the border beams, able to permit the shifts due to temperature changes or to creep. For dynamic forces of the instantaneous type (earthquake, braking) it is provided that the bearing for the central beam be fixed longitudinally as well, so as to distribute over each pier the dynamic forces falling to it. Called for anyway is the insertion of a fixed bearing into one of the two central piers. Called for on the abutments is the insertion of expansion joints able to take the shifts due to the summation of slow and dynamic forces. It has been ascertained, on the basis of preliminary calculations and after checking the original statics relationships, that the hollow box structure overlying the beams’ current support plane is not essential to the strength of the pier-pulvino complex and will thus be demolished (three sides). Therefore, the construction can be prospected, above the pulvino itself, of a continuous steelconcrete deck outfitted with expansion joints only at the abutments.The structure will appear slenderer than the preceding one (H=1.26 m versus H=1.58 m). User comfort will be increased and maintenance costs reduced owing to the radically reduced number of joints and bearings. Under the conditions indicated above, the carriageway can be widened to 9.50 m. In relation to traffic conditions (current and future) the placement of lateral containment barriers is envisaged, sized for an H2 impact-severity index. On the outside of the curbing the placement of a metal cladding 2.80 m high is called for, its function to clad the deck as well as to provide partial protection of the roadway surface. CONSTRUCTION - Civil engineering Works 1- Axonometric view of the plate constituting the floor slab. 2- Axonometric ex•ploded view of the floor slab. 3- The paired piers, placed with a 20 m interaxial distance. 4-5 Laying the precast slabs. 1 1. precast plate 2. completion pour 3. stiffening socle 4. binder 5. finish layer 2 3 5 4 CONSTRUCTION - Civil engineering Works 241 “Isola della Scala” bridge Project Road bridge Location Isola della Scala, Verona, Italy Client ANAS S.p.A. (Italian Road Administration) Original design ANAS S.p.A. Redraft design and structural engineering Prof. Enzo Siviero CE, Prof. Bruno Briseghella CE, Prof. Tobia Zordan CE The project presented concerns a flyover which construction was completed in 2007, located in Verona - Isola della Scala, Italy. The total length of the structure is approximately of 400m with 13 spans. According to the designers’ knowledge, this is at the moment the longest IAB ever built. The construction of the bridge, initiated in 2001 as a simply supported flyover, was interrupted after 2 years because of economical problems. At the time of interruption, all pre-stressed concrete girders had been nevertheless purchased. At the beginning of 2006, works restarted with a new proposal, aiming to improve the quality of the structure and change the static scheme from simply supported to integral abutment without changing the built parts, namely, the rigid abutments and the piers, in the purpose of not to increase the cost of the final structure. During refurbishment, in order to achieve an IAB eliminating all bearings and expansion joints, continuity was attained at the pier caps with the casting of concrete diaphragms between the beams of adjacent spans, in order to achieve negative moment resistance. Hogging moment resistance was also determined with a similar technique at the abutments for the end bays. Connection between adjacent beams was carried out casting the concrete of the diaphragms also inside the V-shaped girders for a length of 2 meters. The bridge was opened to traffic in 2007; no mentionable damages have been noticed until now, except for some cracks in the approach slabs. Management Contractor ANAS S.p.A. General contractor Nuova Bitumi srl, Trento Year of completion 2007 242 CONSTRUCTION - Civil engineering Works 1- Typical cross section. 2- Longitudinal section at the pier. 3-4 Detail of the deck •reinforcings. 5- Typical crosspiece during construction. 6- The bridge in an advanced phase of construction. 7- Viaduct scheme. 2 1 4 3 6 5 7 CONSTRUCTION - Civil engineering Works 243 The “Strada dei Parchi” Project The first most urgent operations to make safe the structures involved in the earthquake of April 6th 2009 Location Motorway A24 – Various viaducts between 99+000 km and 116+500 km Motorway A25 - Popoli viaduct Client Strada dei Parchi S.p.A. Firm Responsible for the proceeding Strada dei Parchi S.p.A. – Marco Carlo Rocchi CE Design SPEA Ingegneria Europea – Fulvio di Taddeo CE Supervision of construction Strada dei Parchi S.p.A. – Luca Bartoccini CE General contractor TOTO S.p.A. Year of completion 2009 Main features The project calls for the provisional restoration to function of the structures, with a view to re-opening the following viaducts to traffic: A24 - Fornaca viaduct, A24 - Genzano viaduct, A24 - Raio viaduct, A24 - Aterno viaduct, A24 - S.S. 17 viaduct, A24 - Fosso Vetoio viaduct A24 - Pettino viaduct A24 - S. Sisto viaduct A24 - S.Giacomo viaduct A24 - viaduct on the L’Aquila Est interchange A24 - Le Campane viaduct A24 - Palude viaduct A24 - Viadotto Vigne Basse A24 - Costa del Molino viaduct A25 - Popoli viaduct 244 On April 6th 2009 at 3.32 AM the L’Aquila area was struck by a strong earthquake (Richter magnitude (Ml) of 5.8, Moment magnitude (Mw) of 6.3, 8th-9th degree on the Mercalli scale).The earthquake sequence continued developing with a great many aftershocks, more than 20,000 of them recorded as of June 10th 2009. 31 of them had a M1 lying between 3.5 and 5 and three had a magnitude exceeding 5 (April 6th M1=5.8, April 7th M1=5.3, April 9th Ml=5.1) The plan distribution of the aftershocks brings out very well the area concerned by the earthquake sequence, extending for more than 30 km in the NW-SE direction, parallel to the axis of the Apennine chain. The earthquakes of the sequence took place for the most part in the upper crust, a depth of 1012 km. Only the event Ml=5.3 of April 7th to the SE of L’Aquila was as deep as 15 km.The data gathered to date (seismicity, GPS, SAR, geology) agree in identifying the structure responsible for the main shock as a fault having direct movement that extends some 15 km in the NW-SE direction with a SW dip. Its extension on the surface is located in correspondence with the Paganica fault. The damage in the epicenter zone was due, not only to the size of the earthquake (and therefore to its magnitude), but also to the break’s direction of propagation and to the soil geology. In particular, the major damage is observed in the direction along which the faulting propagates (effect of the source directivity) and is amplified in the areas where “soft” sediments (such as alluvial deposits, earth fill, etc.) lie on the surface. In the case of the L’Aquila earthquake, the break associated with the April 6th event was propagated from below upwards (and therefore towards the city of L’Aquila) and from northwest to southeast, towards the Aterno valley. Motorways A24 and A25 have a total length of 281.4 km, and feature 174 viaducts of various length and typology.Their total length sums to 58.3 km (21% of highway length).They were built between the end of the sixties and the first half of the eighties. Added to these are 77 overcrossings so that there is a high incidence of crossing structures, owing to the territory’s orography. The seismic event involved an extensive area crossed by motorways A24 and A25, causing much damage to the infrastructures. After the shock that struck at 3.32AM of April 6th 2009, Strada dei Parchi SpA activated its own engineering structures and those of the principal companies in the sector to carry out checks on the infrastructures managed. The most serious damage observed was that done to the bearings of forty spans on nine viaducts. The consequent discontinuities at the expansion joints exhibited 10-20 cm steps. The damage undergone by the roadway infrastructures varied depending on their zone. Three motorway stretches (two on A24 and one on A25) can in fact be identified exhibiting very obvious problems: • A24 –from the Tornimparte interchange to that of L’Aquila West, featuring moderate damage to viaducts and settlements of embankments at the viaduct abutments; • A24 –from the L’Aquila West interchange to that of Assergi, featuring both important damage to the viaducts (particularly to the S.Sisto viaduct), and breakage of the motorway embankment and its settlements at the abutments; • A25 –from the exit for Pratola Peligna to the exit for Bussi, with motorway embankment settlements at the abutments of some viaducts and serious damage to the Popoli viaduct. The activities of monitoring the structures started up by Strada dei Parchi SpA and the very first repairs carried out right from the start of the event kept the motorway open for rescue vehicles. On the other hand, the activities necessary to immediately restore the infrastructures enabled reopening to traffic the stretch lying between the Tornimparte exit and that of L’Aquila West at 8.00PM of April 6th, without any limitations on speed. On this stretch Civil Defence anyway kept in force the limitation for vehicles heavier than 7.5 tons in order to handle the rescue vehicle flows. CONSTRUCTION - Civil engineering Works 1- Map of L’Aquila area, showing active faults. 2- Raio viaduct: yielding of the •abutment body. The motorway stretch between the L’Aquila West station and that of L’Aquila East was instead reopened to traffic on Friday April 10th at 5.50 PM on the S.Sisto viaduct.This involved using one two-lane carriageway with traffic in both directions, but without weight limits and with the sole constraint that top speed be limited to 60 kmph. For the left carriageway the situation was instead more serious and more restoration time was needed. On A25, in the stretch lying between the station of Pratola Peligna and the Bussi station, the critical element was the Popoli viaduct, with separate carriageways. In particular the left carriageway (Pescara to Rome) was made transitable on an emergency basis only for light vehicles right from the first minutes after the earthquake.Thanks to the restoration operations carried out, on Thursday afternoon of April 9th all the weight constraints that conditioned transitability could be removed. Traffic then ran in both senses of flow on a single carriageway up through June 5th 2009, when the detour was removed and circulation returned to normal. In all these operations, contracted to Toto SpA through the Extreme Urgency procedure, a daily average number of eighty persons were working with the numerous equipment items available (by-bridges, cranes, hoisting equipment, trucks, cutters, finishing machines, rollers, etc.) as well as seventy persons between engineers and workmen of Strada dei Parchi SpA. To be highlighted in particular is the uncommon spirit of self-sacrifice and emotional involvement exhibited by the executives, engineers and workmen involved in the job, who worked under conditions truly at the limit. Only thanks to this spirit of sacrifice was it possible to assure full-capacity driving along the motorway on April 10th. 1 2 CONSTRUCTION - Civil engineering Works 245 EPICENTRO DEL SISMA SEISM’S EPICENTRE 3 4 246 5 CONSTRUCTION - Civil engineering Works involved in the earthquake of April 6 2009. 4- San Sisto viaduct: breaka•ge 3-ofAreas the roller and detachment of rack from the rack-roller supports. 5- San Sisto th viaduct: step resulting from breakage of the supports. 6- Vigne Basse viaduct: yielding of the embankment on the abutment body. 7- Popoli viaduct: step on the platform owing to the expulsion of the roller from its support. 8- Le Campane viaduct: complete expulsion of the roller from the roller-rack support. 9- Vigne Basse viaduct: disarrangement of the rack-and-roller support. 10- Popoli viaduct: expulsion of the roller of the rack-and-roller support at the abutment. 11- Popoli viaduct: expulsion of the rollers of the rack-and-roller supports. 7 6 8 9 10 11 CONSTRUCTION - Civil engineering Works 247 A24 – Completion of the motorway Roma-L’Aquila-Teramo Project A24 – Completion of the motorway Roma-L’Aquila-Teramo Location Motorway A24 - Villa Vomano-Teramo stretch Client Strada dei Parchi S.p.A. Firm Responsible for the proceeding Strada dei Parchi S.p.A. – Marco Carlo Rocchi CE Design TOTO S.p.A. – Vincenzo Consalvo CE Supervision of construction Strada dei Parchi S.p.A. – Ernesto Maffei CE General contractor TOTO S.p.A. Year of completion 2009 The job involved the completion of motorway A24 in the Villa Vomano-Teramo stretch, by the reconstruction of the east carriageway for a length of 5.7 km. The principal structures included in the project are: • Vomano viaduct: a structure of 770 m long, on 44 m spans whose first two spans on the Rome side run on a continuous beam having a mixed steel-concrete structure.The remaining part runs on simply-supported prestressed-concrete decks having spans from 26.70 m to 35.40 m, and a continuous-slab deck.The viaduct displays over its entire length a left curve in plan.The roadway platform of the new east carriageway is a total 13.00 m wide, with two curbings of 65 cm and 115 cm, and a carriageway 11.20 m wide. • S. Antonio viaduct: a structure having a total length of 2500 m with simply-supported beams and 33.80 m and 35.30 m spans, with a continuous slab in 500-meter-long segments, which subdivides the viaduct into five stretches.The roadway platform is identical to that described above for the Vomano viaduct. • Carestia Tunnel: the structure has a total length of 824 m with a route in plan and a grade that follows the existing adjacent west-carriageway tunnel of the same name.The soils involved in the driving are Miocene marls, mantled by layers of detritus. The stretch in driven tunnel is 731 m long, while at the tunnel mouths there are two stretches in cut-and-cover tunnel 49 m long on the L’Aquila side and 33 m long on the Teramo side. The distance between the two tunnel centerlines is 40 meters. The average section is 173 square meters with a driving width of 15.85 m and a height of 13.40 m, and a tunnel soffit profile having a radius of 6.77 m.The tunnel roof reaches peak heights of 60 meters above the soffit in the central stretch, while it stays rather moderate (10.20 m) at the two mouths for a total stretch of 300 m. At spacings of 300 m are two emergency foot by-passes.The tunnel was outfitted with modern safety systems. 1 248 CONSTRUCTION - Civil engineering Works A24 Towards L’Aquila 1- A24: Panoramic view of the Vomano viaduct. 2- A24: Panoramic view of the S. •Antonio viaduct. 3- A24: Mouth of the new barrel of the Carestia tunnel. 1.Vomano viaduct 2. S. Antonio viaduct 3. Carestia tunnel 4. Underpass transitable by car 5. Subway 6. Interchange underpass 7. Embankment 8. Abutment wall (BVV) 9. Beams field. 10. Begin job segment. A24 Towards Teramo 2 3 CONSTRUCTION - Civil engineering Works 249 “S. Antonio” viaduct Project Motorway A24 – Rome-L’Aquila Teramo – Completion of the doubling between Villa Vomano and Teramo – the new S. Antonio viaduct Location Villa Vomano, Teramo, Abruzzo, Italy Client Strada Dei Parchi S.p.a Holder of the Motorway A24 Rome-L’Aquila Teramo concession for ANAS Design Prof. M. P. Petrangeli CE Management Contractor Strada Dei Parchi S.p.a. General contractor TOTO Costruzioni S.p.A., Chieti, Italy Year of completion 2007 250 The operation is necessary to doubling the roadway in the motorway’s last stretch of remaining single-lane-per-carriageway; it runs from Villa Vomana to Teramo. The job as designed, its overall amount being 110 million euros, consists of building all the structures needed for doubling the stretch. Among the structures, the S. Antonio viaduct is the most important economically, but also engineeringwise and construction-wise. It comprises 72 spans 35 m in length with decks comprising two precast beams and a continuous slab poured in place. The essential aspects in addition to those just mentioned concern the study of this viaduct’s foundations. In the stretch in question, the infrastructure in fact runs through many landslip-prone areas. This fact led the designers of the existing viaduct 20 years ago to use caisson foundations for all the piers. In our case, careful study of the site geomorphology led to a differentiation of the foundation type. In fact, for the valley bottom areas the choice fell on more economical foundations on piles (1500). The Decks The decks are built of precast U beams 2.0 m deep, prestressed with bonded cables (80T15). The beams are connected in place by the pour of the upper concrete slab 25 cm deep. Continuity under horizontal forces is provided by the slab, which at the beam heads, owing to expedients aimed at reducing its depth, enables transfer of the longitudinal stresses in its own plane and hence on the one hand the use of the technique of precasting the beams on a supported scheme (with obvious economic and construction-time advantages) and on the other the possibility of seismically isolating the viaducts (Precast beams: 45 MPa; In situ pours: 30 MPa; Concrete incidence: 7.5 m3/ml; Steel: slack for r.c. fy = 430 MPa; incidence: 200 kg/m3; Bounded-cable prestressing: fptk = 1860 MPa; incidence: 14.5 kg/m2; Cross prestressing bars: fptk = 1230 MPa; incidence: 1,8 kg/m2). Seismic isolation It was mentioned that the site’s strong seismicity (ag=0.25) and the need to limit the forces at the foundation led to widespread use of seismic isolation of the deck from the substructures. In fact, the site’s orography and the constraints on the design grade profile (the viaduct lies at the mouth of an existing tunnel) demanded piers of quite variable height, though always less than 18.01 m, and hence an irregular viaduct, low ductility and high foundation stresses. Thus, seismic isolation both crosswise and longitudinally was obligatory. The viaduct was broken down into five sub viaducts having a varying number of spans (an average of 15), whose constraints scheme envisages, longitudinally, connection with elastomer isolations at the five central piers and moveable constraints on all the other piers and abutments. In the crosswise direction fixed constraints on the abutments or joint piers and elastomer isolations of varying stiffness on all other piers. By acting on the isolations’ stiffnesses (32000kN/m ÷ 80000kN/m), the forces on the foundation could be regularized and diffused practically uniformly over all piers, whatever be their height. The result was the adoption of joint devices and most especially of slides for the moveable bearings, of significant dimensions: (l 260 mm; t 150 mm). CONSTRUCTION - Civil engineering Works • 1- General plan, from pier 0 to pier 45. 1 CONSTRUCTION - Civil engineering Works 251 for the foundation caissons (Ø = 12 m; h = 20 m). 3- Construc•tion2-ofExcavation a prestressed beam. 4- The beam precasting field was located in the West construction yard. In view is the tensioning head for the adherent-strand prestressing cables. 5- Longitudinal profile: new East carriageway works. 6- Cross section through prestressed-concrete beam. 7- Deck construction phase, with the launch of the beams by steel launch car bearing on the piers. 8- The new viaduct: in view is the S. Antonio ditch, repositioned and diverted between the two viaducts. 9- Precast beam plan. 5 6 2 3 4 252 7 CONSTRUCTION - Civil engineering Works 8 9 CONSTRUCTION - Civil engineering Works 253 Viaduct for the Algeria East-West Motorway Project Road viaduct Location Algeria, El Affroun-Hoceinia job segment Customer A.N.A. National Motorway Agency Design Studio SINTECNA – Prof. Giuseppe Mancini CE Contractor Cooperativa Muratori & Cementisti CMC, Ravenna The viaducts were built as part of the construction of a stretch of 15 kilometers of the EastWest motorway in Algeria. Both were built of prestressed prefabricated reinforced-concrete segments having a caisson cross section. The structure at station 50.1 kilometers comprised a continuous deck of two separate carriageways, each of five spans having end spans 45.50 m long and intermediate spans 70 or 80 m long. Both carriageways are in curve, its plan radius 500 m. The structure at station 49.2 kilometers also comprises a continuous deck of two separate carriageways. It has eight or nine spans, each having end spans of 35 m or 45 m and intermediate spans of 50, 60, 70 or 80 meters. Both carriageways are in curve, its plan radius 500 m. The 15.57 m wide individual carriageway was built having a single-light caisson section, its depth varying from 2.80 m (in midspan) to 4.00 m (at the piertop). Both viaducts were seismically isolated using elastoplastic dissipators both longitudinally, at one abutment, and crosswise (at the piers).The degree of seismicity corresponds to a peak acceleration at the ground of 0.35 g. The foundations are on 1200 mm diameter piles. The construction system called for precast segments using the “short line” system, the segment earlier cast being used as form wall for the next one. Launching was effected by a launch car, the segments were mounted with provisional prestressing bars; the tee prestressing cables being subsequently tensioned. Year of completion 2007 254 CONSTRUCTION - Civil engineering Works 1-. Cross section through double-deck viaduct. 2- Structural steel for the span •segment. 1 2 CONSTRUCTION - Civil engineering Works 255 and installation of the deck precast segments. 5- Structural steel •for3-4the Handling pierhead segment. 6- Steel reinforcing of the segment. 7- Dissipator for the structure’s seismic isolation. 6 3 5 4 256 CONSTRUCTION - Civil engineering Works 7 CONSTRUCTION - Civil engineering Works 257 MAXXI – Center for the contemporary arts Winner A.I.C.A.P. Award 2009 for Structural Concrete Works - Category “Buildings” Project MAXXI – National Museum of Arts of the XXI Century Location Rome, Italy Customer Ministry for Cultural Assets and Activities – Department for architecture and contemporary art Creation Ministry of Infrastructure and Transport – Public Works Superintendence of Regione Lazio: Angelo Balducci R.U.P./Proceedings’ person in charge: Roberto Linetti – Construction yard management: Roberto Tartaro Architectural aspects’ operating director: Mario Avagnina Architectural design Designers: Zaha Hadid – Patrik Schumacher Project leader: Gianluca Racana (Zaha Hadid Limited) Structural consultants Anthony Hunt Ass., OK Design Group In Rome’s Flaminio district, nearby the capital’s new Auditorium, has risen the MAXXI, the national museum for the arts of the 21st (XXI) century, conceived by architect Zaha Hadid. Its construction began in 2003, in a construction yard of experiment and innovation.The new structure, which houses museums and cultural activities as well as workshops and exposition spaces, brought about a great transformation of the entire block. And this even if the design solution adopted took its point of departure from a reading of the context, configuring a fabric and a volume in continuity with the strictly horizontal lines of the surroundings. Entrance to the MAXXI is gained in the heart of the block. From the building-high hall access is had to two museums – Maxxi Art and Maxxi architecture – and to the reception services, the cafeteria, the book shop and the spaces for temporary expositions. Outside, a foot route insinuated below the overhanging volumes follows the building plan, restoring an urban connection interrupted by the earlier military installation occupying the lot. The architectural and structural elements connoting the oeuvre basically number two: the walls that delimit the exposition galleries and that determine the interlacing of the volumes; and the transparent roof that naturally lights the rooms. The concrete wall is the element organizing space, while the roof system is the highly innovatory technological and systems element. In fact, integrated into the roof are the skylightframe elements, the devices for controlling natural lighting, the artificial lighting fixtures, and mechanisms for limiting heat from solar irradiation.The roof system comprises a dual glazing and is protected on the outside by a metalgrille sunshade that, besides screening light, acts as walkways for maintenance purposes. Cement concrete (self-compacting concrete, SCC) is the MAXXI’s true protagonist. In fact of r.c. are the walls characterizing its form and structure, as too are the horizontal surfaces and the roof blades, entirely clad with fibre-reinforced concrete (GRC). Concrete also forms a large part of the finishings, such as surfaces in view, floorings and furnishings. Final construction design Structural design: Studio S.P.C. S.r.l. Giorgio Croci – Aymen Herzalla Geotechnical consulting: V. M. Santoro Specialist consulting: A. Viskovic, S. Di Cintio, M. Francini Assistants for the structural design: F. Croci, S. Di Carlo, I. De Rossi, A. Bozzetti, C. Russo. Steel staircase and “monocoque” floor design: Studio E.D. In. s.r.l. - Fabio Brancaleoni, Marcello Colasanti SCC mix design consultant: Mario Collepardi Structural design validator: Antonio Maffey Construction Syndicate: MAXXI 2006 Group leader: ITALIANA COSTRUZIONI S.p.A. (Group Navarra) Assignor: S.A.C. Società Appalti Costruzioni S.p.A. (Group Cerasi) Prime Contractor: Marco Odoardi Construction site engineering manager: Roberto Rossi Construction yard chief: Gianni Scenna Assistant construction yard chief: Luigi Carducci Engineering office: Daniele Centurioni, Silvia La Pergola, Fabio Ceci Design coordination, execution of systems: Claudio Passini Accounting Office: Roberto Cascino, Enrico Bottacchiari Photographs Iwan Baan 258 CONSTRUCTION - Buildings CONSTRUCTION - Buildings 259 • 1- Ground-floor plan. 2- Section through building. 1 260 CONSTRUCTION - Buildings 2 11 CONSTRUCTION - Buildings 261 “Olympic Palavela” Project The renewal of “Palavela” Location Turin, Italy Client Agenzia Torino 2006 Final design ing. Arnaldo De Bernardi, arch. Gae Aulenti, ing. G. Siniscalco, arch. C. Roluti, arch. S. Basso, arch. M. Filippi, ing. G.C. Gramoni, arch. F. Quadri, ing. W. Peisino, ing. G. Forte, ing. E. Rosati Construction design ing. Valerio Actis Grosso (Project Manager), ing. Giovanni Vallino Costassa (Structural engineer) Yard management prof. ing. Giorgio Siniscalco (SI.ME.TE Snc) General contractor A.T.I. (Maire Engineering SpA, Impresa Costruzioni Rosso Geom. Francesco & Figli SpA, Keltermica Cordero) The affairs of the Palavela (“sail hall”) go back to 1958. In that year, as part of the Italia 61 exposition (organized in the Piedmontese capital to celebrate the centennial of Italy’s unity), a competition was promoted for the design of a building to house the Fashion and Costumes event.The winning solution was a smooth reinforced-concrete box vault, bearing on three points and built using procedures like those used in the construction of the Centre des nouvelles industries et technologies, built between 1956 and 1958 in the Défense quarter. The roof has a hexagonal plan inscribed in a circle 150 m in diameter, and consists of a self-bearing reinforced – and prestressed-concrete shell.The height at the crown of the arches is 29.00 m, while the composite vault roofs an area of 14,625 square metres; the volume enclosed is 332,000 cubic metres.The vault structure consists of two slabs, each 60 mm deep, developing over the entire roof and connected together by continuous longitudinal and crosswise ribs; its 1.30 m gross depth includes a transitable interspace 1.18 m high.The continuous monitorings the structure was subjected to over the years gave results so encouraging as to include the building in the list of works potentially useable for the competition outfittings of the 2006 Winter Olympics. In fact, its restructuring aimed at the creation of plant for artistic ice-skating and for short-track. The new building, wrapped by its original roof, comprises two bodies set close together, with a reticular steel roof that, although at different elevations, connects them together. The southeast-southwest body is assigned to spectators of sectors 1 and 2 (7196 seats), and the northeast-northwest body is assigned to the “Olympic family”, to the athletes and to the media (1062 seats) for a total of 8258 seats. Structurally, the two building bodies are supported by parallel septums, on which the floor structures are made to bear as are the precast seating tiers, and by the perimetral walls. The bearing septums were built of reinforced concrete with a fair-face finish. Self Compacting Concrete (SCC) Unical SpA - Gruppo BuzziUnicem Formworks Doka Italia SpA 262 CONSTRUCTION - Buildings Images from the files (1958-1961) of phases in the construction of the Pa•lavela1-2-(“Sail palace”). 3- The sail roof was given a preliminary restoration: one of no particular significance since careful monitoring over the years had brought out that the building’s structural integrity and its surfaces had remained very nearly perfect. 1 2 3 CONSTRUCTION - Buildings 263 of the new building’s structure were created with fair-face con•crete,4- Thethe elements structure having to perform an architectural and aesthetic task as well. Thus design opted for self-compacting mixes, capable of assuring both high mechanical performance and aesthetic beauty, besides meeting the specific pour requisites tied to so particular a construction job. 5- Design envisaged for the Ice Palace the construction of a galvanized steel reticular roof, given the necessary soundabsorbent and sound-insulation panelling. 6- The sports facility’s plan: the ground projection of the hexagonal sail roof completely encloses the Ice Palace structure. 7- Phases in the construction, by in situ pour, of the tank that holds the ice-skating rink. 8- Section through the building. 9- Detail of the facade of the new Ice Palace during the final finish phases: the mix design and the special care taken in carrying out the pours made it possible to create quality concrete surfaces, which at the same time became the sign characterizing the entire oeuvre. 4 5 6 7 8 9 264 CONSTRUCTION - Buildings CONSTRUCTION - Buildings 265 New Bocconi University Project “Bocconi 2000” of Bocconi University (enlargement) Location Milan, Italy Client Università commerciale Luigi Bocconi, Milano Client representative Geom. Nicolò Di Blasi Architect Grafton Studio, Dublino - arch. Shelley McNamara, arch. Yvonne Farrel Design team Gerard Carty, Philippe O'Sullivan, Emmett Scanlon Project Architect Simona Castelli The new building housing Milan’s Luigi Bocconi Business University, officially opened on October 31st last, completes the historic campus – conceived by Giuseppe Pagano a little more than seventy years ago and enlarged to a design by Giovanni Muzio and Ignazio Gardella – and becomes the whole university complex’s new “entrance gate”. The construction stands at the intersection of Viale Bligny and Via Roentgen on a 60 m x 150 m lot. Its functional program envisages that on the 68,000 square metres of walking surface a quarter of the university’s needs be housed, among which the offices, the departments, the classrooms, the exposition zone and the great hall seating a thousand. Characterizing the oeuvre too is the complex structural design worked out: the sophisticated foundations, which reach down more than 14 m below site level, the traditional continuous concrete raft 2-3 metres deep, the prestressed-concrete floor structures on the basement levels, and the enormous wall beams, with thicknesses of 400 mm, heights up to 30 m and 24 m spacings. To build the enlargement of Milan’s Bocconi, concrete was used to pour almost the whole of the bearing structures, which remain in view on the interiors and in some parts on the outside too. In particular, for the wall beams, the bearing septums, the roof beams and the great hall’s roof structure, self-compacting concrete (SCC) was used, a material of long-lasting workability that ensures greater compactness of the pours and therefore better quality and a more uniform fair face in terms of aspect and colour, as well as an improvement in the oeuvre’s mechanical strength and durability. Many reasons led to this construction and technological choice: first of all, the design’s architectural and structural complexity, which meant the need for thickly-laced reinforcing units that would not have permitted the introduction of vibration equipment, the heavy stresses in the hardest-working areas, the high ambient temperatures and the jobsite’s location right in downtown Milan. Co-workers Lennart Breternitz, Matthew Beattie, Philip Comerford, Miriam Dunn, Andreas Degn, Ann Henry, David Leech, John Barry Lowe, Eavan Meagher, Orla Murphy, Aoibheann Ni Mhearainn, Kieran O'Brien, Sterrin O’Shea, Eoghan O’Shea, Michael Pike, Anna Ryan, Maurizio Scalera, Ansgar Staudt, Gavin Wheatley Structural design and supervision of construction Studio Pereira, Milano - ing. Emilio Pereira, ing Vincenzo Collina, ing. Massimo Sandrelli, ing. Silvio Valloni On-site building supervision Progetto CMR - Marco Ferrario, Danila Aimone, Maurizio Cantoni, Claudio Pin Utility systems design Amman Progetti Lighting consultant Metis - Claudio Valent, Marinella Patetta Interior design Avenue Architects - arch. Dante Bonuccelli Acoustic and electrical consultant ARP Service, Paolo Molina Fire-fighting consultant ing. Silvestre Mistretta General Contractor GDM Costruzioni S.p.a. Photographs UNICAL, Studio Pereira, A. Faresin, Redazione iiC 266 CONSTRUCTION - Buildings • 1- Floor plan. 2- Construction of the basement-levels’ r.c. bearing septums. 1 2 CONSTRUCTION - Buildings 267 First-basement-floor plan. 4-5 Box elements composing the above-ground bea•ring3-structure. 6- Cross section through building. It shows the common underground base and the breakdown of the standing portion into distinct bodies. 7- Installing a floor structure’s slack reinforcings and its prestressing. 3 5 4 7 6 268 CONSTRUCTION - Buildings CONSTRUCTION - Buildings 269 Milanofiori 2000 – Corporate Center Project Milanofiori 2000 – Corporate Center (Segments B and C1) Location Milan, Italy Client Brioschi Sviluppo Immobiliare spa Design Erick van Egeraat, Rotterdam Structural engineer and supervision of construction Redesco srl, ing. Mauro E. Giuliani, ing. Gianluca Vesa, Milan General contractor Unionbau srl Coordination of final design, general supervision of construction Intertecno spa, Milan 270 The job is the first part of the Milanofiori 2000 development project. Located nearby the MilanGenoa motorway, it is also served by the subway’s line 2. It consists of a large plate housing two floors above ground of parking and a raised plaza at the elevation of the subway’s loading platform, i.e. at 6 m above site level. Three nine-storey office buildings stand up from this foot plaza; on it space is found for business activities, dining and refreshment, and sundry services. The built area is 70,000 square meters, plus another 19,500 for site-level parking. The structures feature an inclined lay of the plans of the standing buildings, which must be wed with the orthogonal grid of the underlying parking structures.They are built of solid concrete plates. The buildings’ typical grid (they feature irregular projections on their sides and large free-plan openings too) is 9 m by 6 m, arranged parallelogram-wise with a 73° minor angle. The parking grid is square, 8.1 m on a side. The columns, their dimensions kept limited, are typically in reinforced concrete, with a steel-concrete composite section for the buildings’ lower floors. Right from the start of the study of possible structural alternatives to serve the buildings’ architecture with economy and speed of execution of the design, the solid-r.c.-slabs solution, cast over industrialized formwork, was seen to be most advantageous. Analysis of the geotechnical data and the value of the acting loads yielded the selection of an indirect foundations on r.c. piles drilled using the continuous helix technology. Three types of piles are distinguished: a. 80 cm diameter piles, 21.5m long, with Pnom = 2500kN; b. 60 cm diameter piles 21.5m long, with Pnom = 1400kN; c. 60cm diameter piles 11.5m long, with, Pnom = 875kN. The parking area columns are of r.c., of typical circular section 50 cm in diameter. Columns of different dimensions and types are envisaged in the standing buildings The fire resistance requirement is R90. The columns in the standing buildings are typically circular in form 50 to 70 cm in diameter, with a composite steel-concrete type, which includes a steel H-section. The outer concrete of the columns is not only requested by fire protection, but is considered as working with the steel column to provide the necessary bearing capacity. The deck of the first floor above ground (second parking level) and the deck at plaza elevation consist of solid r.c. plates, one 28 cm deep having REI90 fire characteristics and the other 400 mm deep with REI180 fire characteristics.Their construction is envisaged by in situ casting over industrialized modular forms. The plate fields’ plan dimensions vary depending on architectural layout. The typical plate dimensions are 8.10 m x 8.10 m. A dual grid of two-way reinforcing bars is necessary, with densely reinforced zones on the extrados at the columns and on the soffit in span at points where the fields are most highly stressed. Prefabricated bundles of bars were used and unrolled on site in order to achieve the correct spacings, speed up the construction time and reduce the placing price. A specific shear reinforcing against punching was included at the columns. The offices floor deck comprises solid r.c. plates 300 mm deep with REI90 fire characteristics. Its construction is envisaged by in situ casting over industrialized modular forms. The plan dimensions of the plate fields vary depending on architectural layout and measure 9.00 m by 8.50 m or 6.00 m by 8.50 m. The need to create terraces for the top offices floor and to maintain the facade module constant as per the inter storey type meant that the mechanical deck and the roof had to be suspended at the terraces. In fact, since the façade columns had to be set back without increasing the deck depth for the top offices floor, a part of the mechanical deck and its roof had to be hung from tendons. CONSTRUCTION - Buildings • 1- Cross section. 2- Longitudinal section. 1 2 CONSTRUCTION - Buildings 271 3-4- Construction of the first levels: the pour of the deck plates. 5- Use of pre•fabricated bundles of rebars. 6- East façade. 7- North façade. 5 3 4 272 CONSTRUCTION - Buildings 6 7 CONSTRUCTION - Buildings 273 “Acqua minerale San Benedetto” plant Project Building for industrial plant Location Paese (Treviso), Italy Client Acqua Minerale San Benedetto S.p.A., Scorzè (Venice) Design Giuseppe Zago CE Structural engineering Studio di ingegneria RS – Stefano Secchi CE, Padua General contractor Setten Genesio S.p.A. 274 The new industrial installation called for the construction of various buildings on an area of 400,000 square meters, for a roofed area of 175,000 square meters. It stands within a gravel quarry and runs parallel to the Vicenza-Treviso railway line for a kilometer. The most extensive building complex forms a heterogeneous body of plan 700 m x 120 m, its height varying between 12 m for buildings A1 and A2 and 30 m for the remaining area. Buildings A1 and A2 were built with reinforced- and prestressed-concrete precastings, while buildings A3, A3/1 and A5 have steel bearing structures. The production buildings, A4 and A4/1, were built of post-tensioned in situ-cast concrete. Building A4 (production division) has a rectangular plan of 121 m x 164 m. On the railway side and on the quarry side, adjacent to the building, stand four 26-meter-tall towers, in which are created the stairwells. The building has two floors, each of net height 8.5 m, and a total height of 30 meters. The structural grid is 15 m x 15 m with rectangular-section columns of section sufficient to ensure, in at least one direction, a net distance between columns of not less than 14 m. To build the floor structures various structural solutions were evaluated.That best able to meet specifications and most advantageous appeared to be the in situ-cast, with a grating-type floor structure having post-tensioned ribs. Construction needs, together with the need to create suitable expansion joints, identified the “ideal” module as a 30 m x 30 m floor structure constituted of four meshes 15 m on a side each. Thus was identified the dual typology of a “bearing” floor structure, statically indeterminable, on nine columns, and of a “borne” floor structure, on just three columns in line and borne on saddles envisaged at the sides of the adjacent floor structure. Each module is a twoway ribbed floor structure, built of in situ-cast concrete with partial prestressing.The post-tensioning was effected with both bonded cables and unbounded cables. The definitive solution calls for the construction of: 12 “bearing” modules of 1100 square meters, 12 “borne” modules of 820 square meters, and 12 “hybrid” modules (bearing on one side and borne on the other) of a thousand square meters each.The floor structure is lightened with re-useable aluminum forms so arranged as to create a two-dimensional ribbed structure. The ribs are spaced 1.50 m apart and are 28 cm wide.The upper cap is 120 mm deep and is surface-treated with quartz powder. A further surface treatment having a modified sodium silicate base forms a protective barrier against aggressive agents and limits shrinkage effects. The arrangement of the prestressing cables is such as to create “principal bands” 6 m wide, aligned to the columns and prestressed with grouted-sheath cables of six and eight 0.6” strands. On the remaining ribs are present two unbonded single-strand cables. Further grouted cables 6 meters in length are called for in the areas of greatest negative moment and shear. CONSTRUCTION - Buildings • 1- The industrial complex’s development in plan and in elevation. RAILWAY QUARRY 1 CONSTRUCTION - Buildings 275 lightener forms. 3- Pour phases for a bearing module. 4- Installa•tion2-ofAluminium the curtain walls. 5- Bearing-module plan. 6- Ribbed floor-structure soffit. 7Support system with saddles. 8- Support system with shear-connectors. 9- Support system. 2 3 4 5 276 6 CONSTRUCTION - Buildings 7 8 9 CONSTRUCTION - Buildings 277 New Sky Italia headquarters Project New Sky Italia headquarters – Top Management and Television Production Location Milan Rogoredo, Italy Client Milano Santa Giulia S.p.A., with the technical direction of Silvio Bernabè CE Design Byron Harford & Associates – East Sydney Structural engineer In situ-built structures design and supervision of construction: MSC Associati S.r.l. (Milan) – Danilo Campagna CE, Andrea Sangalli CE; Precast/prefabricated structures design: Gamma Engineering (Lecco) – Gianluigi Fregosi CE, Riccardo Castagna CE Architects Byron Harford & Associates – East Sydney Management Contractor Colombo Costruzioni S.p.A – Lecco General Contractor Colombo Costruzioni S.p.A – Lecco Year of completion 2008 278 Building 1 is tied to building 2 through a connector body, building 2 in its turn being tied to building 3 through a suspended bridge. The multifloor bridge (30.15 m in span, 16.80 m wide) over the city street is held up by structural-steel work, consisting of two trestlework girders placed on the facade to form a resisting structure as high as the entire (three-story) facade. Regarding the structural system’s capacity to stand up to horizontal forces, this is delegated to the r.c. structures of the first- and top-level floor structures, which in their plane act as infinitely stiff beams (plates).The facade glazings transfer, at these levels, the wind loading to the diagonals of the main trestlework beam, which have elliptical sections (composed of two semi-elliptical pipes) with greater inertia crosswise to the loads. Except for the stair blocks, the structure is built of precastings. The building floor structures are precast of adherentstrand prestressed concrete, the columns are plant precast (Rck=50 MPa) in forms prepared especially for the SKY project, with different r.c. sections for transport, assembly and removal from the forms in the plant.Their weight was kept down to forty tons. The column was then cast in two pieces, solidly joined together during assembly phase. The central column, its section varying with height from the base, 0.90 m x 0.90 m, is a single piece twenty meters high. It was jointed with an element whose section varied with height, the element being 20-25 m high. The structures were mounted using precise sequences, which permitted construction of the structures in shorter times than is usual for traditional r.c. structures. The construction module is based on a typical grid of 8.40 m x 8.40 m, which is adapted to the various situations, the spans reaching 18.00 m (building 1) and 16.80 m (building 2). Building 1 – technological: rectangular-plan, of dimensions 180.5 m x 28.2 m (36,000 m2 of floor structure). Composed of: basement floor structure, ground floor and seven floor structures above ground. Total height: 39.20 m. Building 2 – offices: trapezoidal-plan, with dimensions 103 m x 26 m (22,000 m2 of floor structure. Composed of: basement floor structure, ground floor and nine floor structures above ground. Total height: 47.30 m. Building 1B: connector building between buildings 1 and 2 (4400 m2 of floor structure). Composed of: basement floor structure, ground floor and six floor structures above ground. Total height: 34.45 m. Building 3: trapezoidal-plan, dimensions 12 m x 25 m (25,700 m2 of floor structure). Composed of: basement floor structure, ground floor and eight floor structures above ground. Total height: 44.75 m. The structures (stairwells and elevator shafts) acting as shearbracing for the buildings under horizontal forces were built in situ (Rck=37 MPa) and tied in a second phase to the precast structure by various pourrestart and continuity systems. The soils demanded a raft foundation on single-fluid or twofluid jet-grouting columns, whether interpenetrating or tangent to one another, having a maximum diameter of 1.90 m for the greater vertical loadings and maximum height of 11.15 m beneath the stair wells. Owing to the high level of the water table, the raft was waterproofed using the so-called “white tank” waterproofing system. Building 1 required specific structural analyses as well as special design choices since it had to possess considerable stiffness (maximum allowable antenna rotation: 0.01° or 36”) under horizontal forces (reference wind speed: 110 km/h), in order to ensure alignment of the trasmitting signals to the satellites through the roof antennas. The displacement and rotation fields were derived by analyzing two different structural models. The first is of a generalized type and was used to evaluate the field of floor structure horizontal displacements at the various floors. From this the horizontal rotations of the decks (rotations with axes normal to the building floor structures) could be deduced. The second concerns the building’s top floor structure, where the trasmitting apparatus is installed. From this latter model the rotations at the antenna bases (rotations with axes in the plane of the floor structures) were derived due to the wind pressures on the trasmitting antennas. CONSTRUCTION - Buildings • 1- Section through buildings. 2- Plan of the complex. 1 2 CONSTRUCTION - Buildings 279 3- Construction of the stairwell core structures. 4-5 Phases in construction of the •buildings. 6- Section through building 2. 7- Foundations plan. 8- Typical-floor plan. 8 3 6 4 5 7 280 CONSTRUCTION - Buildings CONSTRUCTION - Buildings 281 Light Pavilion Project Exhibition pavilion Location Grand Hotel, Como, Italy Client Meta S.p.A. (Paolo De Santis) Design and yard management Attilio Terragni The Light pavilion stands under Lake Como’s evocative light, in a ten-thousand-square-meter park between the city’s historic downtown and Cernobbio. The project’s origin was quite simple: the program in fact needed a space as open to the outside as possible, without the natural light’s disturbing the staging of the events. To meet this need the construction’s volume was intersected by several plane surfaces, arranged arbitrarily in space in such fashion as to create a series of fragments, suggesting a process that could continue on to infinity. The intersections thus determined have become the linear voids through which a limited and quite definite dialogue develops, between rule and free will, between structure and light. The hall volume unveils a continual weave of cuts crossing it vertically and horizontally, taking on the landscape’s blue and green tints. The idea behind these cuts came out of the suggestiveness evoked by a former Fascist-headquarters building standing not far off, where a crystal slash crosses the upper part of the atrium roof, putting the mountains behind the city in relation with the cathedral nave. Analogously, in the pavilion the irregular network of cuts takes as its aim to reveal the power and the all-pervasiveness of the corrosive action of the lines that have over hundreds of millennia modelled the present-day forms of the Lombard lakes landscape. Design Team Chiara Assanelli, Luca Mangione, Maja Leonelli Structural design Amis Milano – Antonio Migliacci CE, Giovanni Franchi CE Mechanical and electrical equipment Amman Progetti Milano Acoustics Paolo Molina CE Sun-protections Abba Srl, Treviso (Person in charge: Luca Franceschin) Safety engineering CDR, Carlo Ruckstul CE General contractor Mondelli Battista. Construction yard supervision: Aldo Mondelli CE Facade PERMASTELISA Construction yard supervision: Alfredo Piccoli 282 CONSTRUCTION - Buildings • 1- Pavilion plan. 1 CONSTRUCTION - Buildings 283 • 2- Sections through pavilion. 3-4 Phases in building the structure. 2 3 4 284 CONSTRUCTION - Buildings CONSTRUCTION - Buildings 285 Agenzia Spaziale Italiana new headquarters Project Headquarters Location Tor Vergata, Rome, Italy Client Agenzia Spaziale Italiana Structural engineer Prof. Camillo Nuti CE with STIN Section chief: Danilo Pierucci CE, Rome Architects 5+1AA Alfonso Femia, Gianluca Peluffo with Annalaura Spalla arch. Management Contractor Infrastructures Ministry Interregional Office for Public Works for Latium, Abruzzo and Sardinia Superintendent: Giovanni Guglielmi CE Supervision of construction: Mario Avagnina arch. General contractor SAC Società Appalti Costruzioni S.p.A. – Rome Project manager: Bruno Cavallaro CE Year of completion 2010 286 The Italian Space Agency’s new headquarters stands in the Tor Vergata university district, East of Rome’s great ring road, on a sloping lot adjacent to the engineering faculty. The complex comprises ten buildings: the semicircular main building (A), where most of the offices are concentrated; the rectangular auditorium and atrium buildings (B’ and B”), which eccentrically intersect the previous one, on the centerline of the faculty of engineering – they represent the monumental aspect and act as connection with the outside; a series of minor buildings, for offices or services, such as the library (C), the nursery-school and offices building (D), the bank and fitness-center building (E), the doorkeeper’s office (F), the cafeteria-kitchen (G), the laboratories-offices (I), and the underground parking garages (L). Structural design had as reference OPCM 3274, and thus took account of the city of Rome’s listing in seismic zone 3. This is one of the first applications of the new seismic design criteria for a complex of considerable size. The design was sifted by the Higher Public Works Council, as a building having a value exceeding 25 million euros. The main building A and buildings C-D are buildings having an r.c. core and a mixed steelconcrete structure, with hanging steel columns and floor structures made up of predalles and a 9 cm deep slab.The other buildings are substantially wholly of r.c., in some cases with floor structures made of prestressed elements (honeycomb floor structures or omega tiles). Retaining walls of considerable height are present. Vertical seismic joints separate building A into three bodies. In each body there are two r.c. cores, while the remaining structure is mixed steel-concrete. The first two bodies have each six floors, one or two of which are below ground depending on the lay of the land. The third body stands five floors above ground. Buildings B” (lobby) and B’ (auditorium) stand along a line that crosses main building A, with which they share the joint. They are almost totally built of r.c., with walls of great extent in plan. Both are lower than building A. The zone of intersection, the focus of the complex, where four structurally - independent buildings converge, is as high as building A and is without floor structures from the second floor to the roof. In correspondence with the facade of the concave side, on the higher floors, the overhead passageways run between the two bodies composing the main building, bearing on more-or-less radial septums. The overhead ways, the first two floor structures and the concave facade have vertical joints in the middle of the atrium. To roof this space an innovatory solution was found. It consists of a steel grid with concrete slab resting through seismic isolators on the two r.c. cores of the two independent bodies of the main building which delimit the atrium. The upper part of the convex facade hangs from the isolated roof. At mid height a horizontal joint separate the facade from its lower part which sticks out from steel structure of the roof of building B. Vertical joints separate the facade from the cores of building A on which the roof of the atrium stands. The latter solution, involving a structure bearing on seismic isolators, was particularly apt. In fact, the stresses induced by independent seismic motion of the cores are moderate, the structure is simple, the support scheme is particularly suited to the mixed steel-concrete structure typology and its construction proceeded rapidly. The connection of the mixed-steel concrete floors to the two bracing cores in each of the bodies which compose building A was effected with special metal inserts to which the slab’s restart reinforcing were welded. These special pieces were connected to anchorage plates buried in the cores by welding in place. The vertical reinforcement of the structural walls stick up from the foundations for one floor and a half without interruption, so as to exclude overlapping in the critical zones of the bracing walls where yielding may happen. CONSTRUCTION - Buildings General plan of the complex. 2- Main building (A) and Auditorium (B’). (pho•to: 1-Giuseppe Maritati). 3- Main building (A) West facade, concave side. Building A – “Crescent” offices Building B –Atrium-auditorium system Building C – Library Building D –Nursery, offices Building E –Bank, infirmary, gymnasium Building F –Doorkeeper’s office Building G –Cafeteria, kitchen Building H – Bar Building I – Former workshop offices Building L –Underground parking 1 2 3 CONSTRUCTION - Buildings 287 plan. 5- Main building (A): restart steels. 6- Building atrium (B”). 7•Main4- Foundations building (A): body 3, mounting the mixed structure after construction of the r.c. core. 8- Main building (A) and Auditorium (B’). 9- Main building (A) – Concave side. 10- Cafeteria building structure (G). 11- Cafeteria building (G). 6 4 7 5 9 8 288 CONSTRUCTION - Buildings 10 11 CONSTRUCTION - Buildings 289 “Altra Sede” for the Regione Lombardia Project New administrative center for Lombardia’s regional government Location Milan, Italy Architectural design Pei Cobb Freed & Partners Architects, New York, Caputo Partnership & Sistema Duemila, Milan Architectural Design Supervision Arch. Henry N. Cobb Structural Design Prof. Franco Mola CE – ECSD S.r.l., Milan Construction Supervisor Infrastrutture Lombarde S.p.a. – General Manager: Antonio Giulio Rognoni CE General Contractor Consorzio Torre (Impregilo S.p.A., Techint Infrastrutture, cmb, Cile S.p.A., Montagna Costruzioni S.r.l., Pessina Costruzioni S.p.A., Consorzio Cooperative Costruzioni, Sirti S.p.A.) Leading Contractor Impregilo S.p.A. General Manager Gaetano Salonia CE Site Technical Manager Vinicio Scerri CE Construction Site General Manager and Safety Supervisor Guglielmo Fariello CE Formwork Doka italia S.p.A. Precast vertical elements and beams CSP Prefabbricati S.p.A. Slabs Cobiax Technologies S.r.l. Year of completion 2009 290 The ‘Altra Sede’Tower, located in the center of the city of Milan, has recently been completed. On January 22, 2010 an official ceremony marked the end of the construction phase and unveiled the new building to the citizens of Milan, who were also called to cast their vote and decide the new name of the complex: Palazzo Lombardia.The building is currently the tallest in Italy, and one of the strongest features of the skyline of the city for years to come. The Tower is the new administrative centre for Lombardia’s regional government in Milan; the administrative complex also includes five lower buildings (about 40 m high, called Cores 2, 3, 4, 5 and 6), surrounding the high-rise Tower (Core 1), which, 161.30 metres tall, set an Italian record.The building’s sinuous interweaving strands recall mountains, valleys, and rivers of the Lombardia region.Their curvilinear forms are adaptable to changing functional requirements and are receptive to the region’s evolving organizational structure. In addition to its headquarter functions, the building accommodates public amenities accessible to all.The winning architectural project for the new regional headquarters was conceived, according to the guidelines set forward by the Adminisration, by the architecture bureaus Pei Cobb Freed & Partners from NewYork, together with Caputo partnership and Sistema Duemila from Italy in 2003. Given the very strict construction times (October 2006-December 2009), wise and innovative choices were enforced as for the design of structures, entirely consisting of reinforced concrete elements.The foundation system is a 4m thick reinforced concrete slab resting on soil whose load bearing capacity was preliminarily improved by means of the jet grouting technique.The total volume of concrete is about 8.000 m3. For the lower layer, 1m thick, including most of the steel rebar, SC 30/37 self compacting concrete was used, whereas for the upper layer, 3m thick, a high performance C 30/37 concrete was employed. The vertical structures of the Tower consist of one 15,5x16,3m inner core hosting stairways and lifts, whose maximum thickness of the walls is 45cm, and 22 circular columns with diameters ranging from 120cm at the bottom to 65cm at the top floors.The columns are located along two curved lines and define a structural grid of 8,60mx6,50m. For the cast in situ slabs, 35cm thick, C 40/50 concrete was used. Regarding the construction techniques, both for the vertical load bearing structure (cores and columns) and for the horizontal ones (slabs), it was decided to make extensive use of industrialized systems, together with high profile state-of-the-art construction technologies, such as the self-climbing formwork employed to build the core of theTower, for which high strength concrete (class C 45/55) was used. An hybrid steel encasing/reinforced concrete system was employed to build the columns, allowing the columns to be cast at the same time for an height of up to three floors. Slabs consisted in pre-assembled panels including the main reinforcement and polyethylene spheres with a diameter of 27cm. In this way, the total weight of the slab was reduced by about 25% with respect to a solid section and only additional reinforcement had to be placed, thus considerably reducing the construction time.These techniques, coupled to the self-climbing formwork, allowed the construction of each storey of the tower in an average of 5.5 days, as opposed to the 8 days needed with the traditional casting system.The synergic use of these technologies allowed the 38 floors of the Tower, of which those from 1 to 11 have a surface of about 2000 m2 and those from 12 to 38 have a surface of 900m2, to be built in about eleven months. This very remarkable reduction in construction times of the structural system of the Tower was reflected in the global construction ending 60 days ahead of schedule.The roofing of the inner plaza, with a surface of about 4200 m2, consists of a steel truss structure made of welded and bolted S355 J2 steel tubes on top of which a double-layer Texlon ETFE (ethylene-co-tetrafluoroethylene) film is installed.The ETFE cushions guarantee a filtering of sunlight of about 50%. EFTE was chosen since it is a transparent plastic film, lighter and more resistant than glass, with superior insulating power and easier and less expensive to install.The ETFE film is also stable to UV rays and is not altered by environmental pollution and weather conditions. Sustainability, environmental impact, durability and reduced management and maintenance costs were also consistently pursued, by recurring to the most effective solutions for plants, photovoltaic energy production, air conditioning, façades and ventilation, such as the double-layer façade making up a ‘thermal wall’ for the internal rooms, with an automated system of sun shades conceived to minimize heat dispersion and maximize the efficiency of the air conditioning system. CONSTRUCTION - Buildings 1- View of the Tower through the roofing. 2- Construction: facades. 3- Con•struction of Core 1. 4- Cross section of the slab. 1 2 3 4 CONSTRUCTION - Buildings 291 Ground floor plan. 6- Columns and slab systems. 7- Tower contruction. 8•Slab5-system. 9- Core 1: reinforcement details. 5 6 8 292 7 CONSTRUCTION - Buildings 9 CONSTRUCTION - Buildings 293 New “Sant’Anna” Hospital Project New Sant’Anna Hospital Location Como, Italy Client Infrastrutture Lombarde and Azienda Ospedaliera Sant’Anna Architectural and plants design Bortolazzi Consulting Structural design Prof. Franco Mola CE – ECSD S.r.l., Milan On-site Supervisor Francesco de Probizer CE Construction Supervisor Infrastrutture Lombarde S.p.A. - General Manager: Antonio Giulio Rognoni CE General Contractor S.A.N.C.O. SCarl (Altair, GDM Costruzioni, Aster) Year of completion 2009 294 The new Sant’Anna Hospital in Como, located in the heart of the Lombardia Region, in northern Italy, is a large hospital complex for which a short time for construction, fixed in 900 days, was allowed by the Administration. The complex is made of eight interconnected buildings, with heights up to 22 m, including, respectively, a number of floors ranging between 2 and 3 floors above the ground. The underground floors range between one and three, according to the height of each building above the ground and the ground level itself varying across the plan.The whole complex is surrounded by reinforced concrete walls with varying height. Two main aspects governed the design choices: the earthquake hazard for the area where the Hospital is located and the deep foundations, which caused the foundations themselves and the lower underground floors to be entirely below the water level. As for the seismicity, the Lombardia Region is classified as ‘Zone N.4’ in the Italian Seismic Code, which corresponds to a PGA of about 0.05g. Since the hospital buildings are classified as ‘strategic’, an importance coefficient of 1.4 on the PGA is also compulsory, meaning that the design PGA value became 0.07g. Due to their limited height, the buildings are all quite rigid, so that earthquake effects are strongly prevailing on those of wind loads: earthquake is thus the main load condition for pre-dimensioning of the structural elements for lateral resistance (global base shear). The chosen structural elements were reinforced concrete cores, adequately distributed in plan, so as to reduce torque effects due to lateral loads; as for static loading, reinforced concrete columns were dimensioned to the vertical loads in addition to the flexural effects derived from the lateral displacements produced by the cores and also taking into account the interaction with slab elements under vertical loading. The foundation system includes reinforced concrete basements for the columns, supported by concrete piles with driven steel formwork, having a maximum length of 26m. The cores are supported by concrete plates resting on reinforced concrete diaphragms.The plan configuration of the buildings, with a complex distribution of columns, not lined into orthogonal patterns, gave way to varying spans for the slab structures.The lack of regularity in the distribution of vertical elements is not very strong, though, so, except for some peculiar areas, the mean spans for the slab were 7.50mx7.50m.The ratio between the two spans calls for elements with a two-dimensional behavior. The irregularities in the grids called for the use of construction systems that are totally or mostly independent on the morphology of the slabs themselves. The most competitive technique at this regard is the use of in situ casting: continuous prestressed concrete cast-in-situ slabs resting on the columns turn out to be the best choice. An adequate number of prestressed unbonded steel strands was introduced in the slab, which allowed a reduction of the slab thickness to 26cm.The quantity of prestressing strands and additional rebar is globally reduced with respect to ordinary rebar, so that the time to arrange the steel before casting is significantly shortened. Even if the arrangement of prestressing steel must be accurately carried out and supervised, and special construction methods to guarantee the effectiveness of prestressing must be enforced – in particular provisional gaps, sliding supports along the cores and punching shear additional reinforcement – construction time can still be reduced, because the formworks can be removed as soon as after only 36 hours from casting, when concrete, whose mix-design was accurately studied, reaches a strength of about 30MPa, implying an elastic modulus of about 3x104 MPa. In this way, a good productivity level was guaranteed, coupled to high structural performance and strong standardization in the construction process. CONSTRUCTION - Buildings Overview of the completed Hospital. 2- Plan view of the complex (architect•ural1-drawing). 1 2 CONSTRUCTION - Buildings 295 • 3- Column-slab joint. 4- Floor plan. 5- Vertical section. 6- Facades assembling. 4 3 HOSPITAL EAST PARKING NORTH PARKING 5 6 296 CONSTRUCTION - Buildings CONSTRUCTION - Buildings 297 “Verdi” Theatre Project New “Verdi” Theatre Location Pordenone, Italy Client Municipality of Pordenone Design Ing. Carlo Filipuzzi, arch. Paola Moretti – Interstudio s.r.l., Udine Structural engineer consultant Ing. Carlo Filipuzzi Yard management Arch. Ermanno Dell’Agnolo General contractor Mazzi Impresa generale SpA, Verona Photographs Interstudio s.r.l. 298 The theatre stands on a long narrow lot bounded by the orthogonal street grid, and is in a place of transition between the historic downtown and an urban outskirts almost a large city’s. The position of the architectural complex has not compromised the language of continuity of the sur-rounding buildings, indeed, it has relaunched their vitality through the great appeal it enjoys within the city.The theatre main entrance opens on two broad streets: the via Battisti and the via Martel-li, which meet at an angle, right at the building entrance and on the entrance to the plaza.Volume-wise, three elements identify the theatre’s principal use assignments: the halls and the foyer, the stage tower, and the dressing rooms. The project called for three halls: a principal hall seating 998 between the orchestra and three orders of balconies; a smaller one containing 160 seats, and a multi-use hall seating one hundred at the third level, useable both for small entertainments and for rehearsals, since its dimensions are those of the stage. The choice of theatre-hall conformation fell on the traditional horseshoe, to guarantee good visibility and acoustics. The public accesses it through the building-high foyer: two grand stairways serve the three balconies and a route along the perimeter of the foyer joins the three balconies with three rings. The dressing rooms are divided into four singles, three doubles, three quadruples and six group dressing rooms. In the basement there is only the wardrobe. The first floor of the backstage zone is taken up by some of the dressing rooms and by the dressmaker’s. The second floor holds more dressing rooms, while the third floor, besides other dressing rooms, also holds offices, including the press office, and in the central part the choir rehearsals hall, useable too as a conference room. The fourth floor holds the final dressing rooms, the rest of the offices, a workshop, the carpenter’s shop (directly connected to the stage tower), and the rehearsal room. CONSTRUCTION - Buildings of the project, right downtown. 2- The reinforced-concrete sculpture pla•ced1-inPlan the foyer. 3- The foyer, characterized by the sculpture and the fair-face bearing structures of the roof and of the galleries accessing the three higher balconies. 1 2 3 CONSTRUCTION - Buildings 299 plan at the level of the main hall orchestra seating. 5- The building’s •top4-floorBuilding (level of the boxes, 12.90 m). 6- Longitudinal section through building. 7Facade, on the via Martelli. 4 5 300 CONSTRUCTION - Buildings 7 6 CONSTRUCTION - Buildings 301 Banca Lombarda Center Project Banca Lombarda Center Location Brescia, Italy Client SBIM – Società Immobiliare Mobiliare S.p.A. , Brescia Architect Gregotti Associati International s.r.l., Milano Structural engineer Sajni e Zambetti s.r.l., Milano System design Amman Progetti S.p.A., Milano General contractor Colombo Costruzioni S.p.A., Lecco Photographs Donato Di Bello – Gregotti Associati International S.p.A. 302 The construction of the Lombarda bank’s new headquarters in Brescia, in the area of urban expansion, is the result of a design search for an alternative to the tower typology, often used for the design of buildings having a high services concentration. The complex is conceived as a sort of virtual cube, 50 metres on a side, consisting of two lateral wings connected on the north by a suspended volume and on the south by a low body having truncated-pyramidal roof and by a glazed walkway at the tenth floor. The two lateral wings are assigned to operations offices; the block to the north is reserved to halls and offices for meeting the public, and the volume that concludes in a truncated pyramid houses the two great congresses halls, seating 500 and 150 persons. They may be accessed independently for any public use. The complex features a sharp contrast between the white of the marble cladding of the stair bodies’ four corner volumes and the transparent surfaces of the continuous glazed facades. In the east and west wings completely transparent bands of glazing alternate with glass blocks, while for the suspended building body a “dual skin” solution was adopted with a brisesoleil towards the south, and a wholly glazed façade to the north.The corporate offices building runs up twelve floors above ground, reaching a height of 54 metres, and has two basement floors, one outfitted for services and the other for parking, the total net area being 27,000 square metres. To this is added the 25,000 square metres of underground parking adjacent. The office building structure features two trios of steel latticework beams placed at elevations 23.35 and 44.15 metres. Their span is 36 m and their function is to sustain the nine-floor suspended body.The beams bear on reinforced-concrete columns stabilized by two of the four stairwells. For the foundations, considering the soil’s low compressibility and its bearing capacity, separate direct footings were chosen. CONSTRUCTION - Buildings 1- Plan. 2-3 Phases in the construction of the structures: all reinforced-concrete •components were in situ poured. 1 2 3 CONSTRUCTION - Buildings 303 • 4- Ground-floor plan. 5- Second-level plan. 5 4 304 CONSTRUCTION - Buildings CONSTRUCTION - Buildings 305 Boglietti Palace Project Boglietti Palace – Cultural Center Location Biella, Italy Client Giovanni Boglietti – “Obiettivo Domani” Cultural Centre Architects Arch. Alberto Rizzi, Biella Assistants Luca Gibello, Filippo Chiocchetti, Paolo Strobino, Francesca Frigato Structural engineer Orio Delpiano, A.I.R.E., Biella General contractor Lasimon S.a.s., Biella Photographs Archivio Studio Rizzi, Costantino Merlini, Davide Lovatti, Roberto Marchisotti 306 The building, located on the southwest outskirts of the city of Biella, is essentially characterized by the juxtaposition of two truncated pyramids: one, upright, takes in and configures the basic structural system, i.e. the great reinforced-concrete spherical caps representative of the entire spatial order. The other, inverted and differently oriented relative to the axes of the system of caps themselves, houses the main stairwell, making possible the natural statics equilibrium of the whole. The construction develops on the whole on four levels above ground, besides the basement floor and the roof terrace, for a total net area of 1500 square metres. Between the ground floor, housing the accesses and reception desk, and the first floor is a mezzanine floor having as its basic function to act as an intermediate between the spaces, all wholly devoted to housing, small and large events, such as showings, reviews and exhibitions and the video projections they involve. The first floor develops within the great spherical caps. On the second and top floors, directly connected with the overlying terrace, space is found for a cafeteria and a small multimedia library, while on the basement floor is the great exhibition area, naturally lighted by special large skylights “excavated” in the structure of the hanging garden.This permits its conversion, as needed, into a sizeable conference hall.The building is strongly characterized by the massive use, not only of r.c., but also of marble and stone.The whole main construction above ground bears on five columns, placed at the sides of an equilateral triangle, that is in respect of the primary design of a truncated pyramid, which is what, substantially, the building configures. The two columns near the top of this triangle, towards the east, are 0.60 m in diameter, while the remaining three, placed at the corners and in midspan of the west side, are 0.70 m in diameter. Starting from the upper level (ground floor) the columns change typology, being converted into characteristic oblique pilasters, two of which – along the west axis – display a variable rhomboidal section owing to their tapering towards the top. CONSTRUCTION - Buildings 1- The building in plan and volume. 2- Structural system of the large spherical •vaults. 3- Basement-floor plan. 4- Ground-floor plan. 2 1 3 4 CONSTRUCTION - Buildings 307 5- First-floor plan. 6- View of building from the south during final finish phases. •7- Section through building. 6 5 7 308 CONSTRUCTION - Buildings CONSTRUCTION - Buildings 309 “Cuore immacolato di Maria” parish complex Project “Cuore immacolato di Maria” parish complex Location Formia, Latina, Italy Client Parroco Maccioni Don Gesuino – Arcivescovo di Gaeta, Mons. Vincenzo Farano Project Arch. Bernardo Re Geothecnical advisory Ing. Giovanni Gambacorta Photographs Arch. Bernardo Re 310 The Immaculate Heart of Maria parish complex stands in an area donated by the bordering Salesian Sacred Heart hospice. During design it seemed fitting to exploit the lot’s orographic conformation in relation to the main street, as did the need to lower the foundation plane to reach a soil of consistency adequate to permit direct foundations.Thus was permitted: the shifting of the catechism classrooms and the services below the sacristy into a band as long as the lot, lighted by a light shaft with plantings; the location below the church of the multi-use community salon seating 450; and the construction of the weekday chapel for seventy faithful. On the upper floor were located the assembly hall, with access from the sacristy, the sacristy itself with parish office, and hygienic facilities for the handicapped. Over the sacristy, suspended from the roof, are the priest’s quarters. The bell tower, placed pseudobaricentrically, completes the whole; it is accessed from the sacristy. The entire oeuvre was built of fair-face white lightweight structural cement concrete, having as well an excellent heat-transfer coefficient, which meant the adoption of walls only 250 mm thick that met energy-consumption standards. The lightness of the statics scheme was made possible by the special technologies applied for construction. One such was that used for the ribbed triangular lacunar plates with fine triangular mesh that permitted very low structural weights and were aesthetically pleasing as well as acoustically suitable. Stimulating too was the design and construction of the five bombé “sail” walls of trapezoidal form, all different the one from the other. Extremely complex was the construction of the belltower, especially at the points where it was grafted onto the arches and at the floor structures where the in-depth beams arrive with strong traction forces.The sacristy floor structure is a dual slab lightened with polystyrol pads, poured in situ without break. The three St. Andrew’s crosses, placed on each end of the frames connecting the walls to take up horizontal forces, were built on site, positioned and solidly joined in the pour of the ends of the rectangular section walls. CONSTRUCTION - Buildings • 1- Church plan. 1 CONSTRUCTION - Buildings 311 front facade. 3- The soffit of the special roof created with ribbed trian•gular2- Church plates. 4- The wooden intermediate floor suspended from the concrete frame. 2 3 4 312 CONSTRUCTION - Buildings CONSTRUCTION - Buildings 313 “San Giovanni Battista” parish complex Project New parish complex of San Giovanni Battista Location Lecce, Italy Client Archdiocese of Lecce, Italy Architect Arch. Franco Purini, prof. Laura Thermes – Rome Assistants Luigi Paglialunga, Massimiliano De Meo Structural engineeer Ing. Enzo Pierri (church), ing. Andrea Cinuzi (belltower) Supervision of construction Raffaele Parlangèli General Contractor Fratelli Marullo, Calimera (Lecce) Photographs Studio Purini Thermes 314 The St. John the Baptist parish complex was built in Lecce, in the Stadio district, a zone on the outskirts featuring numerous residential buildings and economic and subsidized public building construction.The design of the centre was thus made up with the aim of creating an urban pole of attraction, a true “community house”, able finally to attribute recognizability to the entire area. The complex comprises a series of volumes that de-limit and define a foot plaza, an internal court and a closed space, the Walled Garden, conceived for meditation. The church’s assembly hall is square-plan, 24 m on a side. Next to it is a rectangular wing holding the sacristy and the weekday chapel. The assembly hall’s bearing structure is sustained by just four columns, which identify a fullheight central basin, trapezoidal in plan, connoted by a strong feeling of lightness. On the hall perimeter are the service spaces, lower in height. The four columns are con-nected by isolated beams, at a height of eight metres. One of the beams of this internal frame extends towards the entrance wall, piercing it and projecting beyond cantilever-wise. From it hangs the large cross that connotes the building façade. The hall roof bearing structure, which reaches a peak elevation of 15.65 m, is seen as a lacunar complex formed of square-section beams 1.60 m on a side. In one section, the roof cantilevers out by 7 m. In the lateral areas the beams and the columns create a square-mesh modular grid 6 m on a side. The frame structure arranged on the perimeter is clad with plastered tuff block walls. The parish works building has an r.c. frame bearing structure. Of special interest is the stairway, created by a cantilevered slab.The campanile is shaped like a portal, expanded in height.The two vertical outside septums are 0.30 m thick, as is the septum supporting the stairway, and have a total height of 28 m. The foundations are a one metre deep footing. The cladding for the Parish hall and for the entrance security lock, both inside and outside, is of Lecce stone. CONSTRUCTION - Buildings plan and facade (line of section 4). 2- First-floor plan and in•terior1- Ground-floor facades (lines of sections 2 and 3). 1 2 CONSTRUCTION - Buildings 315 316 CONSTRUCTION - Buildings • 3- Sezione trasversale. 3 CONSTRUCTION - Buildings 317 “Somada” Business Center Project Business Center Location Residential and shopping centre “Somada”, Italy Design Arch. Enzo Zacchiroli, Bologna Precast structure design Ing. Mauro Ferrari, Reggio Emilia General contractor for structure Edilquattro spa, Montecavolo di Quattro Castella (RE) General contractor for precast structures APE spa, Montecchio Emilia (RE) Photographs PatriziaVirginia Belli, Bologna 318 The project concerns a corporate complex including offices and shops set down in and completing the residential and business center of a subdivision called Somada. The triangular-plan building features a large internal patio-garden. Lining the patio’s three sides are the shop spaces, on the raised ground floor and the first floor, while the spaces assigned to offices are on the 2nd and 3th floors. At the building’s heart, besides its planted area, is the cylindrical core. Within it, starting from the raised ground floor, the helicoidal stairs and a glazed-wall elevator develop. It culminates in a conical-roof skylight.The shops, all enjoying extensive glazing, and the offices are served, and accessed, on all levels by broad porticoed foot ways. On the raised ground floor, the area fronting on the court is furnished around the whole perimeter with chairs in which to sit and enjoy the outdoor area. Formally, the complex is characterized by a number of elements, which spring from the search for an appropriate architectural system, filled out with the necessary functional elements.The building comprises a bearing frame structure of semi-precast typeK reinforced concrete. Being conceptually connected with the traditional reinforced-concrete frame, it is composed of reinforced-concrete precastings (beams, stair flights) light-weight predalles-type floor structures, prestressed-concrete honeycomb slabs and in situ-poured members (foundations, columns, perimetral and dividing walls, and the stairwells). Characteristic of the system is the wet-type node, where beam-column structure continuity is created by the simple overlapping of reinforcings and a successive solidizing pour, made at the same time as the floor structure is poured.The structures subsystem consists of v.r.c. semi-precastings, whose joins, effected by reinforcings and integrating pours, create a statically indeterminate structural complex. Its performance characteristics can be traced back to an equivalent in situ-poured structure, as regards the absorption of both vertical and horizontal forces. CONSTRUCTION - Buildings • 1-2 Sections through the building. 3- Second-level plan: structural details. 1 2 3 CONSTRUCTION - Buildings 319 Established in 1959, is the national association of the Italian cement producers AITEC belongs to Confindustria and to CEMBUREAU, the European cement producer’s association; its missions is to promote and to communicate the product’s technical and economic potentials, as well as a correct image of the whole cement sector. To this purpose AITEC shares its knowledge and information with all those who, by profession, business or studies are interested in knowing the world of cement. w w w . a i t e c w e b . c o m