The SWING Project: status and closure of the project Bruno Zolesi. [email protected] Istituto Nazionale di Geofisica e Vulcanologia The Project • Starting date: January 1st , 2012 • End date: December 31st , 2013 • Duration: 24 Months Partnership: • Consiglio Nazionale universitario per le Telecomunicazioni • Istituto Nazionale di Geofisica e Vulcanologia • Observatori de l’Ebre • National Observatory of Athens 13/12/2013 SWING Final Meeting | CNIT - Pisa, Italy 2 The Aim of the Project In case of wide scale terroristic or attacks able to render useless Internet links the aim of the Project named SWING was: 1. to establish the basis for a South European robust radio network, based on SW architecture; 2. to utilize innovative ionospheric sounding techniques and real time signal processing and forecasting, to support Critical Infrastructure communications, both short and long range. 13/12/2013 SWING Final Meeting | CNIT - Pisa, Italy 3 The Aim of the Project In fact the potential risk of wide scale terrorist attacks able to put out of order, for a long period, the internet connections capabilities exposes the some European Critical Infrastructures (ECIs), like electric power distribution and production infrastructure, CPAs, safety and defense organization, water distribution agency, airports, etc. in a stage of vulnerability because of some essential information are transferred by means of internet both for management and control. 13/12/2013 SWING Final Meeting | CNIT - Pisa, Italy 4 The Aim of the Project The aim of SWING was to study a high survival HF radio network (data/voice) to real time support of ECIs communications, maintaining the minimum flux of essential information for the management and control in case of wide scale terrorist attacks able to render internet links useless over the Mediterranean region. This will increase the awareness of ECIs operator in the extreme case of the complete broadband failure of the communication. 13/12/2013 SWING Final Meeting | CNIT - Pisa, Italy 5 Objectives 1. To study internet communications criticality. 2. To analyze the requirements necessary to ECIs and CGAs management and control. 3. To develop a communication protocols in order to define standard software and hardware tools supporting reliable and interoperable Short Wave radio communication techniques for ECIs and CGAs protection. 4. To study the frequency management system taking into account the special characteristics of the ionospheric channel. 5. To design a radio-communication architecture for a distributed South European short wave radio network. 13/12/2013 SWING Final Meeting | CNIT - Pisa, Italy 6 The Aim of the Project Target groups Agencies and institution devoted to management of Critical Infrastructures that are linked by internet network. Expected results The project is finalized to demonstrate the feasibility of a network high survival HF communication as buck-up and independent system to ensure minimum management and communication requirements, in the case of internet failure due to a terrorist attack. 13/12/2013 SWING Final Meeting | CNIT - Pisa, Italy 7 Activities and Deliverables 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. Interface with EU authorities and coordination. Technical analysis of the communication problems related to the identification and designation of CIs in the interested area. Determination of the topology of high survival radio communication network. Characterization of the minimal amount of information necessary for the survival of the CIs communication. Operative supervision of the network architecture. 6-Analysis of the existing architecture of HF communication based on internet protocol access with reference to the above considered infrastructures. Analysis of existing HF connection system in terms of software and hardware for internet connection. Definition of the High survival HF radio network technical requirements. Radio network system design. Criteria of early warning alert and procedures to activate the back up network. Monthly prediction of the hourly HF set of frequencies over the n radio links given by the network, based on the available ionospheric model and methods. Daily forecasting of the hourly HF set of frequencies based on the Mediterranean ionospheric measurements. Ground wave propagation analysis when required. Frequency management system for HF communication link optimization. Identification of the professional profile able to maintain and operate network. Dissemination of deliverables within communities informing about initiatives organised in the context of the project. Professional training activities trough courses, workshops and conferences. Assessment of the potential impact and feasibility of the project for ECIs and CGAs and final recommendations for the EC. Realization of a demonstrator constituted by 4- terminals HF network. 13/12/2013 SWING Final Meeting | CNIT - Pisa, Italy 8 SWING System’s generalities and structure of the final report: Cesidio Bianchi. 13/12/2013 SWING Final Meeting | CNIT - Pisa, Italy 9 Design and realization of HF station prototype: James Baskaradas and Anna Lisa Saverino. 13/12/2013 SWING Final Meeting | CNIT - Pisa, Italy 10 HF management communication system and link optimization: Bruno Zolesi 13/12/2013 SWING Final Meeting | CNIT - Pisa, Italy 11 High Survival HF radio Network: Michele Morelli. 13/12/2013 SWING Final Meeting | CNIT - Pisa, Italy 12 • Internet Criticalities: Fabrizio Cuccoli. • Determination of the topology of high survival HF radio communication network: Andrea Abrardo. • Identification of Critical Infrastructures in the Mediterranean Sea context and communications’ criticalities: Irene Fiorucci. 13/12/2013 SWING Final Meeting | CNIT - Pisa, Italy 13 Final recommendations and closure of the financial budget: Antonio Meloni INGV PART B - PROJECT BUDGET ESTIMATE FORM - CIPS 2010 Action Grants SWING Applicant organisation EXPENDITURE (€) REF Headings IN EURO Verification of division of costs between partnersbeneficiary INGV 1. Partner 2. Partner CNIT 3. Partner NOA 4. Partner 5. Partner Fill in the name of the Partner in worksheet K Partn in cell A 12 EBRE 6. Partner Fill in the name of the Partner in worksheet K Partn in cell A 13 7. Partner Fill in the name of the Partner in worksheet K Partn in cell A 14 8. Partner Fill in the name of the Partner in worksheet K Partn in cell A 15 9. Partner 10. Partner 11. Partner 12.Partner 13. Partner 14. Partner Fill in the Fill in the Fill in the Fill in the Fill in the Fill in the name name of the name of the name of the name of the name of the of the Partner in Partner in Partner in Partner in Partner in Partner in worksheet K worksheet K worksheet K worksheet K worksheet K worksheet K Partn in cell A Partn in cell A Partn in cell A Partn in cell Partn in cell A Partn in cell A 17 16 18 A 19 20 21 Fill in the name of the Partner in worksheet K Partn in cell A 22 1. Eligible direct costs Division among A Staff Costs 496.730,82 partners OK Travel and subsistence B allowances for project staff C Equipment and Consumables D Conferences and seminars E Publications and dissemination F Other possible direct costs (subcontracting up to max 30% of I - Total eligible costs) G Total eligible direct costs (A+B+C+D+E+F) 2. Eligible indirect costs Overheads (max 7% of G H Total eligible direct costs and max 50.000 €) I Total eligible costs for the action (G+H) Division among 19.250,67 partners OK 237.421,72 227.309,10 16.000,00 16.000,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 9.192,82 1.457,85 4.300,00 4.300,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 55.039,46 42.772,04 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 10.000,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 20.000,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 Division among 97.811,50 partners OK Division among 10.000,00 partners OK Division among 20.000,00 partners OK 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 643.792,99 331.654,00 271.538,99 20.300,00 20.300,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 Division among 27.352,83 partners OK 671.145,82 10.000,00 10.000,00 3.678,02 3.674,81 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 341.654,00 281.538,99 23.978,02 23.974,81 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 106.339,38 96.500,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4,2487% OK: overheads below 50.000€ REVENUE (€) REF Headings J Project-related income K Financial contribution from Applicant organisation /coordinator and project partners L Financial contribution from other organisations M Grant requested from the EU € N Total expected income (J+K+L+M) IN EURO 0,00 Division among 202.839,38 partners OK 0,00 Division among 468.306,44 partners OK 671.145,82 238.387,04 196.457,91 16.731,86 16.729,62 0,0000 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 344.726,42 292.957,91 16.731,86 16.729,62 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 50,90% 41,95% 3,57% 3,57% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% OK: the Budget is in balance % Share of grant → SUMMARY OF THE BUDGET Total budget estimate (eligible costs) € 671.145,82 Grant requested from the EU € 468.306,44 Grant requested from the EU / Total eligible costs % 13/12/2013 69,78% The information in this Budget Estimate Form and in the Timetable is complete, true and verifiable. OK: the % of the requested amount of grant is within the eligible limit NOTE: Before the award decision, the Commission reserves the right to reduce and/or remove any costs if deemed unreasonable, unjustified and contrary to sound financial management SWING Final Meeting | CNIT - Pisa, Italy Name of Authorised signatory: Prof domenico Giardini Position: President Signature: Date : 14 Partner members Consiglio Nazionale universitario per le Telecomunicazioni 13/12/2013 SWING Final Meeting | CNIT - Pisa, Italy Enzo Dalle Mese Fabrizio Berizzi Alessandro Andreadis Andrea Abrardo Annalisa Saverino Davide Adami Fabrizio Cuccoli Francesco Sermi Giovanni Dore Luca Sanguinetti Marco Moretti Michele Morelli Amerigo Capria Marco Martorella Giovanna Zanello Simeon Kamdem Kuiteing 15 Partner members Anna Belehaki Ioanna Tsagouri National Observatory of Athens David Altadill Estefania Blanch Observatori de l’Ebre 13/12/2013 SWING Final Meeting | CNIT - Pisa, Italy 16 Partner members Istituto Nazionale di Geofisica e Vulcanologia 13/12/2013 SWING Final Meeting | CNIT - Pisa, Italy Cesidio Bianchi James Arokiasamy Baskaradas Antonio Meloni Irene Fiorucci Valentina Orlandi Alessandro Settimi Adriano Azzarone Bruno Zolesi 17 Website Home page screenshot of the SWING website at http://swing.rm.ingv.it 13/12/2013 SWING Final Meeting | CNIT - Pisa, Italy 18 Conclusion Thanks for your attention! 13/12/2013 SWING Final Meeting | CNIT - Pisa, Italy 19