CHANTI Update and High rate effects Fabio Ambrosino, Tiziana Capussela, Michele Corvino (B.Sc.), Domenico Di Filippo, Paolo Massarotti, Marco Mirra, Marco Napolitano, Giulio Saracino 1 Domenico Di Filippo CHANTI Status 2 100% of bars to produce 6 additional stations completed We need ~1 month to finish bar characterization Station assembling will start in ~ 1 month. It will take ~1 week per station. small vessel 90% completed in Napoli Mechanical Workshop. Assembly & welding of the full two vessels system two expected Domenico Di Filippo DCS A draft version of DCS specification for the CHANTI is ready and will be in EDMS by end of the week. Starting the next week I will be at CERN working on the DCS software. 3 Domenico Di Filippo High rate efficiency estimation We expect a mean rate of about 500 kHz on a single CHANTI bar (see Marco Mirra talk at software meeting). In order to get an estimation of the high rate behavior of the CHANTI electronic we use BTF data taken last summer (analysis performed in Michele Corvino B.Sc. Thesis work) Flash ADC Beam: 575 MeV eRate: O(Hz) Multiplicity: O(1) 4 e- beam Tag1 5 Bar CHANTI prototype. 2 channel instrumented. Tag2 Domenico Di Filippo Emulating high rate with BTF data Event # Some events present two distinct peaks (they are not particle of same burst because there are about 20 ns between them). Restricting our analysis to these kind of event we can emulate high rates Peak delay (us) 5 Domenico Di Filippo Efficiency on the 2nd peak 1st peak revelation efficiency; it is due to acceptance. 0.924 Dead time < 60 ns. We (conservatively) estimate an inefficiency of about 2%. Peak Delay (us) 6 Domenico Di Filippo Tot Board CAEN bus over USB (LVDS over HD cable) Arbitrary Waveform Generator HPTDC Tot board calibration setup (trigger) VME Bus ( Thanks to Frascati and F.Gonnella for the TDC controlling software ) PC (Linux) 7 Domenico Di Filippo Tot board calibration strategy (base-Tot)*slope = Th_trail (base-Tot)*slope = Th_lead Trail threshold Lead threshold We first add a stable part to the signal to not stress the electronic 8 100 ns 100 ns 147 mV Domenico Di Filippo Threshold calibration Trail Threshold Lead Threshold Threshold (DAC count) 9 Domenico Di Filippo Hysteresis Hysteresis Reproducibility Threshold (DAC count) 10 Domenico Di Filippo Signal width dependance The CHANTI signal have not the flat region, so we want to check the ToT behavior in more realistic condition width Trail Threshold Lead Threshold 100 ns There is an unexpected width behavior. Width (ns) 11 Domenico Di Filippo DC cut Looking at the Tot 4-channel analog adder, it seem to be there a sensible DC cut. Big (in charge) signals get a (positive) offset, so we get a wrong threshold estimation. This could be a problem in high rate environment because the signal mean charge could sensibly differs from zero. 12 Domenico Di Filippo Threshold (mV) DC cut effect on CHANTI We expect a ~500kHz rate i.e. 2000 ns period. 50 ns Trail Threshold Lead Threshold 100 ns CHANTI working point at ~6000 However we use a signal with 3x the real signal charge, so it is comparable with 6000 ns with real signals. Period (ns) So, this effect should be under control. More (direct) test soon... 13 Domenico Di Filippo